Can You Buy a Factory With Only a Master Title, or One With a Pollution History? What to Check in Rawang, Serendah and Shah Alam

Written by , PEA 1478 · Published · Licences, Bomba and approvals

Short answer

Yes to both, with checks. A factory on a master title is bought by SPA and deed of assignment, and the bank takes an assignment until the individual or strata title issues. A factory with a pollution history can be bought, but DOE guidelines expect the buyer to assess soil and groundwater first.

A row of newly completed semi-detached factories beside a concrete drain, with a fenced patch of bare soil marked for sampling at the edge of the plot.
Illustrative image

Key Takeaways

  • Yes, you can buy a factory that still sits on a master title. The deal runs on the sale and purchase agreement and a deed of assignment until the individual or strata title is issued, and your bank takes an assignment of your rights instead of a charge.
  • The title is the developer's job, with deadlines for strata. Under the Strata Titles Act the developer must apply for strata titles once it sells a parcel, and missing the deadlines carries a fine of RM10,000 to RM100,000, jail of up to three years, or both.
  • If the master title is charged to the developer's bank, get that bank's disclaimer. Your lawyer asks for a redemption statement and a letter of disclaimer, so the bank cannot sell your unit with the rest of the land.
  • A factory with a pollution history can also be bought, but the risk can move to you. The Department of Environment's guidelines say a buyer should assess soil and groundwater before the deal, and that the current landowner may have to pay for clean-up when the polluter is gone.
  • Penalties went up in 2024. Since the Environmental Quality (Amendment) Act 2024 came into force in July 2024, polluting land can cost RM50,000 to RM500,000 or up to five years in jail.

What does "master title" mean when you buy a factory?

Many factories in a new scheme are sold before each unit has its own title. The whole development then sits under one title, the master title, in the developer's name. Each buyer's unit gets its own title later, in one of two ways:

  • An individual title by subdivision. For landed lots, section 135 of the National Land Code lets the owner subdivide the land into separate titles with the approval of the State Director or the Land Administrator.
  • A strata title. The Strata Titles Act 1985 covers not only flats. Its "land parcel" is a unit in a building of not more than four storeys, held under a strata title, which is how many terrace and semi-detached factories in managed parks are titled.

When I look at a factory in a newer estate in Rawang, Serendah or Shah Alam, the first question is which of these two routes the unit is on, and how far along it is.

Can I buy a factory that only has a master title?

Yes. The National Land Code does not stop a contract simply because the title is not yet issued. Section 206 says no instrument transfers title until it is registered, but subsection (3) keeps the contract itself effective. So the purchase is documented in two parts:

  1. Now: the sale and purchase agreement (SPA) with the developer or the current owner, and a deed of assignment that passes the owner's rights in the unit to you.
  2. Later: once your title is issued, a transfer in Form 14A is registered, and under section 215 the title passes to you only on registration.

The Malaysian Bar's conveyancing practice committee describes the same split: a Form 14A transfer for a property with title, a deed of assignment for a property without one. In a subsale before title, the seller usually needs the developer's consent, and the seller's bank signs a receipt and reassignment to hand back its rights.

A point many buyers miss: a factory is not housing, so the Housing Development Act and its standard contracts do not protect you. My guide on buying a new factory from a developer explains why the SPA is your main protection.

How does a bank finance a factory without its own title?

Instead of a charge on a title, the bank takes an assignment of your rights under the SPA. UOB's deed of assignment (version 04/25) is a good example of what you sign. Its recitals state that a separate title has yet to be issued. You agree to sign the transfer and a charge to the bank as soon as the title is issued. The developer undertakes to refund if the transfer and the bank's charge cannot be registered free from encumbrances, and, if the developer has charged the land, to give a letter of disclaimer and keep your unit out of any order for sale.

That last point matters most. Developers often finance a project by charging the master title to their own bank. A 2022 Malaysian Bar article explains that the buyer's lawyer then asks for a redemption statement and a letter of disclaimer, under which the master chargee agrees not to foreclose on your unit as long as the redemption sum is paid.

The same bank also has a say in the subdivision. Section 136(1)(e) of the National Land Code requires every chargee of the land to consent in writing to the subdivision application, so the developer's financier can hold up your individual title if the developer falls behind.

What are the risks, and what do I check before the SPA?

The real risks are a long wait for the title and a developer that runs into trouble before it is issued. These are the checks I make, with your lawyer, before a client signs:

  1. An official search on the master title. I read the registered owner, the land use category, the express conditions and any charge. An official search in the Petaling land office costs RM50.
  2. The title route and its stage. Individual title by subdivision or strata title, and whether the application has been filed or approved.
  3. The developer's bank. If the master title is charged, the redemption statement and letter of disclaimer must be in hand before your loan is released.
  4. The developer's undertakings. To transfer once the title is issued, not to create further charges, and to apply for the consents.
  5. Consents. A title with a restriction in interest needs state consent for the transfer and the charge; see my guide on state consent in Selangor. A Bumiputera lot needs a release, covered in my Bumi lot guide.
  6. A caveat, where your lawyer advises it. Section 323 of the National Land Code lets a person claiming a right to a title or an interest lodge a private caveat (Form 19B).

For strata factories, the law adds pressure on the developer. Section 8 of the Strata Titles Act requires the original owner to apply for subdivision once it has sold any parcel, section 8A sets short deadlines (for example, three months from the document certifying the superstructure stage), and section 8 penalises a breach with a fine of RM10,000 to RM100,000, jail of up to three years, or both, plus RM100 to RM1,000 a day while it continues.

Can I still buy a factory that has had a pollution problem?

Yes, nothing in the law bars the sale. The question is who carries the problem afterwards, and whether you can still use the factory the way you plan.

Section 24(1) of the Environmental Quality Act 1974 says no person shall, unless licensed, pollute "or cause or permit to be polluted" any soil or surface of land. The word "permit" reaches owners who let pollution happen on their land. Section 31 lets the Director General serve notices on "the owner or occupier" of premises, and section 43 treats directors and managers of a company as guilty of its offences unless they show they used due diligence.

The Environmental Quality (Amendment) Act 2024 raised the penalties. The minister said it would take effect on 7 July 2024:

Offence under the Act Penalty after the 2024 amendment
Polluting soil or land (section 24) RM50,000 to RM500,000, or jail of up to 5 years
Polluting inland waters (section 25) Jail of up to 5 years and a fine of RM50,000 to RM10 million
Scheduled waste offences (section 34B) RM100,000 to RM10 million and jail of up to 5 years
Not complying with a notice (section 31) RM50,000 to RM1 million

Rawang has seen how far this goes. In September 2020, after pollution of Sungai Gong cut water supply, the Selangor Menteri Besar said the factory involved owned its land but had no planning approval, and it was ordered to close. A buyer of such a site inherits the history, the neighbours' attention and any approval gaps.

Who pays to clean up contaminated factory land?

The Department of Environment's Contaminated Land Management and Control Guidelines, the first of three (2009) set out the approach. The polluter should pay, but if the polluter is no longer operating in Malaysia, the responsibility falls on the current landowner. The seller is expected to disclose all soil and groundwater information, and the buyer is responsible for assessing soil and groundwater as part of due diligence before the transaction.

These guidelines are still guidelines. The DOE's own FAQ says they stay in that status until regulations on soil pollution are gazetted, and that the department is drafting regulations so that section 24 can be enforced. I treat that as a reason to check now, not later: the rules are moving towards enforcement, and the guidelines already tell you who will be asked first.

How do I check a factory with a pollution history before buying?

Guidelines No. 2 recommend an initial assessment (a Phase I environmental site assessment) for land that is being transferred, as part of due diligence. If it points to possible contamination, a Phase II assessment follows, with soil and groundwater sampling. In practice I work through this list with the buyer:

  • History of use. What trades occupied the factory: plating, chemicals, paint, recycling and workshops raise more questions than storage.
  • Paper trail. Ask the seller in writing for any DOE notice, compound or court case, and for the scheduled waste records. The Scheduled Wastes Regulations 2005 require a waste generator to notify the DOE within 30 days, store waste for no more than 180 days and 20 tonnes, and keep an up-to-date inventory.
  • Site walk. Stained ground, buried tanks, old drums, effluent pipes to the drain. My guide on industrial effluent and wastewater covers the discharge side.
  • A Phase I report before the SPA, and a Phase II if it recommends one.
  • The SPA. Seller's disclosure and warranties on environmental matters, an indemnity, and the right to withdraw if the assessment finds contamination.
  • Approvals. Check the building has its approvals and CCC; a factory with gaps is covered in my guide on illegal factory extensions.

If you would like a master title or a factory's past use checked before you sign in Rawang, Serendah or Shah Alam, WhatsApp Jason Low, Probationary Estate Agent PEA 1478 with CID Realtors, on +60 12-288 1834.

Questions people ask

01Can I buy a factory with a master title?+

Yes. Until the individual or strata title is issued, the purchase runs on the SPA and a deed of assignment, and section 206(3) of the National Land Code keeps the contract effective before registration. Once your title is issued, a Form 14A transfer is registered and the title passes to you.

02Can I get a bank loan for a factory without an individual title?+

Yes, banks finance it by taking an assignment of your rights under the SPA instead of a charge. UOB's deed of assignment, for example, requires you to sign the transfer and charge once the title is issued, and has the developer undertake to refund if they cannot be registered free from encumbrances.

03What happens if the master title is charged to the developer's bank?+

Your lawyer asks that bank for a redemption statement and a letter of disclaimer. Under the disclaimer the bank agrees not to foreclose on your unit as long as the redemption sum is paid. Do not let your loan be released before these are in hand.

04How long does a developer have to apply for strata titles?+

Section 8 of the Strata Titles Act requires the developer to apply once it has sold any parcel, and section 8A sets short deadlines, such as three months from the document certifying the superstructure stage. A breach can bring a fine of RM10,000 to RM100,000, jail of up to three years, or both.

05Can I still buy a factory that has had environmental pollution incidents?+

Yes, the law does not bar the sale, but the risk can pass to you. Under DOE's 2009 guidelines the current landowner may have to pay for clean-up if the polluter is no longer operating in Malaysia. Ask for the history, the DOE records and a Phase I site assessment before you sign.

06What are the penalties for polluting land in Malaysia now?+

Since the 2024 amendment to the Environmental Quality Act, which the minister said took effect on 7 July 2024, polluting soil or land carries RM50,000 to RM500,000 or up to five years in jail. Polluting inland waters carries jail of up to five years and a fine of RM50,000 to RM10 million.

07Do I need an Environmental Site Assessment before buying a factory?+

No law requires one for every factory purchase, but the DOE's Contaminated Land Management and Control Guidelines No. 2 recommend an initial Phase I assessment for land being transferred, as part of due diligence. I advise one whenever the past occupiers did plating, chemicals, paint, recycling or similar work, and a Phase II with soil and groundwater sampling if the Phase I points to contamination. Commission it before you sign the SPA, or make the SPA conditional on it.

08Will an environmental violation record affect the sale of a factory?+

It does not stop the sale, but it changes the terms. A careful buyer asks for the DOE notices, compounds and scheduled waste records, may commission a Phase I site assessment, and will want disclosure, warranties and an indemnity in the SPA or a price that reflects the risk. A seller should settle open notices first and handing over the records.

Sources

  1. National Land Code (Act 828), sections 135, 136, 206, 215 and 323
  2. Strata Titles Act 1985 (Act 318), sections 8 and 8A, AGC
  3. Malaysian Bar: Understanding an SPA, part 2 (conveyancing practice committee)
  4. Malaysian Bar: Conveyance lawyer, professional service trumps theoretical knowledge, part 2 (2022)
  5. UOB Malaysia: deed of assignment (version 04/25)
  6. Pejabat Tanah dan Daerah Petaling: search fees
  7. Environmental Quality Act 1974 (Act 127), DOE
  8. Environmental Quality (Amendment) Act 2024 (Act A1712)
  9. Malay Mail: Heavier penalties under the amended Environmental Quality Act from 7 July (June 2024)
  10. DOE: Contaminated Land Management and Contaminated Land Management and Control Guidelines 1 of 3 (2009)
  11. DOE: Contaminated Land Management and Control Guidelines No. 2 (2009)
  12. DOE: FAQ on scheduled waste and contaminated land
  13. Environmental Quality (Scheduled Wastes) Regulations 2005
  14. Malay Mail: Selangor MB on the Rawang factory behind the Sungai Gong pollution (September 2020)

Units on the market nearby

More on licences, bomba and approvals

All guides: Licences, Bomba and approvals →

Probationary Estate Agent · PEA 1478 · CID Realtors Sdn Bhd E(1) 1855About Jason → · Contact →
Ask Jason about this