Illegal Factory Extension in Rawang, Serendah or Shah Alam: What MPS, MPHS and MBSA Can Do and How to Make It Legal
A factory extension needs written approval from MPS, MPHS or MBSA before building. Without it, the council can fine and, after notice, order demolition; the add-on sits outside the CCC, the bank valuer may report it and fire cover on it can lapse. Regularising needs a PSP to submit as-built plans, often at ten times the plan fee.
Key Takeaways
- Every extension needs the council's written permission first. Section 70(1) of the Street, Drainage and Building Act 1974 says no one may erect a building without it, and section 70(16) counts an addition with new foundations, or a new or larger roof, as erecting a building. In my areas the council is MPS (Rawang, Kundang), MPHS (Serendah, Sungai Choh, Bukit Beruntung, Batang Kali) or MBSA (Shah Alam).
- The landowner carries the risk. Section 70(17) presumes the owner of the land built it, and section 72 lets the council serve its demolition notice on the landowner, so a buyer takes over the problem at completion.
- The CCC only covers what is on the approved plans. An add-on built later sits outside the original CCC or CF, and a bank valuer who knows of a breach of statutory requirements is expected to disclose it in the report.
- Fire cover can stop for the changed part. A standard Malaysian fire policy ceases to cover the affected property if the building is changed in a way that raises the fire risk and the insurer has not endorsed it.
- Regularising is possible but costs more than asking first. Selangor's building by-laws allow ten times the plan fee when work started before approval, and the Act sets five to twenty times when plans follow unauthorised work.
How do I spot an unapproved extension before I sign?
When a client shortlists a factory in Rawang, Serendah or Shah Alam, I ask the owner for three papers before we visit: the approved building plan, the CCC (Form F) or, for an older building, the CF, and the latest paid cukai pintu bill. Then I walk the unit with the plan in my hand. Add-ons tend to turn up in the same places:
- a roof or steel shed over the side or rear setback, often running to the boundary wall
- a loading bay canopy pushed out past the original roof line
- a mezzanine office or storage deck that is not on the floor plan
- an enclosed car porch, a guardhouse or a covered parking bay at the gate
- container cabins used as offices, canteens or rooms for workers
- brick partitions, or a party wall opened between two terrace units
- roof sheets of a newer colour or profile, or steel columns of a different size bolted to the old frame
I compare what I see with the floor area table on the plan. If the owner has lost the approved plan, the council keeps one. Under the First Schedule of the Selangor Uniform Building By-Laws, an approved plan can be inspected at the council for RM100 a set and copied for RM200 a set, and a copy needs the owner's written consent.
I also ask, plainly, whether the council has ever served a notice or a compound on the unit. The MPS form for factory add-ons asks for a copy of any notice or compound already issued, so these papers exist and an honest owner can show them.
The cukai pintu bill is a quiet clue. A bigger building usually means a bigger annual value, and in my cukai pintu guide I explain how a material change takes a holding outside Selangor's limit on revaluation increases. A bill that never moved while the building grew is worth a question.
What needs plan approval, and what can go on a simple permit?
Section 70(16) of the Act treats a person as erecting a building when they add to or alter an existing building in a way that involves new foundations, or a new, partly new or increased superstructure or roof on existing walls or foundations. Works done on the same building on two or more occasions within ten years may be added together. That catches nearly every factory extension I see.
The councils do allow small works on a permit instead of full plans:
- The MPS minor works form covers repairs such as doors, tiles, grilles, ceilings and roof repairs that do not change the original structure, and an awning of up to 4 feet without posts inside the owner's lot, for a RM100 processing fee and a RM5 sticker. The same form says any new structure, wall breaking or added floor area needs building plan approval through a qualified principal submitting person (PSP).
- The MPS internal partition permit covers gypsum board partitions of up to three rooms. In a factory, partitions in materials other than gypsum board or glass must go through a PSP and the One Stop Centre (OSC).
- MBSA issues temporary building permits for partitions and awnings on a standard plan within one working day of a paid receipt. Its licensing checklist adds that terrace, semi-detached and detached factories must send addition and alteration plans to the OSC for partitions, shed roofs and extra space at the front, side and rear.
What can MPS, MPHS or MBSA do about it?
The figures below are the maximums in the Attorney General's Chambers reprint of Act 133.
| Provision | What it covers | Maximum |
|---|---|---|
| s.70(11) | Altering a building without the council's prior written permission | Fine up to RM25,000, and a court order to alter or demolish |
| s.70(13) | Erecting a building against the Act or by-laws, or ignoring a council order | Fine up to RM50,000 or 3 years' jail or both, plus RM1,000 a day after conviction |
| s.72 | Notice to the landowner to stop or demolish | RM250 a day after the notice period runs out, and the council may demolish and recover its costs |
| s.73(3) | Letting an unauthorised building | Fine up to RM1,000 |
| s.73(2) | Selling a building one put up without approval | Up to 2 years' jail and a fine up to RM10,000 |
Before the council itself demolishes, section 72(6) gives the occupants at least 30 days' notice to vacate.
These powers are used in my areas. In September 2020 MPS served a notice on a machinery maintenance factory near Sungai Gong, Rawang, for erecting a building without permission and gave it three days to produce documents before demolition, while the Gombak land office served a Form 7A notice for breaching the land use condition, as Sinar Harian reported. The MPHS 2025 annual report records 1,277 notices, 284 compounds and 77 demolition operations by its building department, across all types of buildings in Hulu Selangor.
There is a licensing side as well. MBSA's licence checklist asks for the CF or CCC, the current floor plan and the approval letters for any partition, awning or addition, so an unapproved add-on can hold up a tenant's premises licence.
Does an unapproved extension affect the bank loan?
It can. Under the Board of Valuers' Malaysian Valuation Standards on inspection, the valuer must inspect the building inside and out, and where the valuer is aware of any breach of statutory requirements it should be disclosed in the report. The standard on reports also asks for planning details and the building plans. A valuer standing in a factory that is bigger than its approved plan is likely to say so.
How the bank treats that finding is its own credit decision, and I do not guess it for a client. What I do is ask the buyer to raise the extension with the banker before the offer is signed, and to work out the loan on the approved floor area only, for example with FactoryHub's mortgage calculator. I also check the asking price against registered sales on FactoryHub's transactions page, where JPPH sale prices are per square foot of land, so the buyer does not pay extra for floor area that has no approval.
What happens to fire insurance and the CCC?
The CCC is tied to the approved plans. Under by-law 25 of the Selangor by-laws the PSP certifies that the building was built in accordance with the Act, the by-laws and the approved plans, so an extension added afterwards is not covered by it. MBSA still issues a CF only for plans submitted before the CCC system began on 12 April 2007; the same point applies to those older factories. Section 70(27)(f) of the Act makes it an offence to occupy, or let someone occupy, a building or any part of it without a CCC. Tenants looking at such a unit can read my guide to renting a factory without a CCC or CF.
Fire insurance has its own trap. In a typical Malaysian fire policy, such as QBE's wording, cover on the property affected ceases if circumstances affecting the building are changed in a way that increases the risk of fire damage, unless the insurer agrees by endorsement before any loss. The same policy applies average when the property is worth more than the sum insured, so an extension that adds value without a higher sum insured reduces every claim in proportion. For business policies the wording also cites the duty of disclosure under Schedule 9 of the Financial Services Act 2013 and asks the insured to tell the insurer when information given has changed.
If the extension takes the floor area past the line for a designated premises, a fire certificate may be needed too. My Bomba fire certificate guide sets out the thresholds.
How does regularisation work at MPS, MPHS and MBSA?
Regularising means putting the built work through the council as an application, with drawings that show what is really on site. These are the steps I see in the councils' own forms:
- Appoint a PSP. An architect, engineer or registered building draughtsman prepares as-built drawings. MPS wants new work coloured red and demolished work in blue dashed lines, structural plans and calculations or the engineer's letter on stability, and site photos certified by the PSP and taken within 7 days of submission.
- Gather the owner's papers. Title, paid assessment bill, CCC or CF, a statutory declaration by the owner, any Bomba comment, and for an MPS as-built application the notice or compound and a no-objection letter from the neighbours.
- Pay the enhanced fee. Selangor's plan fee is RM14 per 9 square metres of ground floor, with a minimum of RM140, and half for alterations. Paragraph 17 of the First Schedule allows ten times the fee where work began before approval, and says that paying it does not stop a prosecution. Section 70(14) of the Act separately sets five to twenty times the prescribed fee when plans are submitted after unauthorised work and no case has been filed. By my own arithmetic, a 300 square metre single-storey extension is 34 units of 9 square metres: RM476 at the ground floor rate, RM4,760 at ten times, before any consultant's fees. MPHS's minor works checklist warns of the same tenfold charge.
- Pick the right route. An open, temporary awning can sit on an annual permit. Under MPS form JB-B04(A), in force from 1 February 2026, it must be an open awning in metal deck and steel tension, with minimum clearances from gutter to boundary of 10 feet in front and 3 feet at the side and rear for detached and semi-detached factories. The fee is RM10 per 9 square metres with a minimum of RM300, plus a deposit of RM750 to RM1,500. MPHS handled 106 as-built temporary structure permits in 2025 and its customer charter approves temporary permits within 14 working days. These permits are renewed every year. Permanent work goes through the OSC as an addition and alteration plan and ends with the PSP's CCC; MBSA's charter has its OSC recommendation ready within 7 working days.
- Check planning. If the add-on breaks setbacks, plot coverage or the approved use, a building plan alone may not be enough. The MPS checklist for additions asks for the planning permission letter where relevant, and MPS has a separate form to amend a planning permission. Work the rules cannot accept has to come down.
Is this the same as Selangor's kilang haram programme?
No. Selangor's programme for factories without permission (Kilang Tanpa Kebenaran, KTK) deals with whole factories running without planning approval. Utusan reported in April 2026 that the state runs a KTK compliance and enforcement programme for 2025 to 2027, and that 19 of 4,170 KTK had refused to follow it. MPS publishes separate KTK forms for temporary building permits, and MBSA has a licence checklist for KTK factories without a CF. A factory on that programme can hold a temporary permit and a licence, but that is not an approved plan and a CCC, and I tell buyers to read it that way.
What I put in the offer or tenancy when there is an extension
When a unit has add-ons, I list each structure in writing and ask the owner which ones are approved. For a sale, I ask the buyer's lawyer to cover who regularises or removes the unapproved parts and by when, a warranty that no council notice is outstanding, and what happens if a notice arrives before completion. For a tenancy, the landlord is the one exposed under section 73(3), and the MPS forms let a tenant apply only with the owner's consent letter, so I ask the landlord to fix it first or to state it in the agreement. For older terrace units I keep a separate checklist for Bukit Beruntung.
If you want a second pair of eyes on a factory with an extension in Rawang, Serendah or Shah Alam, WhatsApp Jason Low on +60 12-288 1834.
Questions people ask
01Can I buy a factory in Rawang or Shah Alam that has an unapproved extension?+
You can, but once the sale completes you are the landowner the council serves under section 72 of Act 133, and the add-on stays outside the CCC. Ask for the approved plan and CCC or CF, list every add-on, and have the sale agreement say who regularises or removes the unapproved parts before completion. Raise it with your banker before you sign the offer.
02How much is the fine for an illegal factory extension in Selangor?+
Under Act 133, altering a building without permission carries a fine of up to RM25,000 and a court order to alter or demolish. Erecting a building against the Act or ignoring a council order carries up to RM50,000 or three years in jail or both, plus RM1,000 a day after conviction. Ignoring a demolition notice under section 72 costs RM250 a day, and the council can demolish and recover its costs.
03Can an illegal factory extension be approved later?+
Often, yes. A principal submitting person files as-built plans with the council, and Selangor's by-laws allow ten times the normal plan fee where work began before approval, while the Act sets five to twenty times. MPS also has an annual temporary permit for open awnings on factories. Work that breaks setbacks, plot coverage or the approved use may not be approvable and then has to be removed.
04Will the bank finance a factory with an unapproved extension?+
That is the bank's own credit decision. The Malaysian Valuation Standards expect the valuer to disclose any breach of statutory requirements they know of, and the report includes the building plans, so the extension is likely to be noted. Work out the loan on the approved floor area only and tell the banker about the extension before you commit.
05Does the CCC cover renovations done after it was issued?+
No. Under by-law 25 of the Selangor by-laws, the principal submitting person certifies the building against the approved plans, so later additions are outside that CCC. Permanent additions need their own approved plans and a new CCC from the PSP. Section 70(27)(f) of Act 133 makes occupying a building or part of it without a CCC an offence.
06Does fire insurance cover an unapproved factory extension?+
It may not. A standard Malaysian fire policy says cover on the affected property ceases if the building is changed in a way that increases the fire risk, unless the insurer endorses the change before any loss. The average clause also cuts claims in proportion if the property is worth more than the sum insured, so tell your insurer about the extension and review the sum insured.
Sources
- Laws of Malaysia: Street, Drainage and Building Act 1974 (Act 133), sections 70, 72 and 73 (AGC reprint)
- Selangor Uniform Building By-Laws 1986, updated to Sel. P.U. 142/2012: by-laws 18, 19, 25 and the First Schedule of fees (JKT, KPKT)
- Majlis Perbandaran Selayang: Borang JB-B04(A), permit sementara bagi tambahan bangunan kilang (in force 1 February 2026)
- Majlis Perbandaran Selayang: Borang JB-B01(B), pra semakan permohonan tambahan, perubahan dan ubahsuai (OSC 3.0)
- Majlis Perbandaran Selayang: Borang JB-B08, permit kerja-kerja kecil
- Majlis Perbandaran Selayang: Borang JB-B07, permit sekatan dalaman
- Majlis Perbandaran Selayang: Muat turun borang Jabatan Bangunan, including KTK programme forms
- Majlis Perbandaran Hulu Selangor: Senarai semak permit kerja kecil bangunan selain kediaman
- Majlis Perbandaran Hulu Selangor: Laporan Tahunan 2025, Jabatan Bangunan
- Majlis Bandaraya Shah Alam: Jabatan Bangunan, functions and customer charter
- Majlis Bandaraya Shah Alam: Senarai semak (khusus) bagi permohonan lesen komposit (August 2025)
- Dewan Negeri Selangor: written answer 346, Appendix A, industrial areas by local authority
- Board of Valuers, Appraisers, Estate Agents and Property Managers: Malaysian Valuation Standards, Standard 8 Inspection (exposure draft, circular 1/2011)
- Board of Valuers, Appraisers, Estate Agents and Property Managers: Malaysian Valuation Standards, Standard 9 Valuation Reports (exposure draft, circular 1/2011)
- QBE Insurance (Malaysia): Fire policy wording, conditions 9 (Termination) and 20 (Average)
- Sinar Harian: MPS buat pemeriksaan 15 kilang sekitar Sungai Gong (7 September 2020)
- Utusan Malaysia: DUN Selangor, 19 kilang haram enggan patuh arahan (21 April 2026)
- FactoryHub: Industrial transactions (JPPH-registered)
- FactoryHub: Mortgage calculator
Units on the market nearby
Semi-D Factory for Rent in Saujana Teknologi Rawang, Rawang, 6,525 sq ft
RM 10,500/month
Semi-Detached Factory for Sale or Rent in Saujana Rawang, Rawang, 8,000 sq ft
RM 4,000,000 · RM 15,000/month
Detached Factory for Rent in Batu 17 Rawang, 9,000 sq ft
RM 21,000/month
More on licences, bomba and approvals
- Business Premise Licence for a Factory or Warehouse in Rawang, Serendah and Shah Alam: What MPS, MPHS and MBSA Ask For, Signboard Rules, Timelines and Refusals
- Light Industrial Factory, or Medium or Heavy? How Zoning Classes and Buffer Zones Work in Rawang, Serendah and Shah Alam, and How I Check a Unit
- Factory Wastewater in Rawang, Serendah and Shah Alam: Industrial Effluent Regulations 2009, LUAS Licences and What I Check in the Building
- Bomba Requirements for a Factory or Warehouse in Rawang, Serendah and Shah Alam: Sprinklers, Hose Reels, Hydrants, Alarms and Who Pays