Business Premise Licence for a Factory or Warehouse in Rawang, Serendah and Shah Alam: What MPS, MPHS and MBSA Ask For, Signboard Rules, Timelines and Refusals
Apply to the council that bills the factory's assessment tax: MPS for Rawang and Kundang, MPHS for Serendah, Sungai Choh, Bukit Beruntung and Batang Kali, MBSA for Shah Alam. Each wants SSM papers, stamped tenancy or title, a paid assessment bill and a CF or CCC. Industrial and risk licences take 30 working days to two months.
Key Takeaways
- The licence comes from the council, not from SSM. A factory in Rawang or Kundang is licensed by Majlis Perbandaran Selayang (MPS), one in Serendah, Sungai Choh, Bukit Beruntung or Batang Kali by Majlis Perbandaran Hulu Selangor (MPHS), and one in Shah Alam by Majlis Bandaraya Shah Alam (MBSA).
- The building is checked before the business. MPS licenses premises with planning approval, approved building plans and a CF or TCF; MPHS allows making and processing only in premises with industrial or factory status.
- The signboard goes in the same application. MBSA calls it a Lesen Komposit; MPS and MPHS use one form for premises and advertisement. All three want the sign's wording checked by Dewan Bahasa dan Pustaka (DBP).
- Simple licences take a day or less; industrial ones take weeks. The councils' own charters give 1 hour to 1 working day for low-risk licences, 30 days for an MBSA industrial licence and up to 60 working days or two months for risk licences.
- The councils' conditions point to the usual hold-ups: extensions and partitions without approval, a process that needs DOE, Bomba or DOSH approval, or an SSM address, tenancy or assessment bill that does not match.
Which council issues the business licence for a factory in Rawang, Serendah or Shah Alam?
The council that licenses your business is the council that bills the factory for assessment tax, so the postal address is not always a safe guide. The Selangor state assembly's list of industrial areas by local authority settles most cases in my areas:
| Where the factory is | Council | What the application is called |
|---|---|---|
| Rawang estates and Kundang | MPS (Majlis Perbandaran Selayang) | Lesen Premis Perniagaan dan Iklan |
| Serendah, Sungai Choh, Bukit Beruntung, MIEL Batang Kali, UMW HVM Park | MPHS (Majlis Perbandaran Hulu Selangor) | Borang Komposit Permohonan Lesen Premis Perniagaan dan Iklan |
| Shah Alam Seksyen 15, Seksyen 16, HICOM Seksyen 26, HICOM Glenmarie, Temasya | MBSA (Majlis Bandaraya Shah Alam) | Lesen Komposit (Perniagaan / Perindustrian) |
When I show a client a unit, I ask the landlord for the latest assessment bill on the same visit. It names the council, it shows whether the account is paid, and every one of the three councils asks for a copy of it with the licence application. My cukai pintu guide explains how to read that bill.
What does the council check on the factory building before it licenses the business?
Each council looks at the building first, because a licence for an activity in a building that should not host it is the problem they want to avoid. For an MPS example, my guide to Taman Industri Bolton in Batu Caves covers the licence rules there.
- MPS (Rawang, Kundang). Its approval conditions say the premises must have planning approval or a Development Order, approved building plans and a certificate of fitness (CF or TCF), and must meet Health Department and Bomba requirements. The licensed premises may be used only for the activity written on the licence, and the building may not be altered without permission.
- MPHS (Serendah, Sungai Choh, Bukit Beruntung, Batang Kali). The general conditions in its composite form say making and processing may only be done in premises with industrial or factory status, that the holder needs a CF or a Certificate of Completion and Compliance (CCC) confirmed safe for the business, and that renovated premises need the council Building Department's approval. Partition walls, awnings, ramps and broken walls need council approval too, and premises with a material change must renew their planning permission three months before it expires.
- MBSA (Shah Alam). Its general checklist, amended 29 August 2025, asks for a CF or CCC. Partitions, awnings, broken party walls and cabins need a temporary building permit, using the council's standard plan book or a consultant's plan. For terrace, semi-detached and detached factories, added partitions, sheds or extra space at the front, side or back go to the council's One Stop Centre (OSC) as an amendment plan.
Shah Alam also has a route for factories without a CF. MBSA's special checklist lists documents for an industrial licence without a CF under the programme for regularising factories built without approval (Kilang Tanpa Kebenaran, KTK): a current KTK confirmation form from the Planning Department and a certified copy of the title from an e-Tanah search, on top of the usual papers. If a unit's CF is missing, that tells me the licence will take a different path, with extra documents from the Planning Department and the land office records.
The fire side is its own subject. Whether your unit needs a Bomba fire certificate is covered in my Bomba guide, and whether a building approved as a warehouse can host production is in my warehouse vs factory guide.
What documents do MPS, MPHS and MBSA ask for?
The core set is the same at all three: the application form, the applicant's IC or passport, the company's SSM documents (Form 9, 24 and 49 and the constitution for a Sdn Bhd, or the registration certificate with owner and business information for an enterprise), proof that you may use the premises, the latest paid assessment bill, the CF or CCC, a location plan, photographs, and an authorisation letter if a runner submits for you. The differences are in the details:
| Item | MPS (checklist) | MPHS (form) | MBSA (checklist) |
|---|---|---|---|
| Right to use the premises | Tenancy agreement or land title | Stamped tenancy, or landlord's consent attested by a Commissioner for Oaths; title or SPA if you own it | Current tenancy or SPA, stamped by LHDN |
| Photographs | Signboard position, fire extinguisher hung 1 metre from the floor, rubbish bin, first aid box | Colour, dated within 2 weeks of the application with a timestamp app: front, back and two inside views | Front, back, inside and side |
| Plans | Floor plan and location plan | Location plan, 4 copies | Floor plan in square metres and location plan |
| Fire | Extinguisher receipt and photograph | Extinguisher purchase sticker, not expired, with the premises address | Bomba letter where the activity involves flammables |
| Other | Letter explaining why, if you apply without a signboard | SSM address must match the premises address | Passport photo; foreign applicants add passport and work visa; 4 copies of every document |
Then come the documents for the activity itself, and this is where a factory differs from a shop:
- MPHS asks an industrial or manufacturing applicant for a solid waste contractor's appointment letter, Department of Environment (DOE) approval for activities that produce waste, recycle, handle plastics or could harm the environment, Bomba approval, a machinery certificate from the Department of Occupational Safety and Health (DOSH, or JKKP), and other papers depending on the process.
- MPS asks for DOE Selangor, Bomba and DOSH approvals for stores of chemicals, toxic, flammable, hazardous materials or scheduled waste, and DOE approval for any industry releasing effluent to air or drains. A food processing and packing factory adds typhoid jabs, food handling course certificates, a pest control contract, FoSIM registration with the Ministry of Health and a photo of the grease trap.
- MBSA asks for DOE, Bomba or Atomic Energy Licensing Board letters for processing, storing or producing dangerous or flammable materials. It notes that KPDN licences to manufacture or wholesale petrol, diesel, LPG, kerosene and chemical fertiliser are issued only after the council licence.
One local detail for workshops: the MPS checklist lets vehicle workshops in an industrial area operate from 8am to 8pm only, and asks them to hold public liability insurance and carry out pest control at least once a week.
How do you get the signboard licence for a factory?
Apply for it with the premise licence, and do not fabricate the sign before the council has seen the drawing.
- MPS says a sign may not go up before the business licence is issued. It wants a colour sketch showing the size in metres, the activity in Malay, the words MPS/NO. AKAUN LESEN at the lower right corner and whether the sign is lit. Hand sketches and black and white prints are rejected, lit signs may not blink, and where Malay is used with another language the Malay words must be 30% larger and verified by DBP.
- MBSA wants the company's activity in Bahasa Malaysia, in letters 5% larger than the company name and placed above it, with the SSM name, address, sign size, letter size and lighting on the sketch. The sign may not cover windows or glazing or rise above the roof, its structure needs a registered engineer's approval, a large sign or one covering windows may need Bomba's comments, and a two-sided sign on the side of a building needs the neighbour's written consent.
- MPHS asks for the DBP certificate if there is a signboard, and its form records each sign's size, number of faces, lighting, whether it stands vertical, horizontal or projecting, and whether it faces the front, the side or the road.
How long does a factory licence take at MPS, MPHS and MBSA?
These are the councils' own published targets. They run from a complete application, so a missing document stops the clock before it starts.
| Council | Low-risk licence | Industrial or technical licence | Risk licence |
|---|---|---|---|
| MPS (charter) | Decided within 1 hour of paying the processing fee | Decided within 30 working days | Complete applications go to the Business Control and Health Committee within 60 working days |
| MPHS (charter, May 2026 report) | Decided within 1 working day | Complete applications decided in 7 to 60 working days (form) | High-risk licences decided within 2 months |
| MBSA (Licensing Department) | 1 hour for non-risk licences and permanent signs | Industrial licence approved within 30 days |
At MBSA the application flow shows why industrial licences take longer: an incomplete file is returned at the check, a complete one is sent to the technical departments for a site inspection, and a committee meeting approves or rejects it before the decision letter goes out. MBSA charges a processing fee of RM100 for an industrial application and RM50 for a business one (MBSA); its 1 hour licence page says the processing fee is paid on the day you apply and the licence fee straight after the approval letter. You can check an MBSA application at elesen.mbsa.gov.my.
Under section 107 of the Local Government Act 1976, a licence is valid for up to three years, and the holder must display it in a prominent place on the premises. Failing to display or produce it can bring a fine of up to RM500, up to six months in prison, or both.
What stops a factory or warehouse licence from being approved?
From the councils' conditions, these are the points that hold up or end an application:
- The building is not approved for the use. No planning approval, no CF or CCC, or manufacturing in premises without industrial or factory status.
- The building differs from its plans. Partitions, awnings, sheds, ramps or extensions without the council's approval.
- The process needs approvals you do not have yet. DOE, Bomba or DOSH for waste, effluent, chemicals, flammables or machinery.
- The papers do not line up. An SSM address that differs from the premises, an unstamped tenancy, an assessment account in arrears or a missing CF copy.
- The sign drawing fails. No DBP verification, or a sketch the council will not accept.
- The council's discretion. Section 107 lets a council attach conditions, revoke a licence at any time and refuse to grant or renew one without giving reasons. MBSA publishes an appeal form for refused composite licences (MBSA).
After approval the licence still binds you. MPS and MPHS say it cannot be transferred without approval, and MPHS says the holder may not change or add an activity without applying, and must tell the council if the activity changes, ends or moves. If you take over a factory from another tenant, budget for your own application rather than counting on theirs.
What I check on a viewing so the licence does not hold up your move
When a client asks me to shortlist factories in Rawang, Serendah or Shah Alam, the licence is part of the shortlist, not an afterthought. On the visit I go through five points:
- The latest assessment bill. Which council, and whether it is paid.
- The CF or CCC and the approved plan. Then I walk the unit and note anything built since: mezzanines, partitions, side sheds, an enclosed loading area.
- The client's process against the agency list. If it produces waste or effluent, stores chemicals or runs machinery that needs a DOSH certificate, those approvals go on the timeline before the lease start date.
- The tenancy and the company file. The SSM address should match the unit, and the tenancy must be stamped before the council will take it.
- Where the sign will go. I check that the position the client wants will meet the council's rules before the sign maker starts.
For the national picture and other councils, FactoryHub has a guide to business premise licences, and its registered transactions for Rawang and Shah Alam help you set the rent against everything above. For the wider list of pre-lease checks in Rawang, see what to check before renting a factory in Rawang.
If you are weighing a factory or warehouse in Rawang, Serendah or Shah Alam and want the licence checks done before you sign, WhatsApp Jason Low on +60 12-288 1834.
Licences for a wood processing factory
What licences does a wood processing factory need in Rawang or Serendah?
Start with the business premise licence from the council: MPS for Rawang and Kundang, or MPHS for Serendah, Sungai Choh, Bukit Beruntung and Batang Kali. For industrial applicants, MPHS also asks for DOE approval where the process produces waste or could harm the environment, Bomba approval and a DOSH machinery certificate. Check the full list with the council before you sign the tenancy. Whether the company also needs a manufacturing licence from MIDA is covered in my separate guide.
Applying to MBDK in Klang? Klang premises are licensed by MBDK (Majlis Bandaraya Diraja Klang), not by the councils above. Ms Teh Seok Hoon (PEA 4006), the CID Realtors colleague who handles Klang, covers the temporary industrial licence, the agencies on MBDK's list and the conditions to keep in her MBDK factory and warehouse licence guide.
Questions people ask
01Is SSM registration the same as a business premise licence?+
No. SSM registers your company or business, while the local council licenses the premises and the activity carried out there. MPS, MPHS and MBSA all ask for your SSM documents as part of the licence application, and MPHS wants the SSM address to match the factory address.
02How much does a factory business licence cost in Shah Alam?+
MBSA charges a processing fee of RM100 for an industrial application and RM50 for a business one. The licence fee itself is set by the council, and MBSA's 1 hour licence page says it is paid straight after the approval letter, so ask MBSA for the figure for your activity and floor area before you budget.
03How long is a council business licence valid?+
Section 107 of the Local Government Act 1976 allows a licence to be valid for up to three years. MPHS states that its licence runs from the date the licence fee is paid to the expiry date printed on it, and the licence must be displayed in a prominent place on the premises.
04Can I use the previous tenant's licence when I take over a factory?+
No. MPS and MPHS both say a licence cannot be transferred without the council's approval, and MPHS requires a separate application to change or add an activity. A new operator should plan for its own application, including the signboard if it puts up a new one.
05Can the council refuse a factory licence without giving a reason?+
Yes. Section 107 of the Local Government Act 1976 lets a council refuse to grant or renew a licence without assigning a reason, attach conditions, and revoke a licence at any time. MBSA publishes an appeal form for refused composite licence applications.
06Do I need a signboard licence for a factory?+
Yes, if you put up a sign. MBSA combines it with the premise licence in its Lesen Komposit, while MPS and MPHS use one form for premises and advertisement. MPS asks applicants who do not want a sign for a letter explaining why, and does not allow a sign to go up before the business licence is issued.
07How do you apply for an MBSA factory business licence in Shah Alam?+
Apply to MBSA for a Lesen Komposit (Perniagaan / Perindustrian). Hand in the form, your SSM documents, a tenancy or SPA stamped by LHDN, the latest paid assessment bill, the CF or CCC, floor and location plans, photographs and the signboard sketch. Processing costs RM100 for an industrial application and RM50 for a business one, and MBSA approves industrial licences within 30 days, after its technical departments inspect the site and a committee decides.
08Can I change the company name after renting a factory in Rawang or Shah Alam?+
Yes, but the council licence has to carry the new name as well, so plan for an update after the change. MPS, MPHS and MBSA all ask for SSM documents, and MPHS also wants the SSM address to match the factory address. Ask the council that bills the unit for assessment tax (MPS for Rawang and Kundang, MPHS for Serendah and Batang Kali, MBSA for Shah Alam) what it needs from you once the name changes.
Sources
- Majlis Perbandaran Selayang: Memohon Lesen / Permit Lesen Sementara (application and approval conditions)
- Majlis Perbandaran Selayang: Senarai semak permohonan lesen premis perniagaan dan iklan
- Majlis Perbandaran Selayang: Piagam Pelanggan, Jabatan Pelesenan
- Majlis Perbandaran Hulu Selangor: Borang komposit permohonan lesen premis perniagaan dan iklan, senarai semak dan syarat
- Majlis Perbandaran Hulu Selangor: Piagam Pelanggan
- Majlis Perbandaran Hulu Selangor: Pencapaian piagam pelanggan, Mei 2026
- Majlis Bandaraya Shah Alam: Lesen Komposit (Perniagaan / Perindustrian), documents and processing fees
- Majlis Bandaraya Shah Alam: Senarai semak (umum) permohonan lesen komposit, pindaan 29 Ogos 2025
- Majlis Bandaraya Shah Alam: Senarai semak (khusus) permohonan lesen komposit, including industry without CF under the KTK programme
- Majlis Bandaraya Shah Alam: Carta aliran permohonan lesen komposit
- Majlis Bandaraya Shah Alam: Jabatan Pelesenan, client charter
- Majlis Bandaraya Shah Alam: Lesen 1 Jam, fees and payment timing
- Local Government Act 1976 (Act 171), section 107 (DBKL copy)
- Dewan Negeri Selangor: Industrial areas by local authority (written answer 346, Lampiran A)
- FactoryHub: JPPH-registered industrial transactions
Units on the market nearby
Semi-D Factory for Rent in Saujana Teknologi Rawang, Rawang, 6,525 sq ft
RM 10,500/month
Semi-Detached Factory for Sale or Rent in Saujana Rawang, Rawang, 8,000 sq ft
RM 4,000,000 · RM 15,000/month
Detached Factory for Rent in Batu 17 Rawang, 9,000 sq ft
RM 21,000/month
More on licences, bomba and approvals
- Light Industrial Factory, or Medium or Heavy? How Zoning Classes and Buffer Zones Work in Rawang, Serendah and Shah Alam, and How I Check a Unit
- Illegal Factory Extension in Rawang, Serendah or Shah Alam: What MPS, MPHS and MBSA Can Do and How to Make It Legal
- Factory Wastewater in Rawang, Serendah and Shah Alam: Industrial Effluent Regulations 2009, LUAS Licences and What I Check in the Building
- Bomba Requirements for a Factory or Warehouse in Rawang, Serendah and Shah Alam: Sprinklers, Hose Reels, Hydrants, Alarms and Who Pays