TNB Power Upgrade for a Factory in Rawang, Serendah or Shah Alam: Who Pays, What to Do When the Landlord Says No, Substations and Going Up to 3,000A

Written by , PEA 1478 · Published · Power, height, floor and access

Short answer

TNB charges the applicant, usually the tenant, the load charge difference plus a deposit of about two months' bills. An industrial premises also needs the land owner's consent, so the landlord decides. Above about 505A a new substation on the owner's land is required; from 1,000 kVA (about 1,443A) supply moves to 11kV with the factory's own substation.

A detached factory at golden hour with a new compact substation on a concrete plinth inside the front fence and an open cable trench leading to the building.
Illustrative image

Key Takeaways

  • The tenancy, not TNB, decides who pays. TNB charges whoever applies: for an upgrade, the difference between the new and the existing load charge (TNB Connection Charges Book 2025), plus a deposit of about two months' bills (TNB ESAH 3.1). Whether the landlord shares any of it is a term you negotiate.
  • A tenant cannot upgrade a factory's supply without the owner. For commercial and industrial premises, TNB's handbook asks for proof of land ownership or the land owner's consent, plus the council's development order. A landlord who will not sign stops the application.
  • The size of the jump decides the scheme. Above 350 kVA (about 505A at 400V) TNB feeds the factory by direct cable from a new substation on land the owner provides. From 1,000 kVA (about 1,443A) supply moves to 11kV and the factory provides its own consumer substation. A 3,000A plant is about 2,078 kVA, so it is an 11kV project.
  • The cost has two halves. TNB's half is published: going from the 181 to 240 kW band to the 361 to 480 kW band costs RM21,600 minus RM10,800, or RM10,800. Your half (consultant, contractor, switchboard, cables and, at 11kV, transformers and switchgear) has no published price, so get written quotes.
  • When the landlord says no, find out why. The owner may be asked to give TNB a piece of land for RM10, approve building works and, at 11kV, live with a connected load charge period that can outlast a short tenancy. Answer those in writing; if that fails, cut your kVA or move to a unit that already has the power.

Who pays for a factory power upgrade, the landlord or the tenant?

No law splits it. TNB deals only with the applicant. Under its Electricity Supply Application Handbook (ESAH 3.1), TNB issues a Notice of Connection Charges to the Electrical Consultant Engineer and the consultant or applicant pays it; the applicant also places a deposit equal to about two months' bills, and TNB encourages a bank guarantee for deposits above RM2,000. For an additional supply application, the 2025 connection charge book charges the difference between the new load charge and the existing one. Everything else sits between landlord and tenant, so it has to be written into the tenancy agreement or a side letter.

When a client needs more power than a unit has, I break the cost into the items below before we make an offer, because each item has a natural owner and a different life after the tenancy ends.

Cost item Who TNB or the rules put it on My starting proposal
Difference in load charge The applicant, normally the account holder Tenant, because the extra load is its machines
Deposit of about two months' bills The account holder Tenant; the deposit is held by TNB, not by the landlord
Land for a new substation The consumer or developer provides it; only the registered owner can hand it over Landlord signs; tenant pays the surveyor, soil report and legal costs
Compact substation plinth and unit TNB, for applications submitted after 22 November 2024 (TNB CSU guidelines) Nothing to split
Consultant engineer, contractor, switchboard, cables No published rate Tenant, with the landlord's engineer approving the drawings
Reinstatement when the tenancy ends Whatever the tenancy says The upgraded supply stays, with no claim either way

The last row matters more than it looks. A larger supply is not something a tenant can pack up and take away, so I ask the landlord to agree in writing that it stays and that the tenant does not have to reverse it. That is the "items that stay" list in my guide to tenant renovations and reinstatement. When the upgrade is the landlord's idea, for example to make an older unit easier to let, the same table runs the other way and the cost becomes part of the rent discussion covered in my factory rent negotiation guide.

Can a tenant apply to TNB for more power without the landlord?

Not for a factory. TNB accepts the relevant pages of a tenancy agreement as proof that the applicant occupies the premises (TNB required documents). But Appendix 3 of ESAH 3.1 lists two additional documents that commercial and industrial customers must provide under the amended Electricity Supply Act 1990: proof of land ownership or consent from the land owner, and the development order from the local authority. Above 100A, the Electrical Consultant Engineer's submission also carries the approved development order plan, a site plan with the proposed substation sites, the single line diagram and the approval of the building plans. Those are the owner's papers.

So the landlord's signature is the gate. The consent letter I ask an owner to sign covers five points:

  1. Consent for the tenant to apply to TNB for a stated load in kVA, through a named consultant.
  2. Agreement to hand over substation land if TNB requires it, and to sign the transfer or lease.
  3. Access to the site for TNB, the consultant and the contractor.
  4. Approval of the switchroom, cable trench and switchboard works, subject to council permits.
  5. What happens to the installation and the TNB account when the tenancy ends.

Why would a landlord refuse a power upgrade, and what can I do?

A refusal often makes more sense once you list what the owner is being asked to give.

The land. TNB's charge book requires a consumer whose load exceeds 60 kW to provide land for a distribution substation, handed to TNB at a nominal RM10, and ESAH 3.1 adds that TNB has the right to use that substation to supply other consumers. For a compact substation the plot is 5m x 7m, and the applicant must obtain planning permission or authorisation from the council or land office, have a licensed land surveyor confirm the site is free of legal issues, encroachment and existing utilities, and submit a soil investigation report (TNB CSU guidelines). For the owner, that is a permanent piece of the lot going to TNB.

The building works. A switchroom, a cable trench across the yard and a larger main board are building works under the council that covers the estate. The Selangor State Assembly's list of industrial areas places the Rawang estates, Saujana Teknologi Rawang and Kundang under Majlis Perbandaran Selayang (MPS); Sungai Choh, Serendah, Bukit Beruntung, MIEL Batang Kali and UMW High Value Manufacturing Park under Majlis Perbandaran Hulu Selangor (MPHS); and Seksyen 15, Seksyen 16, Seksyen 26 (HICOM) and Temasya under MBSA.

The years after the tenant leaves. An upgrade to 11kV brings TNB's connected load charge (CLC). Under the 2025 charge book, a low voltage consumer that needs a voltage upgrade to medium voltage is treated as a new supply application with a six-year CLC period, and any shortfall against the reference maximum demand is surcharged at RM8.50 per kW. A later occupier who takes over the supply under a change of tenancy carries the remaining CLC period. Medium voltage consumers that terminate supply within five years also pay liquidated damages of 1/120 of TNB's net project cost for each month short of 60 months, capped at half of it. An owner offered a 2+1 tenancy can fairly ask who carries that after year three.

What I do next, in this order:

  1. Get the reason in writing. A "no" to the land is a different problem from a "no" to the cost or to the works.
  2. Offer a package that answers it. The tenant pays TNB and its own side; the landlord's engineer approves the drawings; the upgraded supply stays with no reinstatement claim; and a lease term or renewal option long enough to cover the CLC years, which my lease term guide discusses.
  3. Read the alterations clause. If the agreement says the landlord's consent will not be unreasonably withheld, ask your lawyer what that gives you before you press the point.
  4. Cut the kVA instead. TNB asks customers at 33kV and below to keep their power factor at 0.85 or higher, surcharges anything lower and suggests a capacitor bank (TNB power factor). Because kVA is kW divided by power factor, 300 kW at 0.75 needs 400 kVA, while at 0.95 it needs about 316 kVA. TNB also suggests starting motors and equipment in stages to keep maximum demand down (TNB maximum demand). Sometimes that keeps the load inside the supply the unit already has.
  5. Look at standby generation. ESAH 3.1 allows standby generators subject to the relevant laws, kept as a separate system from TNB's network, declared to TNB and governed by the Energy Commission. Ask your engineer what licence or registration your set needs before you budget for it.
  6. Move. If none of this works, a unit that already has the supply is quicker than any upgrade. My kVA and amps guide shows how I check what a unit really has.

How much does a TNB power upgrade cost, from 400A to 800A or up to 3,000A?

TNB's side is fixed by its Connection Charges Book 2025. The low voltage rates apply where substation land is handed over at RM10 or no substation is needed, and where the supply source is no more than 6km away. Beyond 6km, additional cable charges apply, and work that a council or agency requires beyond TNB's standard, such as drilling under a road, is charged to the consumer.

Three worked examples, with amps at 400V three phase and kW at a power factor of 0.85. They illustrate the arithmetic and are not a quotation.

Upgrade TNB's load bands TNB load charge you pay What else changes
Single phase to three phase, small unit Non-domestic three phase: RM1,700 for 11 to 37 kW, RM2,700 for 38 to 60 kW The difference from your single phase charge (RM450 overhead or RM1,700 underground for non-domestic up to 10 kW) A registered electrical contractor applies
400A (about 277 kVA, 236 kW) to 800A (about 554 kVA, 471 kW) From 181 to 240 kW (RM10,800) to 361 to 480 kW (RM21,600) RM10,800 Above 350 kVA: new substation on the owner's land; CT ratio from 400/5 to 800/5; consultant engineer applies
3,000A (about 2,078 kVA, 1,767 kW) Medium voltage: RM45 per kW of declared maximum demand RM79,515 at 1,767 kW, less any credit for your existing load charge 11kV from a TNB switching station; your own substation; CLC and liquidated damages apply

For the 3,000A line, the book's upgrade rule is that you pay the difference between the new and the existing load charge, so ask TNB in writing how the load charge already paid at low voltage is credited when the supply moves to 11kV.

On top of the load charge, budget for:

  • The deposit, about two months' bills.
  • Your own substation at 11kV. TNB's handbook feeds loads from 1,000 kVA to below 5,000 kVA through a TNB 11kV switching station and notes that land for an additional main distribution substation (PPU) may be needed after its study. The step down to 400V happens in a consumer substation and switchroom you provide. TNB lays and maintains the service cable from its substation to yours only within 30 metres; a longer cable is at your cost. TNB publishes no price for consumer transformers, switchgear or the building, so ask the consultant to price them by transformer rating, number of units and switchgear type.
  • Running it. Under regulation 67 of the Electricity Regulations 1994, a low voltage installation supplied through switchgear rated at 100A or more needs at least one inspection visit a month by a competent person. From 600V to 11,000V it is two visits a month, by an Electrical Services Engineer or a Competent Electrical Engineer.
  • Cancelling. If you cancel before TNB starts work, TNB keeps an administration fee of 10% of the connection charge paid, up to RM5,000, at low and medium voltage.

To turn a machine list into kVA and amps before any of this, FactoryHub's factory power calculator works through it line by line.

For upgrade costs and timelines outside these three areas, see FactoryHub's TNB power upgrade cost guide.

How long does a TNB upgrade take in Rawang, Serendah and Shah Alam?

ESAH 3.1 gives these typical lead times, provided there is no delay in local authority approvals:

Supply after the upgrade Typical TNB lead time
400V, no new substation Less than 3 months
400V, with a new substation 3 to 12 months
11kV 6 to 12 months

TNB's minimum service levels add two markers for supply up to 22kV: the connection charges notified within 30 days, and an electrification scheme that needs new substations carried out within 60 days.

What stretches the time sits mostly outside TNB. Above 100A, the application starts with the authorities' stage: the council registers the development plan with TNB, TNB studies its network and agrees the substation number, size and site with the consultant, and the approved plan is valid for two years. A factory whose extensions were never approved by MPS, MPHS or MBSA can stall here. The handbook also warns that a delay in transferring the substation land title may affect the project, and where no title exists yet the applicant gives TNB a 12-month bank guarantee, renewed until the transfer or lease is registered. If your consultant disagrees with TNB's proposal, the handbook lets the matter go to TNB's State General Manager. When a move-in date depends on the upgrade, I tie the rent-free period to TNB's milestones rather than to a calendar date.

Is there enough power in my industrial estate?

No listing can tell you. TNB's handbook makes every three-phase scheme above 12 kVA "subject to system capability study by TNB", and if its study finds a higher scheme is needed to give quality supply, the higher scheme prevails. The real answer arrives when the consultant engineer submits.

What I check before that point in Rawang, Serendah and Shah Alam:

  1. Where the unit is fed from. I note the nearest TNB substation and feeder pillar; photos of the nearest supply point are part of the contractor's submission anyway.
  2. What the developer planned. In a newer managed park, the master plan may show TNB sites. My UMW HVM Park guide notes the park's plans mark a TNB main intake (PMU) site and reserve land.
  3. Whether there is room for a substation. A semi-detached factory with a full yard may have no 5m x 7m plot at the front, which my compact substation guide explains.
  4. A condition in the offer. For a large jump, I suggest the consultant meets TNB before the tenancy is signed and that the offer lets the tenant withdraw, with deposits returned, if TNB's scheme or cost goes beyond an agreed limit.

What I put in the offer letter before a power upgrade

  1. The load the tenant needs, in kVA and amps, from the machine list.
  2. The landlord's consent to apply, and to hand over substation land if TNB asks.
  3. Who pays each item in the cost table above.
  4. A rent-free or reduced-rent period tied to TNB's lead time.
  5. That the upgraded supply stays at the end, with no reinstatement claim.
  6. The withdrawal condition if TNB's scheme moves to 11kV or the cost passes an agreed figure.

Units that may already have the power you need are on the factory pages, and my TNB tariff guide shows how the new supply changes the monthly bill.

WhatsApp Jason Low, Probationary Estate Agent PEA 1478 with CID Realtors Sdn Bhd, on +60 12-288 1834.

Questions people ask

01How much does it cost to upgrade TNB power for a factory?+

TNB's part is the difference between the new and existing load charge in its 2025 connection charge book, for example RM10,800 to move from the 181 to 240 kW band to the 361 to 480 kW band, plus a deposit of about two months' bills. The consultant, contractor, switchboard, cables and any 11kV equipment are quoted separately, because TNB publishes no rates for them.

02How long does TNB take to upgrade a factory's supply?+

TNB's handbook gives less than 3 months at 400V without a new substation, 3 to 12 months with one, and 6 to 12 months at 11kV, provided local authority approvals are not delayed. Landlord consent, substation land and complete building approvals are the steps to line up early.

03How do I apply for three-phase supply for a small factory?+

Up to 100A, an electrical contractor registered with the Energy Commission applies through myTNB with the application form, company registration, an authorisation letter and the tenancy agreement pages. For industrial premises TNB also wants the land owner's consent and the council's development order. A non-domestic three-phase supply costs RM1,700 for 11 to 37 kW and RM2,700 for 38 to 60 kW, less what your single-phase supply already carried.

04Does my factory need its own substation?+

Above 350 kVA, about 505A at 400V, TNB requires supply by direct cable from a new substation on land the owner provides, while 100 to 350 kVA depends on TNB's study. Below 1,000 kVA the substation equipment is TNB's; from 1,000 kVA supply moves to 11kV and the factory provides its own consumer substation and switchroom.

05How much does a transformer cost for a factory?+

Below 1,000 kVA you do not buy one: TNB installs the substation equipment, and for compact substation applications after 22 November 2024 it also builds the plinth at its own cost, while the owner provides the land. At 11kV the transformers sit in your own substation, and TNB publishes no price, so ask your consultant engineer to quote by rating, number of units, switchgear and building.

06Can a factory get 3000A?+

Yes, but not as a 400V supply from TNB. 3,000A at 400V is about 2,078 kVA, above the 1,000 kVA limit for low voltage, so TNB supplies at 11kV through a switching station and the factory steps it down in its own substation. Expect a load charge of RM45 per kW of declared maximum demand, a six-year connected load charge period and two competent person inspections a month.

Sources

  1. TNB: Electricity Supply Application Handbook (ESAH) 3.1
  2. TNB: Connection Charges Book 2025
  3. TNB: Required documents by applicant and electrical contractor
  4. TNB: Compact Substation Unit (CSU) installation guidelines
  5. TNB: GSL and MSL service levels
  6. TNB: Power Factor
  7. TNB: Maximum Demand
  8. Suruhanjaya Tenaga: Electricity Regulations 1994
  9. Dewan Negeri Selangor: industrial areas by local authority (written answer 346, Lampiran A)
  10. FactoryHub: factory power calculator

Units on the market nearby

More on power, height, floor and access

All guides: Power, height, floor and access →

Probationary Estate Agent · PEA 1478 · CID Realtors Sdn Bhd E(1) 1855About Jason → · Contact →
Ask Jason about this