How Much Power Does Your Factory Need? kVA to Amps From the Machine List, Checking the Unit and a TNB Upgrade in Rawang, Serendah and Shah Alam

Written by , PEA 1478 · Published · Updated · Power, height, floor and access

Short answer

Add the kW of machines running at once, divide by the power factor (TNB expects at least 0.85) to get kVA, then multiply by about 1.44 for amps per phase at 400V three phase. Check a unit with its TNB bill, meter and main switchboard. A TNB upgrade typically takes under 3 months to 12 months.

A factory's open switch room with grey switchboard panels and cable trays beside a fenced green compact substation under tropical trees.
Illustrative image

Key Takeaways

  • Size the load from what runs at the same time, not from everything you own. Add the kW of the machines that run together, divide by the power factor to get kVA, then multiply by about 1.44 to get amps on TNB's 400V three-phase supply. TNB expects customers below 132kV to keep a power factor of at least 0.85 (TNB).
  • 100A is the line that changes the paperwork. Up to 100A, an electrical contractor registered with the Energy Commission applies through myTNB. Above 100A, an Electrical Consultant Engineer registered with the Board of Engineers Malaysia applies, and the supply is metered through current transformers (CTs) (TNB ESAH 3.1).
  • Check a unit three ways before you trust the power line in a listing: the TNB bill, the meter and its CT ratio, and the main switchboard. Then ask for the single line diagram and the last Form G and Form H.
  • An upgrade pays the difference in load charge, not the full new charge. Moving a CT-metered supply from TNB's 241 to 360 kW band to its 361 to 480 kW band costs RM21,600 minus RM16,200, or RM5,400 (TNB Connection Charges Book 2025), plus a deposit of about two months' bills.
  • The supply scheme sets the time. TNB's typical lead time is under 3 months at 400V without a substation, 3 to 12 months with one, and 6 to 12 months at 11kV, provided council approvals are not delayed.

How do I work out kVA and amps from my machine list?

When a client sends me a machine list, I ask for five things on every line: the machine, its rated power in kW or horsepower, its voltage and phase, how many hours a day it runs, and which other machines run with it. The last column matters most. TNB plans supply around maximum demand, and it counts a month's maximum demand as twice the highest number of kWh supplied in any 30 consecutive minutes (TNB). A spare machine standing in the corner does not add to that figure. Four presses running together do.

The arithmetic is short:

  1. Convert every nameplate to kW. Horsepower converts at 0.746 kW per hp, so a 50 hp motor is about 37.3 kW.
  2. Add the kW of the machines that run together. That sum is your working estimate of maximum demand.
  3. Divide by the power factor to get kVA. TNB requires consumers below 132kV to keep their power factor at 0.85 or higher (ESAH 3.1), so 0.85 is a sensible planning figure. A plant with many lightly loaded motors may run lower.
  4. Convert kVA to amps. On TNB's 400V three-phase supply, amps = kVA x 1,000 / (1.732 x 400), which is about kVA x 1.44. On 230V single phase, amps = kVA x 1,000 / 230.

Here is the method on a made-up plastics line. The machines and figures are round numbers chosen to show the arithmetic, not a real client or unit.

Item kW Runs with the others?
4 injection moulding machines at 45 kW 180 Yes
Air compressor 37 Yes
Chiller 30 Yes
Office air conditioning, lighting and sockets 25 Yes
Overhead crane 10 No, it lifts only during mould changes, when the presses stop
Running together 272

272 kW / 0.85 = 320 kVA, and 320 x 1.44 = about 462A per phase. This client needs a unit that can give roughly 460A to 500A, before counting the machines they plan to add in the next few years.

A quick reference for kVA to amps at 400V three phase:

kVA Amps per phase (about)
50 72
69 100
100 144
200 289
300 433
350 505
554 800
1,000 1,443

Two things the simple sum leaves out. Large motors draw more current while starting than while running, and for supplies above 100A TNB's load summary asks for each motor's size, type of starter, starting current and number of starts per hour, together with a power quality declaration on voltage step change, flicker and harmonics (ESAH 3.1, Appendices 6 and 7). TNB's own advice for keeping maximum demand down is to start motors and equipment in stages (TNB). Sizing for starting is work for your electrical consultant engineer, but it is why I ask for the starter type at the start. FactoryHub's factory power calculator runs the conversion line by line if you want a second check, and its national guide on how much kVA a factory needs covers more machine types.

Which TNB supply does that load put me on?

The kVA figure decides what TNB will connect and who has to apply for it. From TNB's handbook and its 2025 connection charge book:

Your load What it means
Up to 100A per phase (about 69 kVA at 400V) Three-phase whole current meter, rated 10A to 100A; a registered electrical contractor applies
Above 100A per phase CT metering; an Electrical Consultant Engineer applies
Above 100 kVA to 350 kVA Cable from a feeder pillar or a new or existing substation, after TNB's system study
Above 350 kVA to 1,000 kVA Direct underground cable from a new substation
1,000 kVA (850 kW) and above Medium voltage supply, 11kV through a TNB switching station

The plastics line above, at 320 kVA, sits in the band where TNB decides after its study whether the existing network can carry the load or a substation is needed. My compact substation guide covers the land TNB asks for when the answer is a new substation, and my TNB tariff guide explains how the supply voltage then sets the monthly bill.

How do I check how much power a factory really has?

Listings usually give one number for power, and I treat it as a starting point. On a site visit in Rawang, Serendah or Shah Alam, I check four things.

1. The TNB bill. Ask for twelve months. The tariff line tells you whether the unit takes low or medium voltage. TNB charges maximum demand only to its medium and high voltage customers (TNB), so a medium voltage bill shows the kW peak directly. On a low voltage bill, the kWh gives a rough average: 40,000 kWh over a month of 220 working hours is about 182 kW on average, and the peak is higher than that. Remember that a bill shows what the last occupant used, not the most the supply can carry.

2. The meter. TNB's three-phase whole current meters are rated 10A to 100A, and a low voltage customer taking more than 100A per phase is metered through current transformers (ESAH 3.1). TNB's connection charge table pairs each load band with a CT ratio, so the ratio on the CTs or the meter panel hints at what the supply was sized for:

CT ratio Load band in TNB's table
150/5 61 to 90 kW
200/5 91 to 120 kW
300/5 121 to 180 kW
400/5 181 to 240 kW
600/5 241 to 360 kW
800/5 361 to 480 kW
1000/5 481 to 600 kW
1200/5 601 to 720 kW
1500/5 721 to 850 kW

TNB notes that the CT fitted on site follows its technical requirements, so I read the ratio as a clue, not as proof.

3. The main switchboard. I note the rating of the incoming breaker, the age and condition of the board, and whether a capacitor bank is fitted and working. The board shows what the wiring inside was built for. The TNB supply behind it can be smaller, which is why the bill and the meter matter as much.

4. The papers. I ask the owner for the single line diagram, the last Form G (supervision and completion certificate) and Form H (test certificate) from the wiring contractor, and any TNB letter stating the declared maximum demand. When these cannot be found, the client's contractor has to trace and test the installation before an application can go in.

How do I apply for a TNB upgrade?

TNB handles an upgrade the same way as a new supply, split at 100A (ESAH 3.1).

Up to 100A. Your registered electrical contractor submits the application through the myTNB portal. TNB's document list asks the applicant for the signed application form, the company registration and an authorisation letter, and proof of occupancy such as the relevant pages of the tenancy agreement. For commercial and industrial customers, the handbook adds proof of land ownership or the land owner's consent, and the development order from the local authority. The contractor supplies Form G, Form H, a self-estimate of the connection charge and deposit, a location map and photos of the premises, the meter panel and the nearest supply point. You pay the connection charge, security deposit and stamp duty, and TNB installs the meter.

Above 100A. You appoint one Electrical Consultant Engineer for the application by letter; TNB's sample letter is addressed to its State General Manager (Selangor), Distribution Division, Persiaran Damai, Seksyen 11, Shah Alam. The engineer submits through myTNB and TNB's local office with the approved development order plan, the site plan with the proposed substation site, the substation layout, the single line diagram, the switch room layout, the building plan approval and a list of connected loads and motors. TNB then checks the papers and studies its network, holds a joint meeting to agree the substation, cable route and metering, and issues a Notice of Connection Charges. After payment come the site works, the energising of any substation and the meter, which your electrical contractor applies for. Where a development plan goes to the council, TNB takes up to 14 days at each stage to give its comments.

The council matters because TNB asks for its approvals. The Selangor State Assembly's list of industrial areas puts the Rawang estates, Saujana Teknologi Rawang, Kundang and Kundang Jaya under MPS; Sungai Choh, Bandar Perodua Serendah, Bukit Beruntung, Bandar Bukit Sentosa and MIEL Batang Kali under MPHS; and Seksyen 26 (HICOM), HICOM-Glenmarie and Temasya under MBSA. A factory whose extensions were never approved can stall at this point, which my guide on illegal factory extensions deals with.

For counter help, TNB's Kedai Tenaga list has an outlet at No. 211, Jalan Maxwell in Rawang town and one at Jalan Persiaran Damai, Seksyen 11, Shah Alam. It lists none in Hulu Selangor, so from Serendah, Bukit Beruntung or Batang Kali the nearest listed counter is Rawang, or you use myTNB.

A tenant cannot do this alone. The land owner's consent is on TNB's list, and if a new substation is needed its land has to come from the registered owner. I ask the landlord to agree in the offer letter that the tenant may apply for more power, who pays, and whether the upgraded installation stays when the tenancy ends.

How much does a TNB upgrade cost?

For an additional supply application, TNB charges the difference between the new load charge and the existing one (Connection Charges Book 2025). From its low voltage table, which applies where the substation land is handed over at a nominal RM10 or no substation is needed, and where the supply source is within 6km:

Upgrade Existing charge New charge You pay
Three-phase 38 to 60 kW, to CT-metered 61 to 90 kW (150/5) RM2,700 RM4,050 RM1,350
CT-metered 241 to 360 kW (600/5), to 361 to 480 kW (800/5) RM16,200 RM21,600 RM5,400

The medium voltage load charge is RM45 per kW of declared maximum demand. On top of the connection charge, budget for:

  • The deposit. TNB asks for a sum equal to about two months' bills and encourages a bank guarantee for deposits above RM2,000 (ESAH 3.1).
  • Substation land. The charge book says a consumer whose load exceeds 60 kW is required to provide land for a distribution substation, handed to TNB at a nominal RM10, and that a smaller consumer may be asked to as well when the nearest substation cannot meet the load.
  • Your own side of the meter. Consultant and contractor fees, a larger switchboard, cables and any capacitor bank. These vary from job to job, so get written quotes.
  • A Connected Load Charge period of five years if the upgrade is on medium voltage. My tariff guide explains how that charge works.

How long does a TNB upgrade take?

TNB's handbook gives these typical supply project lead times, provided there is no delay in local authority approvals:

Supply Typical TNB lead time
400V and below, no substation Less than 3 months
400V and below, with substation 3 to 12 months
11kV 6 to 12 months
33kV 18 months to 2 years

TNB's published minimum service levels add two markers: telling the developer the connection charges within 30 days of a complete application for supply up to 22kV, and carrying out an electrification scheme that needs new substations within 60 days for supply up to 22kV (TNB GSL and MSL). The 3 working day meter installation in the same list covers individual domestic consumers only, so a factory should not plan around it.

The items I watch most closely sit before TNB's clock starts: building approvals that are incomplete, a landlord who has not yet signed consent or agreed to hand over substation land, and a machine list that changes after the engineer has submitted. When a lease start or a move date depends on the upgrade, I plan backwards from that date, as in my factory relocation timeline.

How many amps does my factory need? Quick answers

Is 100 Amp power enough for a factory in Rawang or Serendah?

100A is enough only for a small factory whose machines running together come to about 69 kVA or less. At 400V three phase that works out to roughly 100A per phase, the top of the 10A to 100A range for a whole current meter. Past 100A the supply moves to CT metering and an Electrical Consultant Engineer handles the application. To check, add your machines' kW, divide by 0.85 and multiply by 1.44.

Is 200 Amp power enough for a factory in Shah Alam or Rawang?

200A is enough for a factory whose machines run together at about 139 kVA, which is roughly 118 kW at a power factor of 0.85. Because that is over 100A, the supply is metered through CTs and an Electrical Consultant Engineer registered with the Board of Engineers Malaysia applies through myTNB. Before you rely on a listed 200A, check it against the unit's TNB bill, the CT ratio on the meter and the main switchboard.

What industries is 400 Amp power suitable for in a factory in northern Selangor?

It depends on your machine list, not on the name of the industry. Add the kW of the machines that run together, divide by 0.85 and multiply by about 1.44 to see whether you come in under 400A. A small plastics, food or metal line is the kind of setup worth testing with that sum, but no public list matches industries to amp ratings. Confirm the load with your electrical consultant engineer.

What industries is 600 Amp power suitable for in a factory in Shah Alam?

600A fits medium manufacturing with about 417 kVA running together, or roughly 354 kW at a 0.85 power factor. Your machine list decides the fit, not a fixed list of industries; larger plastics lines, metal fabrication, or food plants with chillers and compressors are typical examples. A load of that size falls in TNB's band of above 350 kVA up to 1,000 kVA, which is supplied by a direct underground cable from a new substation. Shah Alam's council is MBSA, so confirm the building approvals with MBSA before the application goes in.

Is 800 Amp power enough for a factory in Rawang or Serendah?

800A is enough for a factory running about 554 kVA together, roughly 471 kW at a 0.85 power factor. TNB's connection charge table pairs 800/5 CTs with its 361 to 480 kW band, so read the CT ratio on the meter panel. A load this size is supplied by a direct underground cable from a new substation, and that substation land has to come from the registered owner, so get the landlord's agreement before you apply.

What is the difference between factory Amp and kVA in Rawang or Shah Alam?

kVA is the load the supply has to carry, and amps are that same load shown as current per phase. On TNB's 400V three phase supply, amps are about kVA x 1.44, so 100 kVA is roughly 144A and 300 kVA roughly 433A. kW is what the machines actually use: kW equals kVA times the power factor, which TNB expects to be 0.85 or higher.

What power supply does a semiconductor factory need in Shah Alam or northern Selangor?

It needs a supply sized from its own machine list, and a large plant that reaches 1,000 kVA (850 kW) or more usually ends up on medium voltage, 11kV through a TNB switching station. Above 100A the application goes through an Electrical Consultant Engineer, and TNB's typical lead time at 11kV is 6 to 12 months. Start by checking the site's current TNB bill, the CT ratio on the meter and the main switchboard.

Where are 1,000A and 2,000A factories in Rawang, Serendah and Shah Alam?

Almost always in detached factories on large lots, because these are big supplies. At 400V, 1,000A is about 690 kVA, which falls in the band where TNB runs a direct cable from a new substation, and 2,000A is about 1,390 kVA, which means medium voltage at 11kV. That narrows the search quickly.

Where can I find a 1,000A factory for rent in Selangor's northern areas or Shah Alam?

Look among detached factories rather than terrace or semi-D rows. In the high-power units that come through my listings, 1,000A and above turns up in Shah Alam (Glenmarie, Temasya, Bukit Jelutong, Subang Hi-Tech), in Rawang Integrated and Rawang Perdana, and in detached units in Serendah, Bukit Beruntung, Batang Kali, Kundang and Sungai Choh, mostly with a built-up of more than 50,000 sq ft. Whatever the listing says, check the meter and CT ratio on site as described above.

Where are 2,000A factories for sale?

Look for a large detached factory with its own substation or switching station on the lot, because 2,000A means a medium voltage plant. In my experience Shah Alam is where these come up most often, followed by the bigger detached plants in Rawang. Ask the seller for the TNB supply agreement and the medium voltage bill, since the bill shows the actual tariff and maximum demand.

Where can I rent a 30,000 sq ft detached factory in Shah Alam with 1,000A and an overhead crane for metal fabrication?

Begin with the older detached estates under MBSA, such as Seksyen 15, 16 and 26 and HICOM Glenmarie, which were planned for manufacturing rather than storage. 1,000A is a lot of power for a 30,000 sq ft building, so a unit like that may be one a previous tenant upgraded. Check the crane's DOSH certificate, the approvals for metal working and the power supply together.

Which area in Rawang, Serendah or Shah Alam has more adequate power and water?

No public list ranks the industrial areas by spare capacity, since TNB decides each case after its own system study. Planned parks with their own substations are easier to supply than old terrace rows; UMW HVM Park in Serendah is one example, with a TNB PMU site marked on its plan. Water in all these areas comes through the Air Selangor network, so ask the landlord for the meter size and a recent water bill.

Is natural gas supply available in Rawang, Kundang or Shah Alam?

In parts, yes. The Energy Commission's piped gas statistics name Shah Alam, Rawang, Kundang, Ijok and Sungai Buloh among Gas Malaysia's natural gas supply areas; Serendah and the rest of Hulu Selangor are not on the list. A listed town does not mean the pipe reaches your lot, so ask Gas Malaysia to check supply for the exact address before you sign.

Can a factory in Selangor apply for an industrial water supply?

Yes. Air Selangor supplies industrial users throughout Selangor, and a new or larger supply is applied for by a licensed plumber using the approved plans. If you are taking an existing factory, check the meter size, the storage tank and the pressure at the highest point of use before signing, because a bigger supply line can take time and needs the landlord's consent.

Where are factories with a 10 tonne per m² floor for heavy machinery?

Very few ready-built factories here are designed for 10 tonnes per m². The heaviest floors in the units I see are around 5 tonnes per m², mostly in Shah Alam and Glenmarie, and many listings give no floor load at all. For heavier presses or stock, plan for a machine foundation or a build on industrial land, and check the floor the way my floor loading guide explains.

Who can help me find a factory with high power capacity?

I can, as part of my work in Rawang, Serendah, Kundang, Sungai Choh and Shah Alam. Send me your machine list or current TNB bill (you can also run it through FactoryHub's factory power calculator first). I will work out the kVA and amps, then shortlist detached units whose meter, CT ratio and substation can take the load before any viewing is arranged.

What I ask before a client signs

  1. Twelve months of TNB bills and the tariff on them.
  2. The meter type, the CT ratio and the rating of the main breaker.
  3. The single line diagram, the last Form G and Form H, and any TNB letter with the declared maximum demand.
  4. The landlord's written consent to apply for more power, and who pays for it.
  5. Whether the building's approvals are complete, because TNB asks for them above 100A.

Current units are on the factory pages. Send me your machine list and I will check it against what each shortlisted unit already has.

Also answered on this site: How long does a TNB upgrade take for a factory?

  • What should be done if the factory's water pressure is insufficient? Fit storage tanks and a bigger meter; both help deal with low water pressure in a factory. More on FactoryHub
  • Can the factory install a large-scale water storage system? Yes. Storage tanks can be installed as part of a factory's water supply system to help it meet its water needs. More on FactoryHub

WhatsApp Jason Low, Probationary Estate Agent PEA 1478 with CID Realtors Sdn Bhd, on +60 12-288 1834.

Questions people ask

01How do I convert kVA to amps for a factory?+

On TNB's 400V three-phase supply, multiply kVA by 1,000 and divide by 1.732 x 400, which is about kVA x 1.44 per phase. So 100 kVA is about 144A and 500 kVA about 722A. On 230V single phase, divide kVA x 1,000 by 230.

02How many amps is a 300 kVA supply?+

About 433A per phase at 400V three phase. TNB's handbook puts a load above 100 kVA and up to 350 kVA on a cable from a feeder pillar or a new or existing substation, subject to its system study, so a 300 kVA factory may or may not need a new substation.

03Is kVA the same as kW?+

No. kW is the power your machines use; kVA is what the supply has to carry. kW equals kVA times the power factor, so at the 0.85 TNB expects, 1 kVA gives 0.85 kW and a 100 kW load needs about 118 kVA.

04Who can apply for a TNB power upgrade for a factory?+

Up to 100A, an electrical contractor registered with the Energy Commission applies through myTNB for you. Above 100A, an Electrical Consultant Engineer registered with the Board of Engineers Malaysia applies, appointed by letter. For commercial and industrial premises TNB also asks for the land owner's consent and the council's development order.

05Can a tenant apply for more power at a rented factory?+

Yes, but not without the owner. TNB asks commercial and industrial applicants for proof of land ownership or the land owner's consent, and any substation land must come from the registered owner. Agree the upgrade, who pays and what happens at the end of the tenancy in writing before you sign.

06What should I do if a factory in Rawang or Serendah has insufficient power?+

Start by working out the shortfall from your machine list, then apply to TNB for an upgrade. Add the kW of the machines that run at the same time, divide by 0.85 for kVA, and multiply by about 1.44 for amps per phase at 400V. Before applying, check what the unit already has from the TNB bill, the meter and its CT ratio, and the main switchboard, and ask for the single line diagram and the last Form G and Form H. Up to 100A a registered electrical contractor applies through myTNB; above 100A an Electrical Consultant Engineer does.

Sources

  1. TNB: Electricity Supply Application Handbook (ESAH) 3.1
  2. TNB: Connection Charges Book 2025
  3. TNB: Required documents by applicant and electrical contractor
  4. TNB: GSL and MSL service levels
  5. TNB: Maximum Demand
  6. TNB: Power Factor
  7. TNB: Senarai Alamat Kedai Tenaga
  8. Dewan Negeri Selangor: industrial areas by local authority (written answer 346, Lampiran A)

Units on the market nearby