New Factory for Sale by a Developer in Rawang, Serendah or Shah Alam: What Protects the Buyer and What I Check Before You Book

Written by , PEA 1478 · Published · Power, height, floor and access

Short answer

A buyer of a new factory from a developer in Rawang, Serendah or Shah Alam is protected by the sale and purchase agreement and contract law, not the Housing Development Act, which covers only housing. Before a client books, I check the delivery date, CCC and power terms, late-delivery compensation, defects period, payment stages and a land search.

Illustration of a newly completed row of two-storey semi-detached factories with a small substation building beside a freshly paved road in a new industrial park.
Illustrative image

Key Takeaways

  • The Housing Development Act does not cover a factory. Act 118 applies to housing accommodation, buildings meant for people to live in. A developer selling factories needs no housing licence under it, opens no Housing Development Account for your money, and you cannot take a claim to the homebuyer tribunal.
  • Your protection is the sale and purchase agreement (SPA). The developer drafts it, so the delivery date, late-delivery compensation, defects period and payment stages are whatever it says, and they are open to negotiation before you sign.
  • The new law is still a proposal. On 18 November 2026 the Real Property Development Act was still described as proposed, and the ministry's statements name commercial projects, not industrial ones.
  • Delivery should mean a CCC with power and water in place. Under Selangor's by-law 25, the CCC can only be issued once essential services, including electricity, water, fire hydrants, drains and access roads, are provided.
  • Check the land before the booking fee. An official search (Carian Rasmi) on e-Tanah Selangor covers land and strata titles, is paid online and takes one working day.

Does the Housing Development Act protect you when you buy a new factory?

No. The Housing Development (Control and Licensing) Act 1966 defines housing accommodation as a building "wholly or principally constructed, adapted or intended for human habitation or partly for human habitation and partly for business premises". A factory is built for production and storage, so a project of factories sits outside the Act, and three things a house buyer has by law fall away:

  • Licensing. Section 5 allows only a licensed housing developer to carry out a housing development. The Act asks nothing of a developer that sells factories.
  • Your money. Section 7A makes a licensed housing developer pay the purchase money of each housing project into a Housing Development Account for that project or phase. Nothing in the Act does the same for factory payments.
  • The tribunal. Under section 16L only a homebuyer may lodge a claim with the homebuyer tribunal. A factory buyer's dispute goes to court, or to arbitration if the SPA says so.

What remains is the Contracts Act 1950 and the words of your SPA. That is why I spend more time on the SPA of a new factory than on a subsale, where the building, the CCC and the title already exist and can be inspected. My Rawang Perdana guide sets the two routes side by side for one estate.

Will the Real Property Development Act change this?

Not yet, and possibly not for factories. In November 2025 the housing ministry said it expected to table a Real Property Development Bill in June 2026 to replace Act 118 and to widen regulation beyond residential developments to commercial projects (Bernama, 20 November 2025). In August 2026 the minister said the new Act was at the final stage of review and would extend the scope to commercial property, including shop space (Bernama, 10 August 2026). On 18 November 2026 it was still called the proposed Act (The Sun).

None of these statements mentions industrial property. Until a law is passed and its scope is published, I read every factory SPA as a private contract, and I tell clients to do the same.

What does a house buyer get by law that you must write into a factory SPA?

The housing ministry's guide for house buyers sets out the terms of the statutory agreements: Schedule G for landed houses and Schedule H for strata units (JPN, KPKT). They make a useful checklist, because each one is a point I want covered, in some form, in a factory SPA.

Term House buyer, by law What I ask for in a factory SPA
The agreement Statutory Schedule G or H The developer's draft, read with a lawyer before booking
Delivery 24 months (landed) or 36 months (strata) from the SPA date A fixed date, with vacant possession defined as CCC issued and power connected
Late delivery Damages day by day at 10% a year of the price A written rate, how it is counted and when it is paid
Defects 24 months after vacant possession A stated period, a repair deadline and a sum held back
First payment 10% of the price, paid when the SPA is signed The booking fee, what it secures and when it is refunded
Purchase money Paid into a Housing Development Account Payments tied to the architect's certificates for each stage
Disputes Homebuyer tribunal Court, or arbitration if the SPA provides for it

Which clauses do I read first in a developer's factory SPA?

When a client sends me a new-launch SPA for a factory in Rawang, Serendah or Shah Alam, I read it in this order, because these clauses decide whether the unit can run a business on the day it is handed over.

  1. The unit itself. The lot number on the approved layout plan, land area, built-up area, and a specification schedule with floor loading, eaves height, roller shutter sizes and roofing. A figure that is only in the brochure is not in the contract. I also ask how the price changes if the surveyed land area differs from the plan.
  2. Power. The supply per unit in amps, written into the specification, and who pays if a substation is needed. In a new park the supply depends on the developer's application to TNB; see my guides on the TNB compact substation and on sizing power from your machine list.
  3. Delivery and what it means. The date, and a definition of vacant possession that includes the CCC. Selangor's by-law 25 lets the principal submitting person issue the CCC only when the council's technical conditions are met, Forms G1 to G21 are certified, and access roads, drains, water, electricity, fire hydrants and sewerage are provided. With the CCC, the principal submitting person certifies the building as safe and fit for occupation. Keys alone do not open a business: the council licence asks for the CCC, as I explain in renting a factory without CCC or CF.
  4. Late-delivery compensation. The rate, the date it starts and how it is paid. Under section 75 of the Contracts Act the agreed sum caps reasonable compensation. In Cubic Electronics v Mars Telecommunications the Federal Court held that actual loss need not always be proved and that the party in breach must show the sum is unreasonable (Allen & Gledhill). The same case covered a forfeited deposit, so I read the clause that lets the developer keep your money if you default just as closely.
  5. Payment stages. Each stage should match work certified by the developer's architect, not a calendar date. I check what is due on booking and on signing, and whether a final part is held until the CCC and the title.
  6. Defects. How long the period runs, how you notify, how many days the developer has to repair, and whether a sum is held by a solicitor as stakeholder until the period ends.
  7. Changes. Whether the developer may change the layout, specification or land area, and what happens to your price if it does.
  8. Title and consents. Whether the unit will get an individual title or a strata title, and when. A Bumiputera lot in a new project needs a release from LPHS (Lembaga Perumahan dan Hartanah Selangor) before a non-Bumiputera buyer can take it; my Bumi lot guide covers that step.
  9. Use and park rules. The approved use of the building against your industry, plus the park's management fee and house rules. See light, medium or heavy industry and managed parks versus older estates.

How do I check the developer and the land before paying a booking fee?

  • Land search. An official search (Carian Rasmi) on e-Tanah Selangor covers land titles and strata titles, is paid by FPX and takes one working day; the printout stays available for three days. On the result I read the registered owner, the land use category, the express conditions and any charge. If the owner is not the company selling to you, I ask how it is entitled to sell. If the land is charged to a bank, I ask how your unit will be released.
  • Approvals. Planning permission and approved building plans come from the council: MPS for Rawang and Kundang, MPHS for Serendah, Sungai Choh, Bukit Beruntung and Batang Kali, MBSA for Shah Alam (see my business licence guide). I ask for the approval references and check that your lot and building type are on the approved layout.
  • Track record. I visit an earlier phase that already has its CCC, look at its roads and drains, and ask owners there how delivery went. FactoryHub's guide to choosing an industrial park developer goes further on track record.
  • The booking form. The fee, what happens if the SPA is not signed, and whether it is refunded. With no statutory form, these terms are the developer's own, so read them before you pay.

How does a developer's price compare with registered deals?

JPPH-registered transactions give a reference point. In Rawang and Kundang, 129 semi-detached factory deals were recorded in the 24 months to August 2026, at a median RM4.3 million, RM380 psf of land, on a median 12,561 sq ft of land (Rawang & Kundang transaction prices and rents). Serendah's 28 recorded semi-detached deals had a median of RM3.16 million, RM213 psf of land, and Shah Alam's 66 a median of RM5.92 million, RM514 psf of land (JPPH data via FactoryHub).

These are registered transfers that include older units, and the psf is per square foot of land. Compare a launch price per sq ft of land with the same factory type only, and allow for the new building, its specification and its position in the park. If the bank values a new unit below the price, read my guide on a bank valuation lower than the purchase price. Stamp duty on the transfer and the loan is set out in my stamp duty guide.

What I tell a client before they book a new factory

My rule is simple: no booking fee until the client has read the draft SPA with a lawyer, seen the land search, and has the TNB supply per unit and the CCC condition in writing. A new unit gives you a known specification and a new roof; a subsale in Rawang, Serendah or Shah Alam gives you a building you can inspect and move into sooner. Which one suits you depends on how long you can wait and how much your production depends on a specification only a new building offers.

This guide explains public law and practice; it is not legal advice, so have your own lawyer review the SPA before you sign.

To talk through a new launch or a subsale, WhatsApp Jason Low, Probationary Estate Agent (PEA 1478) with CID Realtors Sdn Bhd, on +60 12-288 1834.

Questions people ask

01Does the Housing Development Act protect factory buyers in Malaysia?+

No. Act 118 covers housing accommodation, meaning buildings meant for people to live in, so a factory project falls outside it. A factory buyer has no statutory SPA, no Housing Development Account for the purchase money and no access to the homebuyer tribunal; protection comes from the SPA and the Contracts Act 1950.

02Is there a standard sale and purchase agreement for a new factory?+

No. Schedules G and H are the statutory forms for houses only. For a factory the developer drafts its own SPA, so the delivery, late-delivery compensation, defects and payment terms should be read by your lawyer and negotiated before you sign.

03What can I claim if the developer hands over my factory late?+

Whatever the late-delivery clause in your SPA provides. Under section 75 of the Contracts Act 1950 the agreed sum caps reasonable compensation, and the Federal Court in Cubic Electronics held that actual loss need not always be proved. With no homebuyer tribunal for factories, the claim goes to court, or to arbitration if the SPA provides for it.

04Can I start operating as soon as the developer gives me the keys?+

Plan from the CCC date, not the key date. Under Selangor's by-law 25 the CCC certifies that the building is safe and fit for occupation, and the council asks for it before it licenses a business at the premises. Ask for the SPA to define vacant possession as the CCC issued and power connected.

05Should I pay a booking fee for a new factory before I see the SPA?+

I advise against it. Booking terms for a factory are the developer's own, so ask for the booking form, the draft SPA and a land search first, and get in writing when the fee is refunded if the SPA is not signed.

06Will the Real Property Development Act cover factories?+

Not on what has been announced. On 18 November 2026 the Act was still described as proposed, and the minister's statements in November 2025 and August 2026 extended the scope to commercial projects without mentioning industrial property. Check the final text once it is tabled.

07How do I find out who owns the land of a new industrial project in Selangor?+

Apply for an official search (Carian Rasmi) on e-Tanah Selangor. It covers land and strata titles, is paid online by FPX and is processed in one working day. Read the registered owner, the land use category, the express conditions and any charge to a bank.

Sources

  1. Housing Development (Control and Licensing) Act 1966 (Act 118), Attorney General's Chambers
  2. Jabatan Perumahan Negara (KPKT): guide for house buyers, Schedule G and H terms
  3. Bernama: KPKT to table Real Property Development Bill in June 2026 (20 November 2025)
  4. Bernama: Tiga akta baharu, satu pindaan di bawah Dasar Perumahan Negara (10 August 2026)
  5. The Sun: Nga receives outstanding public service award (18 November 2026)
  6. Selangor Uniform Building By-Laws 1986 (updated), by-law 25
  7. Contracts Act 1950 (Act 136), Attorney General's Chambers
  8. Allen & Gledhill: Federal Court on section 75 of the Contracts Act (Cubic Electronics)
  9. e-Tanah Selangor: Permohonan Carian Rasmi
  10. FactoryHub: Rawang & Kundang transaction prices and rents (JPPH-registered)

Units on the market nearby

More on power, height, floor and access

All guides: Power, height, floor and access →

Probationary Estate Agent · PEA 1478 · CID Realtors Sdn Bhd E(1) 1855About Jason → · Contact →
Ask Jason about this