Renting a Factory Without CCC or CF in Rawang, Serendah or Shah Alam: Licence, Bomba, Insurance and What to Check Before You Sign

Written by , PEA 1478 · Published · Updated · Renting a factory or warehouse

Short answer

Usually not on normal terms. MPS, MPHS and MBSA want a CF or CCC before licensing a factory, and occupying a building without a CCC is an offence for the occupier and the permitting owner, with fines up to RM250,000. Selangor's KTK programme is the exception. Ask for the Form F or CF and approved plan before signing.

A row of older terrace factories with half-open roller shutters, a rusty metal lean-to shed added at one side and a blank clipboard on a table in the forecourt.
Illustrative image

Who can help me check a factory in Rawang, Serendah or Shah Alam that is missing its CCC or CF?

Send Jason Low (PEA 1478) of CID Realtors, via klangindustrial.my or 012-288 1834, the unit address or listing, your intended use, floor size, business licence needs, budget and timing. He can check actual availability, shortlist alternatives, request the CCC or CF copy, approved plans and title from the owner, and line up independent checks by your architect, lawyer and insurer. He cannot confirm approvals or promise retrospective regularisation.

Jason Low · PEA 1478 · 012-288 1834

Key Takeaways

  • No CF or CCC usually means no licence. MPS (Rawang, Kundang) and MBSA (Shah Alam) list a CF or CCC among their licence conditions or documents, and MPHS (Serendah, Sungai Choh, Bukit Beruntung, Batang Kali) makes a CFO or CCC a general licence condition.
  • Occupying the building is itself an offence. Section 70(27)(f) of the Street, Drainage and Building Act 1974 covers anyone who occupies a building without a CCC and anyone who permits it to be occupied: a fine of up to RM250,000, up to ten years in jail, or both.
  • The KTK programme is the only regular way round it. Selangor's programme for factories built without permission runs until 31 December 2027 with temporary permits and temporary licences. It is a holding position, not an approval.
  • Bomba and the insurer look at the same gap. The fire certificate form asks for the approved plan reference numbers, and a business fire policy can be avoided or a claim reduced when a relevant fact was not disclosed.
  • Check before any money changes hands. Ask for the Form F or CF and the approved plan, match them to the building, and make the licence a condition of the tenancy.

What do CCC and CF actually mean for a factory?

The CF, or certificate of fitness for occupation, was issued by the local council. From 12 April 2007, when the Street, Drainage and Building (Amendment) Act 2007 came into force, the CCC replaced it, as the Malaysian Bar explains. So an older terrace factory in Rawang or Bukit Beruntung should have a CF, and a newer semi-D in Serendah or a detached unit in Shah Alam should have a CCC.

Under by-law 25 of the Selangor Uniform Building By-Laws, the CCC is Form F. It is signed by the principal submitting person, a registered architect, engineer or building draughtsman, once the council's technical conditions are met, the stage certificates (Forms G1 to G21) are in, and the essential services such as access roads, drains, water, electricity, fire hydrants and sewerage are in place. A partial CCC (Form F1) can cover part of a building. Within 14 days the submitting person must deposit a copy with the council and with the Board of Architects or Board of Engineers.

When a landlord tells me a unit has "no CCC", I first work out which of three situations it is, because the answer is different for each:

  1. The certificate exists but the copy is lost. This is a paperwork job for the owner, not a reason to walk away.
  2. The original building has a CF or CCC, but parts were added later. A side shed, mezzanine or enclosed loading bay is outside that certificate. My guide on unapproved factory extensions covers how councils treat those.
  3. The building never had approved plans. This is a KTK factory (kilang tanpa kebenaran), sometimes standing outside an industrial zone. This is the case the rest of this guide is mostly about.

FactoryHub's overview of renting a factory without CF or CCC covers the same question for the rest of Malaysia.

Can a tenant get a business licence for a factory without a CCC or CF?

On the normal route, no. The three councils in my areas put the building's certificate in front of the business licence:

  • MPS (Rawang, Kundang). Its approval conditions require planning approval or a Development Order, approved building plans and a CF or TCF, plus Health Department and Bomba requirements.
  • MPHS (Serendah, Sungai Choh, Bukit Beruntung, Batang Kali). Its composite licence form asks for a copy of the CF. General condition 11 requires a CFO or CCC and that the premises are confirmed safe for the business, and condition 9 allows making and processing only in premises with industrial or factory status. A manufacturing applicant also attaches Bomba approval, DOE approval where the process needs it, and DOSH machinery certificates.
  • MBSA (Shah Alam). Item 7 of its general licence checklist, amended 29 August 2025, is a copy of the CF or the CCC (Form F).

The exception is a factory already inside Selangor's KTK programme. MBSA's special checklist has a separate list for an industrial licence without a CF under the KTK programme, built around a current KTK confirmation form from the Planning Department and a certified title from an e-Tanah search. For the full document lists at each council, see my guide to the business premise licence for a factory.

How does a KTK factory stay licensed, and what does that mean for a tenant?

In November 2024 the state said its programme to legalise unlicensed factories would run until 31 December 2027, with applications due by 31 December 2025, and that participants get land premium discounts for land conversion, relaxed technical requirements and temporary business licences (The Star). In April 2026 the state assembly heard that 4,170 KTK had been identified across Selangor (Utusan Malaysia).

The MPS temporary building permit form for the KTK programme, updated 5 March 2026, shows what sits behind a KTK unit in Rawang or Kundang:

  • A submitting person files as-built plans, and the bill includes a penalty of five times the permit fee.
  • The owner signs a sworn undertaking taking full responsibility for the building, and a valid tenancy agreement with the stated activity is attached where the unit is let.
  • An application without a copy of the KTK certificate is rejected.
  • The temporary permit fee is RM10 per 9 square metres a year, with a minimum of RM100, renewable on 1 January each year.
  • For a factory outside an industrial zone (Category B), the factory owner and the registered landowner each sign a statutory declaration that they will bear the risk of fire and damage without involving Bomba or other agencies, will apply for a special permit for three years, will move to an industrial zone set by the council, and accept enforcement if they do not. The Gombak land office's special temporary permit is required at the first renewal.

For a tenant this changes three things. Your licence rests on a permit renewed every year. In Category B, your landlord has already signed that the operation will move within three years, so a longer lease, or a fit-out you cannot take with you, is a poor fit. And the programme's published end date is 31 December 2027; I do not plan a client's lease on a guess about what comes after it.

Can you get a Bomba fire certificate for a factory without a CCC?

Not every factory needs one: only premises Bomba has designated by use, size or location. My guide on the Bomba fire certificate explains the thresholds. Where it is needed, the Fire Services Act 1988 says in section 28 that the certificate is renewed every year, section 29 lets the owner, the occupier or the person managing the premises apply and lets Bomba ask for plans, and section 33 makes the owner guilty of an offence when no certificate is in force.

The application form in the Fire Services (Fire Certificate) Regulations 2001 asks for the date and reference number of the approved plans, both the council's and Bomba's, along with the fire safety organisation certificate, a Fire and Emergency Response Plan and a Fire Safety Report. A building put up without approved plans has nothing to write in that line. Note too that the MPS KTK form lists Bomba's comment or approval only "if any" and exempts Category B premises from it, while the Category B declaration has the owners accept the fire risk themselves.

Will insurance cover a factory without a CCC or CF?

There is no single rule, so I read the wording. QBE Malaysia's fire policy is a useful example of what to look for:

  • Disclosure. For a business policy, Schedule 9 of the Financial Services Act 2013 requires the insured to disclose any matter it knows is relevant and any matter a reasonable person could be expected to know is relevant. If not, the contract can be avoided, a claim denied or reduced, or the terms changed. The insured must also tell the insurer at once if any information given changes.
  • Change of occupation. Under condition 9(a), cover on the affected property stops if the trade carried on or the nature of the occupation changes in a way that increases the fire risk, unless the insurer agrees by endorsement first.
  • Reinstatement. If the building cannot lawfully be rebuilt as it was because of council rules on construction, the insurer pays only what reinstatement would cost if it could lawfully be reinstated to its former condition.

The tenant usually insures machinery, stock and liability; the landlord insures the building. I tell both sides to state the certificate position in writing to their insurer and keep the reply on file.

What are the risks for the tenant and for the landlord?

Risk Tenant Landlord
Occupation without a CCC (Act 133, s.70(27)(f)) Occupies the building Permits it to be occupied
Business licence Cannot obtain or renew it Rent stops when the tenant has to leave
Fire certificate (Act 341) May apply as occupier, but needs approved plan references Owner commits the offence under section 33
Insurance Stock and machinery claim at risk Building claim at risk
KTK Category B May have to move within the permit period Has declared to relocate and to carry the fire risk

Enforcement here is real. In September 2020, MPS, the Gombak land office and the DOE checked 15 factories around Sungai Gong in Rawang. MPS withdrew the licences of four factories for carrying out additional activities without permission, gave a machinery maintenance factory three days to produce documents before demolition for a building put up without permission, and the land office served a Form 7A notice for breach of land use conditions (Sinar Harian).

How do I check a factory's CCC or CF before signing?

This is my order on a viewing in Rawang, Serendah or Shah Alam:

  1. Ask for the certificate and the approved plan together. A Form F (or a CF for a building finished before 12 April 2007) should show the lot, the approved plan number and the submitting person's name and LAM or BEM registration number. Form F1 means only part of the building is covered.
  2. Walk the unit with the plan in hand. Anything built since, such as sheds, mezzanines and enclosed bays, sits outside the certificate.
  3. If the copy is missing, the owner asks for it. The submitting person deposited a copy with the council, so the owner can go to the building department at MPS, MPHS or MBSA, or to the architect or engineer. I ask for this before we sign, not after.
  4. Read the title. The land use category and express condition should match an industrial use; the MBSA KTK checklist itself asks for a certified e-Tanah title search.
  5. Ask straight out whether the unit is on the KTK programme. If it is, I ask for the KTK certificate, the temporary permit, its category and its expiry.
  6. Check the licence history. The latest assessment bill, and whether the previous occupier held a licence for the same activity at this address.

What do I put in the tenancy when the paperwork is incomplete?

If the client still wants the unit, the tenancy has to carry the risk to the right party. Your lawyer drafts it; I make sure these points reach the lawyer:

  • A condition precedent. The tenancy starts only when the council issues the licence for the stated activity, and every deposit is refunded if it refuses.
  • The landlord's warranty. The building as it stands has a CF or CCC, with copies attached, or for a KTK unit, the permit number, category and expiry.
  • A way out. The tenant may end the tenancy with a refund of prepaid rent and deposits if council or land office action stops the business.
  • Who pays to regularise. Submitting person fees, as-built plans and penalties sit with the landlord, because the certificate belongs to the building.
  • A term no longer than the permit, with renewal tied to the permit's renewal.
  • Stamping. MPHS and MBSA ask for a stamped tenancy; FactoryHub's tenancy stamp duty calculator gives the figure.

A lower rent is often what draws a tenant to a KTK unit. Compare the asking rent with the registered rents on FactoryHub's transaction pages for Rawang and Kundang and Shah Alam, then set the difference against a licence that may not come. When you are ready to look at units with their papers in order, start with factories for rent in Rawang, Serendah or Shah Alam.

If you want a factory in Rawang, Serendah or Shah Alam checked for its CCC or CF before you commit, WhatsApp Jason Low on +60 12-288 1834.

Buying a cheap factory without a CCC

I found a very cheap factory in Rawang but it has no CCC. Is it worth buying?

That depends on why the CCC is missing and what you want to use the factory for. In Rawang or Kundang, a unit with no CCC may sit on Selangor's KTK programme, which runs on temporary permits until 31 December 2027. Look at the KTK certificate, the approved plan and the title, set the lower price against the licensing and insurance risk, and confirm the position with MPS before you commit.

Questions people ask

01Can I get a business licence for a factory without a CCC or CF in Rawang, Serendah or Shah Alam?+

Normally no. MPS lists a CF or TCF among its approval conditions, MPHS makes a CFO or CCC a general licence condition, and MBSA asks for a copy of the CF or CCC with the application. The exception is a factory already in Selangor's KTK programme, which can hold a temporary licence on the programme's own documents.

02Is Form F the CCC?+

Yes. Under the Selangor Uniform Building By-Laws, the certificate of completion and compliance is issued in Form F by the principal submitting person. Form F1 is a partial CCC that covers only part of a building until the whole is completed.

03Who issues a certificate of fitness, and who issues a CCC?+

The CF was issued by the local council. Since 12 April 2007 the CCC has replaced it, and it is issued by the principal submitting person, a registered architect, engineer or building draughtsman, who must deposit a copy with the council and the Board of Architects or Board of Engineers within 14 days.

04How do I check whether a factory has a CCC?+

Ask the owner for the Form F or CF together with the approved building plan, and check that the lot and plan numbers match the unit. If the copy is missing, the owner can ask the council's building department or the original architect or engineer, since a copy was deposited with the council.

05Can the landlord or the tenant be fined for occupying a factory without a CCC?+

Yes, both. Section 70(27)(f) of the Street, Drainage and Building Act 1974 applies to anyone who occupies a building without a CCC or permits it to be occupied, with a fine of up to RM250,000, jail of up to ten years, or both.

06Will fire insurance pay out on a factory without a CCC?+

It depends on the policy wording and on what was disclosed. Business fire policies usually require you to disclose relevant facts and allow a claim to be reduced or refused if you did not, and some pay only what a lawful reinstatement would cost. Tell your insurer the certificate position in writing.

07Can a factory without CCC be bought and sold in Rawang or Shah Alam?+

Yes. A factory without a CCC can still change hands, but the missing certificate stays with the building and follows the buyer into financing, licensing and insurance. In Rawang, Kundang, Serendah, Batang Kali and Shah Alam, find out whether the unit is on Selangor's KTK programme, which runs until 31 December 2027. Ask for the Form F or CF and the approved plan, and check the title at the land office.

08How do I check whether a factory in Rawang or Shah Alam complies with all government regulations?+

Begin with the building certificate: ask for the Form F or CF and the approved plan, and check that they match the unit. After that, look at the business licence conditions at MPS, MPHS or MBSA, whether a Bomba fire certificate is needed, and the land use shown on the title; for a KTK factory, also ask for the KTK certificate and the temporary permit. Confirm each point with the council concerned before you sign.

Sources

  1. Laws of Malaysia: Street, Drainage and Building Act 1974 (Act 133), section 70(19) to 70(27) (AGC reprint)
  2. Selangor Uniform Building By-Laws 1986, updated to Sel. P.U. 142/2012: by-laws 25, 27 and 28, Forms F and F1 (JKT, KPKT)
  3. Malaysian Bar: Law and Realty, Understanding the new CCC (CCC replaced the CFO from 12 April 2007)
  4. Majlis Perbandaran Selayang: Memohon Lesen / Permit Lesen Sementara, approval conditions
  5. Majlis Perbandaran Selayang: Borang permohonan permit bangunan sementara, Program Pematuhan Syarat dan Penguatkuasaan Kilang Tanpa Kebenaran (updated 5 March 2026)
  6. Majlis Perbandaran Hulu Selangor: Borang komposit permohonan lesen premis perniagaan dan iklan, checklist and general conditions
  7. Majlis Bandaraya Shah Alam: Senarai semak (umum) permohonan lesen komposit, amended 29 August 2025
  8. Majlis Bandaraya Shah Alam: Senarai semak (khusus) permohonan lesen komposit, Lampiran 16, industrial licence without CF under the KTK programme
  9. Laws of Malaysia: Fire Services Act 1988 (Act 341), sections 28, 29 and 33 (AGC reprint)
  10. Laws of Malaysia: Fire Services (Fire Certificate) Regulations 2001 [P.U.(A) 241/2001], regulation 2 and the application form, reprint as at 1 April 2023
  11. QBE Insurance (Malaysia): Fire policy wording, misdescription, condition 9 (termination) and reinstatement
  12. The Star: No more excuses for 6,690 unlicensed factories in Selangor, says exco rep (14 November 2024)
  13. Utusan Malaysia: DUN Selangor, 19 kilang haram enggan patuh arahan (21 April 2026)
  14. Sinar Harian: MPS buat pemeriksaan 15 kilang sekitar Sungai Gong (7 September 2020)
  15. FactoryHub: Tenancy stamp duty calculator
  16. FactoryHub: Rawang and Kundang JPPH-registered industrial transactions
  17. FactoryHub: Shah Alam JPPH-registered industrial transactions

Units on the market nearby

More on renting a factory or warehouse

All guides: Renting a factory or warehouse →

Probationary Estate Agent · PEA 1478 · CID Realtors Sdn Bhd E(1) 1855About Jason → · Contact →
Ask Jason about this