Build or Buy a Factory in Malaysia? Cost, Approvals, Timeline and Financing in Rawang, Serendah and Shah Alam

Written by , PEA 1478 · Published · Updated · Buying a factory or industrial land

Short answer

Buy a completed factory when you need to start production within months and a standard building fits; build on industrial land when you need a large or special plant and can wait. In Selangor a medium category OSC application takes 57 to 99 days, and TNB needs 3 to 12 months for 400V supply with a substation.

A cleared industrial plot with the steel frame of a new factory and a crane, next to a finished detached factory with green hills behind.
Illustrative image

Key Takeaways

  • Buying is faster; building gives you the plant you designed. A completed factory with its Certificate of Completion and Compliance (CCC) and power already connected can run soon after the sale completes. A new build first has to pass council approval, construction, the TNB connection and the CCC.
  • Land is the cheaper part in the north. JPPH-registered transactions put industrial land at RM57 psf of land in Rawang & Kundang and RM37 psf of land in Serendah, against RM210 psf of land in Shah Alam, where only 6 industrial land deals were registered in 24 months.
  • Approval times are written down. The OSC 3.0 Plus manual sets 57 to 99 days for a medium category simultaneous application and 42 to 98 days for the small category. MPHS, the council for Serendah, Bukit Beruntung and Batang Kali, promises a decision on simultaneous applications within 99 days of receipt.
  • Power is often the longest wait. TNB's supply handbook gives a typical lead time of 3 to 12 months for 400V supply with a substation and 6 to 12 months for 11kV, provided council approvals are not delayed.
  • The money works differently. Banks lend on completed industrial property and on vacant land, and MIDF's soft financing for manufacturers lists commercial property with tenures up to 25 years. A self-build needs the land loan and the construction money planned together, before you sign for the land.

How do land and built factory prices compare in Rawang, Serendah and Shah Alam?

When a client asks me whether to build or buy, I start with what the market has actually paid for each in the town they want. The figures below are JPPH-registered transactions for the 24 months to August 2026, as aggregated on FactoryHub's industrial transactions page. Every price per sq ft here is per sq ft of land, for factories as well as vacant land.

Area Industrial land Detached factory Semi-detached factory
Rawang & Kundang RM57 psf of land, 116 deals RM237 psf of land, median RM6.92 million on 26,215 sq ft of land, 16 deals RM380 psf of land, median RM4.3 million on 12,561 sq ft of land, 129 deals
Serendah RM37 psf of land, 72 deals RM166 psf of land, median RM8.65 million on 49,744 sq ft of land, 8 deals RM213 psf of land, median RM3.16 million on 10,506 sq ft of land, 28 deals
Shah Alam RM210 psf of land, 6 deals RM335 psf of land, median RM16 million on 67,901 sq ft of land, 20 deals RM514 psf of land, median RM5.92 million on 10,779 sq ft of land, 66 deals

Two things stand out. First, the gap between the land column and the factory columns is what buyers paid for a building that already stands with its approvals, mixed with differences in age, size and location. It is not a construction cost, and I never use it as one. Second, the deal counts show where each route is practical. In Shah Alam only 6 vacant industrial lots changed hands in the registered data, at a median of RM20.77 million, so most buyers there end up with a built factory. In Rawang and Serendah vacant industrial land trades often enough (116 and 72 registered deals) for building to be a real option, and the median land deal was RM2.6 million in Rawang & Kundang and RM2.47 million in Serendah.

The cost of the building itself has to come from a quantity surveyor pricing your design: earthworks, piling, structure, roof, floor slab, mechanical and electrical works, fire protection, a TNB substation if your load needs one, roads, drains and consultants' fees. Material prices move every month. The Department of Statistics publishes a building materials cost index monthly, and its October 2026 release came out on 10 November 2026, so ask the QS which month's rates the estimate uses.

How much factory can you build on an industrial lot in Selangor?

This decides whether a piece of land works at all. The Selangor planning standards manual, third edition (2016) sets these standards for detached and semi-detached factories (IND2):

  • Minimum site: 0.20 hectare (0.5 acre) for a small detached factory, 0.4 hectare (1 acre) for a medium to large one, and 60' x 132' for a semi-detached factory.
  • Plinth area: 60% of the site. Up to 30% of the gross floor area can be office.
  • Setbacks: 40' (12.2m) facing the road, 25' (7.6m) at the sides and rear, and 40' (12.2m) on a side facing a road, with a 66' (20.1m) service road.
  • Lorry parking: 1 bay per 10,000 sq ft of gross floor area, or at least 2.
  • Landscape: at least 5% of the site, plus 10' (3.1m) of perimeter planting.

On a 1-acre lot of 43,560 sq ft, a 60% plinth area is about 26,136 sq ft of ground floor before the setbacks are drawn in. Selangor approved its new planning standards for 2025 on 7 November 2025 and confirmed them on 12 November 2025, so ask the architect to check these figures against the 2025 edition and the local plan before you agree a price for the land. For how plot ratio caps the total floor area across several storeys, FactoryHub has a separate explainer on plot ratio.

Which approvals does a new factory need, and which council gives them?

Before anything goes to the council, the title has to be right: the land use category should read industry, and an agricultural title needs conversion first. I cover that step in buying industrial land in Serendah or Batang Kali.

The council follows the mukim on the title, not the town name on a listing:

  • Rawang and Kundang: Majlis Perbandaran Selayang (MPS), whose area covers Mukim Rawang, Mukim Batu and part of Mukim Setapak.
  • Serendah, Bukit Beruntung, Sungai Choh and Batang Kali: Majlis Perbandaran Hulu Selangor (MPHS).
  • Shah Alam: Majlis Bandaraya Shah Alam (MBSA), which takes applications through OSC 3 Plus Online.

All three work through a One Stop Centre (OSC). Under the OSC 3.0 Plus manual, your architect or engineer, as the principal submitting person, can file the planning permission (Kebenaran Merancang) together with the building plan, earthworks plan, road and drainage plan, landscape plan and the other plans as one simultaneous application. After approval the manual sets out the sequence:

  1. Building work has to start within 12 months of the building plan approval, with a notice to start work filed with the council.
  2. The OSC monitors the site and records it if work is suspended for more than three consecutive months (subsection 70(9), Act 133).
  3. At the end, the water authority, TNB, the council's engineering department and JKR (where a JKR road is involved) give their clearances.
  4. The principal submitting person certifies the CCC (Form F) and deposits it with the council.

Power runs alongside the approvals. TNB's Electricity Supply Application Handbook asks applicants to apply early and keep TNB informed so its supply project matches your construction. If your load needs a compact substation, read what that involves in Rawang and Serendah.

How long does building take compared with buying?

The approval windows are published. The OSC 3.0 Plus manual's table of simultaneous applications gives:

Simultaneous application Time set in the manual
Small category planning permission with plans 42 to 98 days
Medium category planning permission with plans 57 to 99 days
Large category B planning permission with plans 71 to 115 days
Large category A planning permission with plans up to 300 days
Plans only, where planning permission exists 50 to 92 days

The manual's medium category includes development that follows the land's express conditions or an approved layout plan; your architect will confirm which category your lot falls into. MPHS's customer charter promises a decision on simultaneous applications within 99 days of receipt.

On top of that come the design work before submission, the contractor's construction programme, and TNB: less than 3 months for 400V without a substation, 3 to 12 months for 400V with one, and 6 to 12 months for 11kV, each provided the council approvals are not delayed. None of these clocks starts until the land is yours or the owner consents to the application.

Buying a completed factory skips all of that. The time goes into the bank's approval, the state's consent where the title is leasehold or restricted (see freehold vs leasehold factory), and the completion period you agree in the sale and purchase agreement.

How do the banks finance building versus buying?

For a completed factory, banks lend against the property. CIMB's SME Biz Property Financing, for example, accepts commercial, industrial and residential property and vacant land, with financing up to RM20,000,000. MBSB Bank's commercial property financing covers the purchase of commercial and industrial properties, completed or under construction.

For a self-build, the money comes in two parts: the land, which the lender values as vacant industrial land, and the construction, which is paid out as the building goes up. Before you sign for the land, ask the bank in writing how it will release the construction portion, which certificates it needs at each stage, and whether one facility covers both parts. If renting is still an option, my guide to renting or buying a factory compares rent with loan instalments.

Manufacturers can also look at MIDF's Soft Financing Scheme for Automation and Modernisation (SFSAM). It is open to manufacturing and manufacturing related services companies registered with SSM, at least 51% Malaysian owned and in operation for at least 2 years, with financing from RM50,000 to RM20 million at 4% a year on monthly rest for SMEs (5% for non-SMEs). Commercial property is one of its financing items, with a tenure of up to 25 years. Confirm with MIDF whether your purchase or construction qualifies. To compare instalments for either route, use FactoryHub's loan calculator.

When does building make sense, and when does buying?

Your situation Usually points to
Production has to start within months Buying a completed factory with CCC and power in place
Standard floor, normal power, ordinary loading Buying; Rawang has the deeper registered stock (129 semi-detached and 16 detached factory deals in 24 months)
Large floor plate, heavy floor loading, cranes or high clear height Building, on a plot sized for it
More power than existing units in the estate can take Building, with TNB applied for from the start
The plant must be in Shah Alam Usually buying, since vacant industrial land rarely trades there
Lower land cost and room to expand Building in Serendah, where registered industrial land is RM37 psf of land

In practice the deciding question is time more than money. If the business cannot wait through approvals, construction and the power connection, a completed factory in Rawang or Shah Alam is the practical route. If it can, land in Serendah or Rawang gives you a building designed around the process. Built units and land on this site are listed under factories and industrial land.

What do I check before a client commits to either route?

For land, I check the title (land use category, express condition, restriction in interest, encumbrances), which council and mukim it falls under, whether a 40-footer can reach the gate, where TNB would want a substation, drainage and flood history, and whether the plot can hold the floor area the client needs once the 60% plinth area and the setbacks are applied. I go through each of these checks in my guide to buying industrial land to build a factory.

For a built factory, I ask for the CCC or CF and the approved building plans, then compare them with what stands on site, because a building can differ from its approved plans. MPS even runs a compliance and enforcement programme for factories built without permission, with its own planning application forms. I also check the TNB supply and meter rating, the fire certificate where the building needs one, and the lease years left on a leasehold title.

  • How large a warehouse can be built on 2 acres of industrial land? Roughly double what fits on 1 acre, where the setbacks leave room for a single-storey factory of about 22,800 sq ft, or 10,300 sq ft if you need a trailer yard.
  • What should be considered in factory building design? Floors, walls, drains and air have to meet the 2009 hygiene rules, and the design also has to cover MeSTI, GMP, HACCP and halal requirements, zoning and licences.
  • What is a Built-to-Suit Factory? It is a factory constructed on land to the tenant's specifications, instead of buying one that is already built.
  • Ready-Built vs Built-to-Suit Factory: what's the difference? A ready-built factory already stands and is bought or leased as it is, while a built-to-suit factory is constructed on land to the occupier's specifications.

These questions are answered in full on FactoryHub.

If you are weighing both routes in Rawang, Serendah or Shah Alam, WhatsApp Jason Low, Probationary Estate Agent PEA 1478 with CID Realtors Sdn Bhd, on +60 12-288 1834.

Questions people ask

01Is it cheaper to build a factory than to buy one in Rawang or Serendah?+

Registered land costs less per sq ft of land than registered built factories: RM57 psf of land for industrial land in Rawang & Kundang against RM237 psf of land for detached factories, and RM37 against RM166 in Serendah. That gap is not a construction cost, so have a quantity surveyor price your own design before comparing. Add consultants, approvals, TNB works and the months you wait.

02How long does council approval take for a new factory in Selangor?+

The OSC 3.0 Plus manual sets 57 to 99 days for a medium category simultaneous application, 42 to 98 days for the small category and up to 300 days for large category A. MPHS, the council for Serendah, Bukit Beruntung and Batang Kali, promises a decision on simultaneous applications within 99 days of receipt. Design work before submission and construction come on top.

03How much of an industrial lot can the factory cover in Selangor?+

The Selangor planning standards manual (third edition, 2016) allows a plinth area of 60% for detached and semi-detached factories, with setbacks of 40 feet facing the road and 25 feet at the sides and rear. Selangor approved new planning standards for 2025 in November 2025, so have your architect confirm the current figures with the council.

04Can I get a loan to build a factory on my own land?+

Yes, but plan it as two parts: the vacant land and the construction, which is paid out as the building goes up. Ask the bank in writing how and when it releases the construction money and which certificates it needs. CIMB SME Biz Property Financing, for example, accepts vacant land and goes up to RM20,000,000, and manufacturers can ask MIDF about SFSAM.

05How long does TNB take to connect a new factory?+

TNB's Electricity Supply Application Handbook gives typical lead times of less than 3 months for 400V without a substation, 3 to 12 months for 400V with a substation and 6 to 12 months for 11kV, provided council approvals are not delayed. Apply as soon as your load is known and keep TNB updated on the construction programme.

06When is buying a ready-built factory the better choice?+

When production has to start within months, your process fits a standard building and the unit already has its CCC and enough power. In Shah Alam it is often the only practical route, because only 6 industrial land deals were registered there in the 24 months to August 2026.

07What government approvals are needed to build a factory in Rawang or Serendah?+

You need planning permission and building plan approval from the local council, submitted through its One Stop Centre together with the earthworks, road and drainage and landscape plans. Rawang and Kundang come under Majlis Perbandaran Selayang (MPS), while Serendah, Bukit Beruntung, Sungai Choh and Batang Kali come under Majlis Perbandaran Hulu Selangor (MPHS). Before any of that, the title has to show industry as its land use. When the building is finished, TNB, the water authority and the council's engineering department give their clearances before the CCC can be certified.

08Is it more cost-effective to rent a ready-built factory in Rawang or Serendah, or to rent a bare unit and renovate it yourself?+

Renting a ready-built factory usually works out cheaper overall when the unit already suits your process, because whatever you spend renovating a rented unit stays behind when the lease ends. In Rawang, Serendah and Kundang, check the CCC, the approved building plans and the TNB supply before you sign, and confirm the land use category on the title reads industry. A bare unit may need MPHS or MPS approval for the works, so agree with the landlord, in writing, who applies and who pays.

Sources

  1. PLANMalaysia Selangor: Manual Garis Panduan dan Piawaian Perancangan Negeri Selangor, Edisi Ketiga (2016), IND2 factory standards
  2. PLANMalaysia Selangor: Garis Panduan dan Piawaian Perancangan Negeri Selangor 2025 (approval dates)
  3. KPKT: Manual OSC 3.0 Plus, second printing June 2020 (simultaneous application timelines, start of work, CCC)
  4. MPHS: customer charter (decision on simultaneous applications within 99 days)
  5. MPS: administrative area (Mukim Rawang, Mukim Batu, part of Mukim Setapak)
  6. MPS: OSC forms, including the compliance and enforcement programme for factories without permission
  7. KPKT OSC 3 Plus Online: Majlis Bandaraya Shah Alam portal
  8. TNB: Electricity Supply Application Handbook (ESAH 3.1), supply project lead times
  9. DOSM: Special Release for Building and Structural Works, October 2026
  10. CIMB: SME Biz Property Financing
  11. MBSB Bank: Commercial Property Financing
  12. MIDF: Soft Financing Scheme for Automation and Modernisation (SFSAM)
  13. FactoryHub: JPPH-registered industrial transactions

Units on the market nearby

More on buying a factory or industrial land

All guides: Buying a factory or industrial land →