Tenant Renovations and Reinstatement Works in a Rawang, Serendah or Shah Alam Factory: Landlord Consent, Council Permits, Who Keeps the Fit-Out and the Deposit
Get the landlord's written consent and the council's permit before any work. MPS (Rawang, Kundang), MPHS (Serendah, Bukit Beruntung) and MBSA (Shah Alam) all want the tenancy agreement. Anything permanently fastened can count as part of the land, so list what you may remove. At exit, reinstate as agreed, close permits and utilities, and request itemised deposit deductions.
Key Takeaways
- Two consents, not one. The landlord's consent comes from your tenancy agreement. The council's permit comes from the law: under section 70(11) of the Street, Drainage and Building Act 1974, altering a building without the local authority's prior written permission can bring a fine of up to RM25,000 and a court order to alter or demolish the work.
- The councils want the owner involved. MPS (Rawang, Kundang), MPHS (Serendah, Sungai Choh, Bukit Beruntung, Batang Kali) and MBSA (Shah Alam) all ask for the tenancy agreement, and the MPS and MBSA forms ask for the owner's consent letter when a tenant applies.
- What is fixed may stay. The National Land Code counts things permanently fastened to the land as part of the land, so write down before the work starts which items you may take away.
- Shah Alam puts restoration in writing. MBSA's temporary permit form asks the applicant to undertake to restore the building to its original state when the permit ends.
- Deposit deductions follow the agreement. Dated handover photos, a reinstatement list and a joint inspection are what get a deposit back without a quarrel.
What does reinstatement work mean in a factory tenancy?
Reinstatement works are what a tenant does at the end of a tenancy to hand the unit back in the condition the agreement describes. In a factory that usually means taking out office partitions, mezzanines and racking, breaking out machine plinths, removing cable trays, compressed air and process piping, patching anchor bolt holes, repainting, and clearing every drum and pallet of waste. In a terrace factory it can also mean closing an opening that was cut into a party wall. If you need to leave before the term ends, my guide on ending a factory tenancy early covers compensation and your deposit.
No Malaysian statute writes these terms for you. A paper on landlord and tenant law hosted by PKNS notes that there is no specific legislation governing tenancy agreements and that the Contracts Act 1950 covers disputes over them. A term of three years or less is a tenancy exempt from registration under section 223 of the National Land Code, and it can be made by word of mouth or in any written form. The repair duties in section 231, such as keeping the property in repair, are implied into registered leases and give way to an express term. For a factory tenancy of three years or less, the reinstatement clause in your agreement does almost all of the work, so it has to be specific.
Do you need the landlord's consent and a council permit before renovating?
Usually both, and they are separate. The landlord's consent is a contract matter: most agreements forbid alterations without written approval, and only the owner can sign the parts of council forms that ask for the owner. The council permit is the law, and the fine in section 70(11) falls on the person who makes the alteration.
Which council you deal with depends on the estate, not the postal address. The Selangor State Assembly's written list of industrial areas puts the Rawang and Kundang estates under Majlis Perbandaran Selayang (MPS); Sungai Choh, Serendah, Bukit Beruntung and MIEL Batang Kali under Majlis Perbandaran Hulu Selangor (MPHS); and Seksyen 15, Seksyen 16, HICOM (Seksyen 26), HICOM-Glenmarie and Temasya under Majlis Bandaraya Shah Alam (MBSA).
| Council and area | Form I read | What it asks of a tenant |
|---|---|---|
| MPS: Rawang, Kundang | Internal partition permit checklist, JB-B07 | An application letter from the owner, the title or sale agreement, a tenancy agreement still in force with its dates, the CF or CCC, the latest assessment bill, photos. Gypsum board or equal for up to three rooms. RM100 per application, RM50 per new room, RM5 sticker. |
| MPS | Temporary permit for factory additions, JB-B04(A) | A principal submitting person (PSP), the owner's consent letter when a tenant applies, the owner's details and signature on the plans, a no-objection letter from neighbouring lots. Open awnings only, in metal deck and steel tension. RM10 per 9 m² (minimum RM300) plus a council deposit of RM750 to RM1,500. |
| MPHS: Serendah, Sungai Choh, Bukit Beruntung, Batang Kali | Minor works permit, non-residential buildings | The title or sale agreement, a current tenancy agreement between owner and tenant, the CF or CCC, an undertaking signed by the owner or applicant. RM100 per item of work and a RM500 permit deposit. |
| MBSA: Shah Alam Seksyen 15, 16, 26, HICOM, Temasya | Temporary building permit, consultant plan (October 2025) | The tenancy agreement, a consent letter from the premises owner, a declaration as owner or tenant, the CF or Form F (CCC), the latest assessment receipt, photos, and an undertaking to restore the building to its original state when the permit ends. |
Three details matter for factories. MPS sends factory partitions in anything other than gypsum board or glass, any new brick wall and any opening in a party wall through a PSP and its One Stop Centre. MBSA asks for a letter stamped as received by Bomba for a mezzanine over 46 m², a shed, a safety staircase or partitions in a building over 1,000 sq ft, and it allows mezzanines in steel structure only. The MPHS minor works form is written mainly for shop units, so for factory work I ask its Building Department which route applies; the same form warns that work started before approval can cost ten times the processing fee.
Before a client commits to a mezzanine, I check the slab, because the floor loading decides more than the permit does. Anything that touches sprinklers, hose reels or escape routes needs the Bomba checks first.
Who owns the renovation when the tenancy ends?
Start with the land law. Section 5 of the National Land Code defines land to include "all things attached to the earth or permanently fastened to anything attached to the earth". A mezzanine bolted to the slab, a brick office, cold room panels set into the floor, cabling run inside the walls or a loading bay canopy can therefore be treated as part of the owner's property, whoever paid for it. Loose machines, racking that stands on its own feet and portable equipment are a different matter. The line between the two is where disputes start, so I do not leave it to the law.
When a client plans a fit-out, I ask for the agreement, or a signed side letter, to sort every item into three lists:
- Tenant's items: removable at exit, for example machines, compressors, racking, loose air conditioners and the tenant's signboard.
- Items that stay: left behind with no claim either way, for example upgraded wiring or a fire system extension that Bomba has approved.
- Items to be removed: taken out and made good at exit, for example partitions, mezzanines, plinths and cut openings.
Attach the approved permit plan and dated photos to each list. Permits also have a life of their own. In MBSA's sample declaration the applicant promises that the area will be returned to its original condition when the permit approval ends. At MPS, the deposit claim checklist for an annual permit asks for colour photos showing the structure demolished and the site cleared, confirmed by the owner, together with the original receipt. If the landlord wants to keep an awning that a tenant built under a permit, settle in writing who holds and renews that permit and who claims the council deposit, and ask the council how a change of applicant is handled.
What should the reinstatement clause in a factory tenancy say?
A clause that only says "restore to original condition" invites an argument, because nobody wrote down what the original condition was. These are the points I want to see in writing on a factory deal:
- A reference condition: a handover report with dated photos and video, signed by both sides when the keys change hands.
- A scope: the three lists above, with the approved plans.
- A standard: fair wear and tear excepted, and what that means for the floor, roof sheets and walls.
- Who does the work: the tenant's contractor, or the landlord's contractor at the tenant's cost against quotes the tenant can see.
- Timing: works finished before the term ends. Under section 28(4)(a) of the Civil Law Act 1956, a tenant holding over after the tenancy ends can be charged, at the landlord's option, double the rent until possession is given up.
- Waste: who removes it, and proof that scheduled waste left the site properly.
- Dates: a joint inspection date and a deposit release date.
Waste is where a factory exit differs from a shop. Under the Environmental Quality (Scheduled Wastes) Regulations 2005, a waste generator must ensure scheduled wastes are properly stored, treated or recovered on site, or delivered to prescribed premises (regulation 8), and they may be disposed of only at prescribed premises (regulation 4). They may be stored for 180 days or less, with no more than 20 tonnes on site (regulation 9). Old oil drums, sludge and solvent tins are the tenant's legal duty, not a cleaning job for the last week. If your process discharges water, read my factory wastewater guide before you sign, not when you leave.
How do you get the deposit back after reinstatement?
The deposit is governed by the agreement. The PKNS-hosted paper cites BBMB Kewangan Berhad v Kueh Teck Swee [2001] 2 AMR 1401, where the High Court in Kuching held that the landlord's right to forfeit depended on the express terms; because the tenant was not in breach, the landlord had to refund the deposit after deducting the cost of repairs at the end of the tenancy. Forfeiting a whole deposit is a harder question. In Cubic Electronics v Mars Telecommunications, the Federal Court held that a deposit is subject to section 75 of the Contracts Act 1950, that proof of actual loss is not always needed, and that the defaulting party carries the burden of showing the sum is unreasonable, according to Allen & Gledhill's summary. That case was about a sale deposit, so read it as a warning that a forfeiture clause can bite, and have a lawyer read yours.
This is the order I work through at exit:
- Well before the end date, a walk-through with the landlord against the handover photos and the three lists.
- The scope agreed in writing, item by item, with who does each one.
- The works carried out, with scheduled waste removed through licensed channels and the records kept.
- A joint inspection, and a signed handover note listing anything left outstanding.
- Deductions itemised against quotes or invoices, not a round figure.
- Utilities closed or transferred. TNB's notice on closing an account says that until an account is closed, the holder is still liable for the electricity used and its payment. The TNB deposit sits with TNB and is separate from the landlord's deposit.
- Any council permit deposit in your name claimed back.
The tenancy agreement itself must be stamped, and FactoryHub's tenancy stamp duty calculator works out the duty from the rent and the term.
What I check on a site visit before a client renovates or hands back a factory
- Approved plan and CCC against the site. Extensions an earlier tenant built without approval are a risk you inherit at exit if the agreement treats them as yours, so I ask the landlord to confirm in writing that they existed at handover.
- Floor, roof and power. A mezzanine, a crane or new machines change the load on the slab and on the supply; my guide to the TNB compact substation covers the power side.
- Fire systems and escape routes against the planned layout.
- The previous tenant's exit. Whether their reinstatement was done, and whether a council permit is still open on the unit.
- The landlord's side. My guide for owners on screening a factory tenant shows what a landlord will ask of you, and what to check before renting a factory in Rawang covers the checks before you sign. For the national picture, FactoryHub has a guide to reinstatement works.
If you are looking for a unit you can fit out, see the factories for rent in Rawang and Shah Alam.
To plan a factory fit-out or a reinstatement exit in Rawang, Serendah or Shah Alam, WhatsApp Jason Low (Probationary Estate Agent PEA 1478, CID Realtors Sdn Bhd E(1) 1855) on +60 12-288 1834.
Questions people ask
01What does reinstatement work mean in a factory tenancy?+
It is the work a tenant does at the end of the tenancy to return the unit to the condition the agreement describes. In a factory that usually covers removing partitions, mezzanines, plinths, piping and signage, patching bolt holes and clearing waste. Malaysian law does not set the scope, so the reinstatement clause and the handover record decide it.
02Is it legal to renovate a rented factory without a council permit?+
Not for work the council regulates. Section 70(11) of the Street, Drainage and Building Act 1974 makes altering a building without the local authority's prior written permission an offence with a fine of up to RM25,000, and a Magistrate's Court can order the work altered or demolished. MPS, MPHS and MBSA each have their own permit route for partitions, awnings, mezzanines and minor works.
03Who applies for the renovation permit, the tenant or the landlord?+
Either can start it, but the owner has to be involved. MPS asks for the owner's consent letter and signature on the plans when a tenant applies for a temporary factory addition, and MBSA's temporary permit list includes a consent letter from the premises owner. Both also ask for the tenancy agreement.
04Can I take my mezzanine or office partitions with me when I move out?+
Only if the agreement allows it. The National Land Code treats things permanently fastened to the land as part of the land, so a bolted mezzanine or a built office may be the owner's property at exit. Write a list of tenant's items, items that stay and items to be removed before the work starts.
05Can the landlord keep the whole deposit for reinstatement?+
It depends on the agreement. In BBMB Kewangan v Kueh Teck Swee the court held that the right to forfeit depends on the express terms, and a landlord whose tenant was not in breach had to refund the deposit after deducting repair costs. Ask for deductions itemised against quotes or invoices and keep your handover photos.
06What happens if reinstatement is not finished when the tenancy ends?+
You may be holding over. Section 28(4)(a) of the Civil Law Act 1956 lets a landlord charge a tenant who holds over double the rent until possession is given up. Agree a finish date inside the term, or a written extension, before the works begin.
07Can structural modifications be made after renting a factory in Rawang or Shah Alam?+
Yes, but only after you have the landlord's written consent and the council's prior written permission. Permits for Rawang and Kundang go through MPS, for Serendah and Bukit Beruntung through MPHS, and for Shah Alam through MBSA. Under section 70(11) of the Street, Drainage and Building Act 1974, altering a building without permission can lead to a fine of up to RM25,000 and an order to alter or demolish the work. Read the tenancy agreement and confirm the permit route with the council before any work starts.
Sources
- Majlis Bandaraya Shah Alam: Borang permohonan dan semakan dokumen permit bangunan / binaan sementara (pelan perunding), Oktober 2025
- Majlis Bandaraya Shah Alam: Contoh surat perakuan pemohon (pemilik / penyewa), permit binaan sementara, Oktober 2025
- Majlis Perbandaran Selayang: Senarai semak permohonan permit sekatan dalaman (JB-B07, kemaskini 07.07.2025)
- Majlis Perbandaran Selayang: Borang pelan bangunan, permit sementara bagi tambahan bangunan kilang / industri (JB-B04(A), kemaskini 05.03.2026)
- Majlis Perbandaran Selayang: Senarai semak tuntutan cagaran permit tahunan / as-built (JB-C09)
- Majlis Perbandaran Hulu Selangor: Borang senarai semak permohonan permit kerja kecil bangunan selain kediaman
- Dewan Negeri Selangor: Jawapan bertulis No. 346, Lampiran A (kawasan perindustrian mengikut PBT)
- Laws of Malaysia: Street, Drainage and Building Act 1974 (Act 133), section 70 (AGC reprint)
- Laws of Malaysia: National Land Code (Revised 2020), Act 828, sections 5, 223 and 231
- Laws of Malaysia: Civil Law Act 1956 (Act 67), section 28(4) (AGC reprint)
- Environmental Quality (Scheduled Wastes) Regulations 2005, P.U.(A) 294/2005, regulations 4, 8 and 9
- PKNS e-Perundangan: Landlord vs Tenant, paper by Messrs Sidek Teoh Wong & Dennis (BBMB Kewangan v Kueh Teck Swee)
- Allen & Gledhill: Federal Court on section 75 Contracts Act 1950 (Cubic Electronics v Mars Telecommunications)
- Tenaga Nasional Berhad: Close of Account Online
- FactoryHub: Tenancy agreement stamp duty calculator
Units on the market nearby
Semi-D Factory for Rent in Saujana Teknologi Rawang, Rawang, 6,525 sq ft
RM 10,500/month
Semi-Detached Factory for Sale or Rent in Saujana Rawang, Rawang, 8,000 sq ft
RM 4,000,000 · RM 15,000/month
Detached Factory for Rent in Batu 17 Rawang, 9,000 sq ft
RM 21,000/month
More on renting a factory or warehouse
- Factory Rental Deposit and Move-In Costs in Rawang, Serendah and Shah Alam: How Much Cash to Prepare, With Worked Examples
- Renting a Factory Without CCC or CF in Rawang, Serendah or Shah Alam: Licence, Bomba, Insurance and What to Check Before You Sign
- How Long Should Your Factory Lease Term Be in Rawang, Serendah or Shah Alam? 2+1 vs 3+3, the Renewal Option, Rent Reviews and the Three-Year Registration Rule
- Can You Sublet or Split a Factory in Rawang, Serendah or Shah Alam? Landlord Consent, Council and Bomba Rules, Insurance and Meters