Bomba Fire Certificate for a Factory or Warehouse in Rawang, Serendah and Shah Alam: Who Needs One and What I Check
A factory or warehouse in Rawang, Serendah or Shah Alam needs a Bomba fire certificate only if it is a designated premises: a sprinklered factory of 2,000 m² (about 21,528 sq ft) or more, any factory with a hazardous process, or sprinklered storage of 1,000 m² or 7,000 m³. A factory certificate costs RM1,000, then RM500 a year.
Key Takeaways
- Only designated premises need a fire certificate. For a factory the line is 2,000 square metres (about 21,528 sq ft) of total floor area fitted with an automatic sprinkler system, whether one storey or more, and any factory with a hazardous process. Storage is designated at 1,000 square metres or 7,000 cubic metres with sprinklers (schedule under P.U.(A) 289/2020, as reproduced by Palcon).
- It is a yearly certificate. The Act makes it renewable annually, and the renewal must be filed at least 30 days before expiry. After the expiry date you cannot renew: you start a fresh application (Fire Services (Fire Certificate) Regulations 2001).
- The fee depends on the use. A factory pays RM1,000 for a new certificate and RM500 to renew; storage pays RM500 and RM250.
- The owner carries the offence, the lease should carry the work. Where no certificate is in force, the owner of the designated premises commits an offence (Fire Services Act 1988, section 33), yet the applicant can be the owner or the occupier, depending on who maintains the fire installation.
- Racking, mezzanines and new processes can be a "material change". The occupier must tell Bomba before the work starts.
Which factories and warehouses need a Bomba fire certificate?
Section 28 of the Fire Services Act 1988 says every designated premises shall require a fire certificate, and that the certificate is renewable annually (Act 341). Which premises count as designated is set by an order under section 27. The current schedule was substituted in 2020 by P.U.(A) 289/2020, and the 2020 changes to the fire certificate rules took effect on 1 October 2020 (Skrine, November 2020).
These are the rows that matter to an industrial buyer or tenant in Rawang, Serendah or Shah Alam:
| Premises | Designated when | Roughly, in imperial units |
|---|---|---|
| Factory, 1 storey | 2,000 m² and over of total floor area, fitted with automatic sprinklers | about 21,528 sq ft of floor |
| Factory, 2 storeys and above | 2,000 m² and over of total floor area, fitted with automatic sprinklers | about 21,528 sq ft of floor |
| Factory, special structure | a hazardous process | any size |
| Storage and general | 1,000 m² and over of total floor area, or 7,000 m³ and over, fitted with automatic sprinklers | about 10,764 sq ft, or about 247,200 cubic feet |
Source: Palcon's copy of the 2020 schedule.
To put the threshold next to what actually changes hands here: in the JPPH-registered deals for the 24 months to August 2026, the median terrace factory sat on 2,384 sq ft of land in Rawang and Kundang and 2,002 sq ft in Serendah, while the median detached factory sat on 26,215 sq ft of land in Rawang and Kundang, 49,744 sq ft in Serendah and 67,901 sq ft in Shah Alam. The median warehouse in Rawang and Kundang sat on 49,175 sq ft of land (Rawang and Kundang transactions, Serendah, Shah Alam). Land is not floor area, but the pattern holds: a terrace unit sits far below the line, and the question becomes real with detached factories and warehouses.
Two phrases in the schedule deserve attention. First, the factory and storage rows catch buildings fitted with automatic sprinklers, so on a viewing the sprinkler tank, the pump room and the heads under the roof tell me early that the building may be designated. Second, "hazardous process" has no size limit. If your work involves solvents, spray painting, flammable gas or similar, ask Bomba about your position before you sign, not after you move in.
What does the fire certificate prove, and how is it different from the CCC?
The CCC, or the older CF that the CCC replaced from 12 April 2007 (Malaysian Bar), confirms that the building was completed to its approved plans and can be occupied. It is issued once.
The fire certificate is about the building in use, year by year. The form in the regulations certifies that the premises comply with the requirements on fire-fighting equipment or fire safety installation, that a fire safety organization has been set up, and that a Fire and Emergency Response Plan and a Fire Safety Report have been prepared. It carries a "valid from ... to" period (Second Schedule of the regulations). Bomba inspects before issuing it, and if the facilities are not adequate it serves a notice listing what must be done first (Act 341, section 29).
The two papers are linked. The application form asks for the local authority and the Fire and Rescue Department reference numbers and approval dates of the building's approved plans (First Schedule). So when a building has been extended or partitioned since its CCC, I ask whether those works also went through Bomba, because the fire certificate application points back to the approved plans.
Who applies for and renews it: the owner or the tenant?
The Act names the applicant as the owner, the occupier or the person having overall management of the premises (section 29(6)). For a landed building, the regulations decide it by who looks after the fire installation: the owner applies when the owner owns or maintains the fire-fighting equipment, the occupier applies when the occupier maintains it, and the occupier and the other party apply jointly when it is shared (regulation 1B). Section 33, on the other hand, makes the owner guilty of an offence when a designated premises has no certificate in force.
Because of that split, I want the tenancy agreement to answer these in plain words:
- who services the sprinklers, fire alarm, hose reels and extinguishers, and who pays for it;
- who files the renewal and pays the renewal fee;
- who staffs the fire safety organization, which must have one fire safety manager and at least three fire safety officers certified by the Director General (regulation 6B);
- who tells Bomba within 14 days when one of them changes, and appoints a replacement within 30 days of a resignation (regulation 6D);
- who pays if Bomba asks for upgrades at renewal.
My guide on screening a tenant and protecting the landlord in the lease covers the other clauses I look at.
What do I check on a viewing in Rawang, Serendah or Shah Alam?
When a client shortlists a detached factory or a warehouse, I go through the fire papers before we talk about price:
- Is the building likely to be designated? The floor area on the approved plan, whether it has sprinklers, and what the client will make or store there.
- The certificate on the wall. The holder must exhibit it in a conspicuous position at the premises (regulation 6). I read the validity dates and check that the premises named on it is the unit we are standing in.
- The papers behind it. The CCC or CF, the approved plans, the certificate of establishment of the fire safety organization and the latest Fire Safety Report, because the application and every renewal need them (regulations 2 and 4).
- Who holds it. A fire certificate is non-transferable, although the Director General may authorize a transfer, for example when the holder company is liquidated or a receiver is appointed (regulation 3). When a factory is sold, or a new tenant takes over the installation, I ask early who will hold the next certificate.
- The expiry date against our timetable. If the certificate runs out around the handover, someone must file the renewal at least 30 days before expiry, or the next holder faces a fresh application.
- The activity. Whether the client's process could count as hazardous, and where it sits in Ms Teh's light, medium and heavy industry guide.
For the wider list (title, CCC, power, access), see what I check before renting a factory in Rawang. Small terrace units are a different case, covered in my terrace factory guide for Bukit Beruntung.
How does renewal work, and what does it cost?
The renewal application goes in on the form in the Third Schedule, at least 30 days before the expiry date, with particulars of any change to the premises and a copy of the Fire Safety Report. Bomba may renew it with or without conditions, or refuse (regulation 4). The fees are fixed in the Sixth Schedule:
| Use | New certificate | Renewal |
|---|---|---|
| Factory | RM1,000 | RM500 |
| Storage and other premises | RM500 | RM250 |
Where a premises has more than one use, the highest fee applies. A lost or destroyed certificate must be reported within 14 days, with a RM50 fee for the replacement (regulation 5).
A missed window costs more than the fee difference. A factory that lets its certificate lapse goes back to a full application, with the inspection and the RM1,000 fee, and the fire safety organization still has to run at least one fire drill and one fire safety course for the occupants every year (regulation 6E).
Which changes need Bomba before you start the work?
Section 32(2) of the Act says that when the occupier of a designated premises proposes a material change while a certificate is in force, he must give notice to the Director General before the work begins, and starting without notice is an offence (Act 341). The regulations define a material change as any change affecting the fire-fighting equipment or fire safety installation in relation to the use of the premises (regulation 1B(3)). Bomba can then say what steps are needed and amend the certificate, or issue a new one on payment of the fee.
Whether a change counts is Bomba's decision, so I treat these as questions for the client's fire consultant before a contractor is booked: taller racking under existing sprinklers, a mezzanine or office partitions, a fire exit that the tenant wants to lock for security, a new spray booth or solvent store. If you are building or extending, my note on contractor's all risk cover and when fire insurance starts explains the insurance side.
What do the councils in Rawang, Hulu Selangor and Shah Alam ask for?
Even a factory too small to be designated meets Bomba through its business licence:
- Rawang (Majlis Perbandaran Selayang). MPS licenses premises that meet Bomba's safety requirements and have planning approval, approved building plans and a CF or TCF, and asks for the receipt for the fire extinguisher inspection (Bomba) when you renew (MPS licence conditions).
- Serendah and Bukit Beruntung (Majlis Perbandaran Hulu Selangor). The MPHS composite licence form lists approval from the Fire and Rescue Department among the documents for an industrial or manufacturing licence, asks for the fire extinguisher purchase sticker with the premises address and not expired, and makes in-date extinguishers a licence condition (MPHS form).
- Shah Alam (Majlis Bandaraya Shah Alam). The MBSA composite licence asks for a copy of the CCC or CF, and the processing fee for an industrial application is RM100 (MBSA).
You will find more on each place on the Rawang, Serendah and Shah Alam pages, and current units on the warehouse page.
To have the fire papers of a factory or warehouse in Rawang, Serendah or Shah Alam checked before you sign, WhatsApp Jason Low (Probationary Estate Agent PEA 1478, CID Realtors Sdn Bhd E(1) 1855) on +60 12-288 1834.
Questions people ask
01Where do I get a Bomba fire certificate for a factory in Selangor?+
You apply to the Fire and Rescue Department (Bomba) on the form set out in the Fire Services (Fire Certificate) Regulations 2001, which is addressed to the department's state office, so for Rawang, Serendah and Shah Alam that means Bomba Selangor. The application must come with the certificate of establishment of a fire safety organization, a Fire and Emergency Response Plan and a Fire Safety Report. Bomba inspects the premises before it issues the certificate.
02What is a Bomba certificate?+
It is the fire certificate, or Perakuan Bomba, issued under the Fire Services Act 1988 to a designated premises. It certifies that the fire-fighting equipment or fire safety installation complies, that a fire safety organization has been set up, and that the emergency plan and fire safety report have been prepared. It states a validity period and is renewed every year.
03Does a warehouse need a Bomba fire certificate?+
Only if it is designated. Under the schedule substituted by P.U.(A) 289/2020, storage premises are designated at 1,000 square metres (about 10,764 sq ft) or more of total floor area, or 7,000 cubic metres or more, fitted with an automatic sprinkler system. A smaller warehouse still has to meet the council's fire safety conditions for its business licence.
04How much is the fire certificate fee for a factory?+
Under the Sixth Schedule of the regulations, a factory pays RM1,000 for a new fire certificate and RM500 for a renewal. Storage and other premises pay RM500 and RM250, and a premises with more than one use pays the highest fee. Servicing the fire systems and preparing the reports are separate costs.
05What happens if a factory's fire certificate expires?+
The renewal has to be filed at least 30 days before the expiry date, and no renewal is allowed once the certificate has expired: the applicant must make a fresh application, with a new inspection and the new-certificate fee. While a designated premises has no certificate in force, its owner commits an offence under section 33 of the Fire Services Act 1988.
06Can a buyer or new tenant use the previous holder's fire certificate?+
A fire certificate is non-transferable under regulation 3 of the Fire Certificate Regulations, although the Director General may authorize a transfer, for example when the holder company is liquidated or a receiver is appointed. So when a factory is sold or a new tenant takes over the fire installation, agree early who will apply for the next certificate and when the current one expires.
07What should be done if a factory's fire protection system in Rawang does not meet Bomba requirements?+
Bomba will serve a notice listing the works that must be done before it issues a fire certificate, so the practical step is to bring in a fire consultant, carry out those works and ask Bomba to inspect again. Before any of that, check the approved plans and the CCC, because the application refers back to them. Where the business licence is affected, confirm what is needed with MPS in Rawang, MPHS in Serendah or MBSA in Shah Alam.
08Can a factory in Rawang or Serendah store hazardous chemicals?+
Yes, it can, but storing hazardous chemicals may make the factory a designated premises that needs a Bomba fire certificate whatever its floor area. The schedule under P.U.(A) 289/2020 treats any factory with a hazardous process as designated, with no size limit. Check the approved plans and CCC, inform Bomba before solvents or flammable gas go into storage, and confirm the licence conditions with MPS for Rawang or MPHS for Serendah.
Sources
- Laws of Malaysia: Fire Services Act 1988 (Act 341), Part V Fire Certificate, sections 27 to 36 (AGC reprint)
- Laws of Malaysia: Fire Services (Fire Certificate) Regulations 2001 [P.U.(A) 241/2001], reprint as at 1 April 2023 (applicant, renewal, exhibit, fire safety organization, Sixth Schedule fees)
- Palcon: Perakuan Bomba, schedule of designated premises substituted by P.U.(A) 289/2020
- Skrine: Fire Safety Requirements Enhanced (November 2020), 2020 amendments in force from 1 October 2020
- Majlis Perbandaran Selayang: licence application documents and approval conditions
- Majlis Perbandaran Hulu Selangor: composite premises licence application form and general conditions
- Majlis Bandaraya Shah Alam: Lesen Komposit (Perniagaan / Perindustrian)
- Malaysian Bar: Understanding the new CCC (CCC replaced the CFO from 12 April 2007)
- FactoryHub: Rawang and Kundang JPPH-registered factory and warehouse transactions
- FactoryHub: Serendah JPPH-registered factory transactions
- FactoryHub: Shah Alam JPPH-registered factory transactions
Units on the market nearby
Semi-D Factory for Rent in Saujana Teknologi Rawang, Rawang, 6,525 sq ft
RM 10,500/month
Semi-Detached Factory for Sale or Rent in Saujana Rawang, Rawang, 8,000 sq ft
RM 4,000,000 · RM 15,000/month
Detached Factory for Rent in Batu 17 Rawang, 9,000 sq ft
RM 21,000/month
More on licences, bomba and approvals
- Business Premise Licence for a Factory or Warehouse in Rawang, Serendah and Shah Alam: What MPS, MPHS and MBSA Ask For, Signboard Rules, Timelines and Refusals
- Light Industrial Factory, or Medium or Heavy? How Zoning Classes and Buffer Zones Work in Rawang, Serendah and Shah Alam, and How I Check a Unit
- Illegal Factory Extension in Rawang, Serendah or Shah Alam: What MPS, MPHS and MBSA Can Do and How to Make It Legal
- Factory Wastewater in Rawang, Serendah and Shah Alam: Industrial Effluent Regulations 2009, LUAS Licences and What I Check in the Building