Factory Relocation to Rawang, Serendah or Shah Alam: A Realistic Timeline From Search to Move-In, With TNB, Fit-Out Permits, Licences, Machine Moving and Overlap Rent
A factory relocation to Rawang, Serendah or Shah Alam has no fixed length: the slowest item sets it, usually power. TNB's handbook: under 3 months for 400V without a substation, 3 to 12 months with one. Council fit-out permits, the premises licence, DOSH approval to reinstall boilers, pressure vessels and cranes, and overlap rent fill in the rest.
Key Takeaways
- Power usually decides the move-in date. TNB's Electricity Supply Application Handbook gives a typical supply project lead time of less than 3 months at 400V without a substation, 3 to 12 months at 400V with a substation, and 6 to 12 months at 11kV, provided local authority approvals are not delayed.
- Fit-out needs a council permit before work starts. At MPS (Rawang, Kundang) the counter permit covers gypsum partitions of up to three rooms only; brick walls and other factory partitions go through a submitting person and the One Stop Centre. MPHS (Serendah, Sungai Choh, Bukit Beruntung, Batang Kali) can charge ten times the processing fee for work done before approval.
- The business licence follows the building. MPS's licensing charter promises a decision on technical premises licences within 30 working days, and both MPS and MBSA ask for the unit's CF or CCC.
- Boilers, pressure vessels and cranes need fresh DOSH approval at the new site. Plant that held a certificate of fitness at one location needs written installation approval and a new inspection before it runs at the next one, unless it is portable plant that is not dismantled.
- Overlap rent is the price of the slowest item. Registered median factory rents are RM1.39 psf/month in Rawang and Kundang, RM0.95 psf/month in Serendah and RM1.71 psf/month in Shah Alam, so each extra month at two sites can be priced before you sign.
How long does a factory relocation take, from search to move-in?
There is no single number, and I do not give clients one. What I give them is a sequence. Each stage below has an owner and, where the agency publishes one, a stated processing time. The total is set by the slowest chain, which is almost always power or plan approval, not the lorry that carries the machines.
| Stage | What happens | What the published rules say |
|---|---|---|
| 1. Brief | Floor area, power in kVA, floor load, truck size, type of industry | Your own inputs; every later stage depends on them |
| 2. Shortlist and checks | CCC or CF, title, approved use, existing TNB supply | MPS licenses only units with approved plans and a CF or TCF (MPS licence conditions) |
| 3. Sign | Tenancy, lease or purchase | A lease of more than 3 years is signed with Form 15A and registered at the land office (LHDN stamp duty guideline) |
| 4. Fit-out permits | Partitions, office, mezzanine, additions | MPS: building plans through the OSC processed within 30 working days, subject to compliance; MPHS: simultaneous applications decided within 99 days |
| 5. Power | Upgrade or new supply | From less than 3 months to 12 months or more, by voltage (TNB ESAH) |
| 6. Environment | Boilers, ovens, gensets, effluent | Written notice to the DOE at least 30 days before the work |
| 7. Machines | Dismantle, move, reinstall | New DOSH installation approval and inspection for boilers, pressure vessels and lifting machinery |
| 8. Licence | Business premises licence | MPS: technical licences within 30 working days; MPHS: non-risk licences within 1 working day |
| 9. Hand back | Old factory reinstated and returned | Set by your old tenancy agreement |
I plan backwards from the last day of the old tenancy. If the new unit needs a substation and the old lease ends in six months, the dates do not work however fast the rest goes, and it is better to know that before the deposit is paid. If you have not started the search yet, my notes on what to check before renting a factory in Rawang cover the shortlist stage.
Why is the TNB upgrade usually the slowest part?
TNB's handbook says the lead time for a supply connection depends on the type of premises, the electrical load, the location and approval from the local authorities. Its typical lead times are:
| Supply | Typical TNB lead time |
|---|---|
| 400V and below, no substation | Less than 3 months |
| 400V and below, with substation | 3 to 12 months |
| 11kV | 6 to 12 months |
| 33kV | 18 months to 2 years |
The handbook also ties the supply scheme to maximum demand. An individual non-domestic consumer up to 100kVA is normally supplied at 400V from the existing low voltage network, subject to TNB's system study. Above 100kVA and up to 350kVA the cable comes from a feeder pillar or a new or existing substation. Above 350kVA and up to 1,000kVA it is a direct underground cable from a new substation. From 1,000kVA the supply moves to 11kV or 22kV through a TNB switching station.
So the first question I ask on any unit in Rawang or Serendah is how many kVA the client's machines will draw, and what the incoming supply on the main switchboard is rated for. If the answer means a new substation, the move sits in the 3 to 12 month band, and no amount of pushing on the fit-out changes that.
Two paperwork points catch people out. For supply above 100A, the handbook's list for the electrical consultant includes the development order plan approved by the local authority and the building plan approval, and its lead times assume no delay in local authority approvals, so where the move involves building works, power waits for the council. And TNB asks for a deposit equal to two months' bill on its notice of deposit, with a bank guarantee encouraged for deposits above RM2,000. My guides on the TNB compact substation and on TNB tariffs for a factory cover the substation land and the bill.
Which council permits does the fit-out need in Rawang, Serendah and Shah Alam?
Settle the council first, because a postal address can mislead. The Selangor state assembly's list of industrial areas by local authority puts the Rawang estates and Kundang under MPS; Sungai Choh, Serendah, Bukit Beruntung, MIEL Batang Kali and UMW High Value Manufacturing Park under MPHS; and Seksyen 15, 16 and 26 (HICOM), HICOM-Glenmarie and Temasya under MBSA.
- MPS (Rawang, Kundang). The internal partition permit checklist JB-B07 asks for the owner's letter, the title or a tenancy agreement still in force, sketch floor plans, the paid assessment bill, the CCC and photos. The fee is RM100 per application, RM50 per new room and RM5 for the approval sticker. The counter permit only covers gypsum board walls for up to three rooms, with no brick or permanent concrete walls. New brick walls, breaking a party wall, and factory partitions in anything other than gypsum board or glass must be submitted by a principal submitting person through the One Stop Centre. The MPS Building Department charter processes building plans through the OSC within 30 working days of receipt, subject to compliance, and the OSC charter circulates complete applications within 2 working days and tells applicants the committee's decision within 2 working days after the meeting.
- MPHS (Serendah, Sungai Choh, Bukit Beruntung, Batang Kali). The minor works permit checklist for non-residential buildings asks for the tenancy agreement, the CF or CCC, the latest assessment receipt and proof that a registered RORO bin contractor has been appointed, with a RM100 processing fee. It warns that no work may start before approval, and that a breach can cost ten times the processing fee under the building by-laws. The MPHS customer charter promises a decision on simultaneous applications within 99 days of receipt.
- MBSA (Shah Alam). MBSA's development FAQ says partitions added in commercial and industrial buildings need a temporary building permit, citing sections 79(1) and 79(4) of the Street, Drainage and Building Act 1974.
If heavy machines or racking are part of the plan, check the slab before the layout is drawn; my floor loading guide explains what the numbers mean.
When can the new business premises licence be issued?
Council licensing comes after the building is in order, not before it. MPS's licence conditions require planning approval or a development order, approved building plans and a CF or TCF, and compliance with the Health Department and Bomba, and they forbid alterations to a licensed building without permission. The MPS licensing charter decides instant premises licences within 1 hour of paying the processing fee, technical premises licences within 30 working days, and brings complete critical or risk licence applications to its business control and health committee within 60 working days. MPHS's charter decides non-risk licences within 1 working day. At MBSA the composite licence page lists a RM100 processing fee for industrial premises, and its application flow chart sends the file to the technical departments for a site inspection and then to a committee meeting before the decision letter goes out.
Bomba sits inside this chain; my guide on the Bomba fire certificate explains which factories need one. If your process counts as medium or heavy industry, Ms Teh's page on light, medium and heavy industry explains why some estates will not take it.
Larger manufacturers have one more licence to move. MIDA says companies with shareholders' funds of RM2.5 million and above, or 75 or more full-time paid employees, need a manufacturing licence. Section 4 of the Industrial Co-ordination Act 1975 issues a separate licence for each place of manufacturing activity and lets its conditions be varied on the manufacturer's application, so speak to MIDA before you commit to the new address.
What does DOSH require when you move boilers, air receivers and cranes?
Since 1 June 2024 the certificate of fitness rules sit in the Occupational Safety and Health Act 1994. Section 27C bars anyone from installing prescribed plant without the Director General's written approval, and section 27D bars operating it without a certificate of fitness; the penalty for operating without one is a fine of up to RM100,000, up to a year in prison, or both. The Plant Requiring Certificate of Fitness Regulations 2024 prescribe three kinds of plant: steam boilers, pressure vessels and lifting machinery.
The relocation rule is regulation 4(3). Plant that was issued a certificate of fitness for a specific location but will be relocated needs a new application for written approval to install it at the new location. Regulation 5(5)(b) keeps a certificate valid after a move only for plant that operates in portable form without being dismantled. The inspection includes functional tests of the safety devices, plus a load test for lifting machinery, and the new certificate runs for fifteen months from the inspection date. So the air receiver, steam boiler or overhead crane at your old factory is a permit item on the timeline, not just a rigging job. I tell clients to book the machine mover only after they know when the inspection can happen.
The environment side has a fixed notice period. Regulation 5 of the Environmental Quality (Clean Air) Regulations 2014 requires written notification to the DOE at least thirty days before work that may result in a source of emission, and its definition of fuel burning equipment includes boilers, ovens and internal combustion engines. If the move adds a wastewater discharge, read my factory wastewater guide before you sign.
How much overlap rent should you plan for?
Overlap rent is the months you pay for two factories. It starts when the new tenancy starts and ends when the old factory is handed back in the condition the old agreement asks for, which can mean taking down partitions, filling anchor holes and removing your own electrical work. Registered tenancies give a fair base for pricing it. In JPPH-registered tenancies over the 24 months up to August 2026, the median factory rent is RM1.39 psf/month in Rawang and Kundang, RM0.95 psf/month in Serendah and RM1.71 psf/month in Shah Alam. The typical registered term is 24 months in Rawang and Shah Alam and 21 months in Serendah, so many tenants meet this question every two years.
What I do to keep the overlap short:
- Put the rent start date and any fit-out period in the offer letter, in writing, before the deposit is paid.
- Ask the landlord at the offer stage to sign the owner's letters that permits need. The MPS partition permit, for one, starts with an application letter from the owner.
- Read the reinstatement clause of the old tenancy now and plan that work into the overlap months.
- Time the notice on the old lease to the slowest item on the list, not to the move date you hope for.
- Price the stamp duty of the new tenancy with FactoryHub's tenancy stamp duty calculator.
What I check on the first site visit for a relocating client
- The rating of the main switchboard and the maximum demand on the last TNB bill, against the client's kVA.
- A copy of the CCC or CF and the approved building plan, and whether the planned use matches them.
- Whether the unit held a premises licence for a similar activity before.
- The floor slab and room for machine foundations.
- Truck access and the loading bay for the machine mover's trailer.
- How quickly the landlord will sign permit applications.
Units I can show in these areas are on the Rawang factory for rent page and the Shah Alam area page.
Planning a move to Rawang, Serendah, Kundang, Sungai Choh or Shah Alam? WhatsApp Jason Low, Probationary Estate Agent PEA 1478 with CID Realtors Sdn Bhd, on +60 12-288 1834.
Also answered on this site: How long does a TNB upgrade take for a factory?
Questions people ask
01How long does it take to relocate a factory in Malaysia?+
It depends on the slowest item, which is usually the power supply. TNB's handbook gives under 3 months at 400V without a substation, 3 to 12 months with one and 6 to 12 months at 11kV, provided council approvals are not delayed. Council permits, the premises licence and DOSH approval for boilers, pressure vessels and cranes run alongside it.
02Do I need a new business licence when my factory moves?+
Yes. Council premises licences are issued for a premises, and MPS, for example, will only license a unit that has planning approval, approved building plans and a CF or TCF. Companies that hold a MIDA manufacturing licence should also talk to MIDA, because the Industrial Co-ordination Act 1975 issues a separate licence for each place of manufacturing activity.
03Can I move my boiler or air receiver to the new factory with its old certificate of fitness?+
Usually not. Regulation 4(3) of the 2024 certificate of fitness regulations requires a new application for written approval to install the plant at the new location, followed by an inspection. Only plant that operates in portable form without being dismantled keeps its certificate after a move.
04Do partitions and an office inside a factory need council approval?+
Yes. MPS issues a counter permit only for gypsum board partitions of up to three rooms, and anything heavier goes through a submitting person and the One Stop Centre. MBSA requires a temporary building permit for partitions in industrial buildings, and MPHS does not allow minor works to start before approval.
05How can I reduce overlap rent when moving factories?+
Plan backwards from the end of the old tenancy, and time your notice to the slowest item, usually power or plan approval. Put the rent start date and fit-out period in the offer letter, and read the reinstatement clause of the old lease early. Registered median rents of RM1.39 psf/month in Rawang and Kundang, RM0.95 in Serendah and RM1.71 in Shah Alam help you price each overlap month.
06Where can I find a factory in Rawang or Shah Alam that is ready to move in?+
A unit is ready to move in only when its power supply, approved plans and CF or CCC already fit the use you have in mind. In Rawang and Kundang, compare the incoming supply rating on the main switchboard with the kVA your machines need, because a new substation can add 3 to 12 months. In Shah Alam, MBSA asks for the CF or CCC, and partitions need a temporary building permit. Before you sign, ask the landlord for the CCC, the approved plans and the latest TNB bill.
07How do you calculate factory relocation costs in Rawang, Serendah or Shah Alam?+
Total the one-off costs of the move, then add overlap rent for each month you pay for two factories. The one-off costs are the fit-out permit fees, moving the machines and their DOSH re-inspection, the new premises licence and the stamp duty on the new tenancy. To price the overlap, multiply your floor area by the registered median factory rent: RM1.39 psf/month in Rawang and Kundang, RM0.95 psf/month in Serendah and RM1.71 psf/month in Shah Alam.
08What is the impact of moving a factory from northern Selangor to a different state?+
You go through the council and state approvals again from the start, because MPS and MPHS licences only cover premises inside their own areas. The premises licence, the fit-out permits and any MIDA manufacturing licence all have to be dealt with again at the new site, since the Industrial Co-ordination Act 1975 issues a separate licence for each place of manufacturing activity. The power application also starts over with the local utility, so its lead time runs from that point.
Sources
- TNB: Electricity Supply Application Handbook (ESAH) 3.1, sections 1.3.5 supply project lead time, 1.3.6 application documents and deposit, Table 3-1 minimum supply schemes
- Occupational Safety and Health Act 1994 (Act 514), reprint as at 1 June 2024, sections 27B to 27E (DOSH)
- Occupational Safety and Health (Plant Requiring Certificate of Fitness) Regulations 2024, P.U.(A) 99/2024, regulations 3, 4(3), 5(5) and 5(6) (DOSH)
- Environmental Quality (Clean Air) Regulations 2014, P.U.(A) 151/2014, regulations 2, 5 and 7 (DOE eSWIS)
- Industrial Co-ordination Act 1975 (Act 156), section 4 (AGC)
- MIDA: Approval and Licensing, manufacturing licence thresholds
- Majlis Perbandaran Selayang: licence application and approval conditions
- Majlis Perbandaran Selayang: Licensing Department customer charter
- Majlis Perbandaran Selayang: Building Department customer charter
- Majlis Perbandaran Selayang: One Stop Centre customer charter
- Majlis Perbandaran Selayang: checklist JB-B07, internal partition permit (updated 7 July 2025)
- Majlis Perbandaran Hulu Selangor: customer charter
- Majlis Perbandaran Hulu Selangor: checklist for minor works permits, non-residential buildings
- Majlis Bandaraya Shah Alam: Lesen Komposit (Perniagaan / Perindustrian), processing fees
- Majlis Bandaraya Shah Alam: composite licence application flow chart
- Majlis Bandaraya Shah Alam: development FAQ, partitions in commercial and industrial buildings
- Dewan Negeri Selangor: industrial areas by local authority (written answer 346, Lampiran A)
- LHDN: guideline on stamp duty under the First Schedule of the Stamp Act 1949 (leases over 3 years, Form 15A)
- FactoryHub: Rawang and Kundang JPPH-registered transaction prices and rents
- FactoryHub: Serendah JPPH-registered transaction prices and rents
- FactoryHub: Shah Alam JPPH-registered transaction prices and rents
Units on the market nearby
Semi-D Factory for Rent in Saujana Teknologi Rawang, Rawang, 6,525 sq ft
RM 10,500/month
Semi-Detached Factory for Sale or Rent in Saujana Rawang, Rawang, 8,000 sq ft
RM 4,000,000 · RM 15,000/month
Detached Factory for Rent in Batu 17 Rawang, 9,000 sq ft
RM 21,000/month
More on choosing an area or industrial park
- Detached, Semi-D or Terrace Factory in Rawang, Serendah and Shah Alam: Land, Access, Power, Price and Which Suits Your Operation
- Taman Industri Bolton, Batu Caves: Terrace Factory Prices, MPS Licence Rules and What to Check Before You Buy or Rent
- Mah Sing Integrated Industrial Park, Seksyen U5 Shah Alam: Lease Expiry, Who Is There and What to Check Before You Buy or Rent
- Kawasan Perindustrian Rawang Perdana: Who Is There, Older Factories vs New Projects, and What to Check Before You Buy or Rent