Planning Permission (Kebenaran Merancang) for a Factory in Rawang, Serendah or Shah Alam: When You Need It, Change of Use, Fees, Validity and Appeals

Written by , PEA 1478 · Published · Buying a factory or industrial land

Short answer

You need kebenaran merancang, the council's planning permission under Act 172, before building or extending a factory, making a material change in how land or a building is used, or splitting or merging lots. Purely internal works are exempt. Selangor charges RM100 per 100 square metres for factories, and approval lapses after 12 months if work has not started.

A levelled plot of red earth with survey pegs and a blank notice board on two posts beside a new grey single-storey factory, with green hills behind.
Illustrative image

Key Takeaways

  • Kebenaran merancang (planning permission) is the council's approval of what you build and how land or a building is used. Section 19 of the Town and Country Planning Act 1976 (Act 172) says no one other than a local authority may start any development without it.
  • "Development" covers far more than a new factory. It includes building and engineering works, a material change in the use of land, a building or any part of one, and the subdivision or amalgamation of lots. Works that only touch the interior, without changing the use, height, floor area, outside appearance, drainage or structure, are exempt.
  • In Selangor a factory or warehouse pays RM100 per 100 square metres of gross floor area, and an extension of an approval costs RM500, under the Kaedah-Kaedah Pengawalan Perancangan (Am) (Selangor) (Pindaan) 2025 as set out in MPS's fee form.
  • An approval lapses 12 months after it is granted if work has not started, unless the council extends it. MBSA asks for the extension application within the 3 months before expiry.
  • Building or changing the use without it is an offence carrying a fine of up to RM500,000, up to 2 years' jail or both, and the landowner is presumed to have permitted it unless the owner proves otherwise.

What is kebenaran merancang, and how is it different from building plan approval?

Kebenaran merancang (KM) is the planning approval that the local planning authority gives under Act 172. In my areas that authority is the council: Majlis Perbandaran Selayang (MPS) for Rawang and Kundang, whose area covers Mukim Rawang, Mukim Batu and Mukim Setapak; Majlis Perbandaran Hulu Selangor (MPHS) for Serendah, Bukit Beruntung, Sungai Choh and Batang Kali; and Majlis Bandaraya Shah Alam (MBSA) for Shah Alam.

KM answers planning questions: whether the local plan allows the use, how the building sits on the lot, its height, setbacks, access and appearance. Section 21(3) lets the council give written directions on the site level, the frontage line, the elevations, the design, the building line and access. Building plan approval comes after KM and deals with structure, fire safety and the building by-laws, and the CCC comes when the building is finished. Land matters, such as converting an agricultural title, go to the land office. Each stage has its own forms, and a KM does not replace any of the others.

The decision arrives on a form: the OSC 3.0 Plus manual names a grant Form C1 and a refusal Form C2. If you are planning a new building, my guide on whether to build or buy a factory walks through the whole approval sequence and the time each stage takes, so I will not repeat it here.

When does a factory owner, buyer or tenant need kebenaran merancang?

Act 172 defines development as "the carrying out of any building, engineering, mining, industrial, or other similar operation in, on, over, or under land, the making of any material change in the use of any land or building or any part thereof, or the subdivision or amalgamation of lands". MPS's application form (Borang A) lists the same six purposes for the applicant to tick: erecting a building or works, subdividing land, amalgamating lots, a material change in the use of land, a material change in the use of a building, and an addition or alteration to a building.

For a factory, that means KM comes into play when you:

  • build a new factory, warehouse or extra block on a lot;
  • extend an existing building outward or upward, or add floor area;
  • change how a building or part of it is used, for example turning part of a factory into worker accommodation. MPHS's short-term foreign worker housing policy, adopted on 17 August 2021, allows housing in existing industrial premises only with a KM for a material change of use and an internal renovation permit. I cover the rest of that topic in my guide to worker hostels near factories;
  • use vacant industrial land for something new, such as open storage or a container yard;
  • split or merge lots, which I explain in subdividing or merging industrial land.

Section 19(2)(a) exempts maintenance, improvement or alteration works that affect only the interior of a building, as long as they do not change the use, materially affect the outside appearance, add height or floor area, affect drainage, sanitation or soundness, or conflict with the local plan. That exemption is from KM only: internal partitions and mezzanines still need the council's building permit, which I cover in factory renovation and reinstatement.

Whether a change of use is "material" is a judgement the council makes against its local plan; the Act does not list factory activities one by one. MPS's change of use form encourages applicants to get technical advice from its town planning department before applying, and that is what I do before a client signs: I ask the planning department, in writing, whether the use the client has in mind needs KM. If the question is really about the industry class of the process, read light, medium and heavy industry zoning first.

Who can apply, and what does the application need?

The application goes through the council's One Stop Centre (OSC) on the OSC 3.0 Plus Online system, filed by a principal submitting person, as MPS's FAQ explains. Section 21C says plans and documents must be prepared by a qualified person, so in practice the owner, tenant or buyer appoints a registered town planner or architect, who prepares and submits it.

A tenant or a prospective buyer can be the applicant, but section 21(2) requires the landowner's written consent endorsed on the application. MPS's checklist for a change of use (form KM/PMB, dated 1 April 2026) accepts a power of attorney registered at the High Court, a sale and purchase agreement, a joint venture agreement or a tenancy agreement where the applicant is not the owner. The same checklist asks for:

  • the title (or the gazette or offer letter for state land) and an official search printed within the last 6 months;
  • the latest assessment and quit rent receipts, and the council's certificate showing no arrears;
  • the company's SSM registration;
  • the CF or the CCC, or a letter from the MPS building department confirming there is none, without which the application is not accepted;
  • a support letter from Bomba on building safety, alternative exits and escape stairs;
  • a brief development proposal report, a sketch of how the space will be used and a location plan.

For a new building, section 21A also requires a full development proposal report: the concept, location and site plans, ownership and restrictions, the physical setting of the land, a land use analysis and the layout plans.

How much does kebenaran merancang cost in Selangor?

The rates are set by the state, so they are the same at every council. MPS's fee form, which follows the Third Schedule of the Kaedah-Kaedah Pengawalan Perancangan (Am) (Selangor) (Pindaan) 2025, sets these rates (MPS Borang A):

Application Fee
Factory, workshop, store or warehouse RM100 per 100 square metres of gross floor area
Material change of use, industrial building RM100 per 100 square metres
Material change of use, land RM100 per 100 square metres
Industrial layout (master plan or concept plan) RM500 per hectare
Engineering works or earthworks RM1,000 per hectare
Demolishing a building RM100 per 100 square metres
Amending a KM, no extra floor area RM500 per application
Extending a KM RM500 per application
Any development on Malay reserve land 50% of the KM fee

By my own arithmetic, a new 2,000 square metre factory pays RM2,000 in KM fees, and changing the use of 300 square metres inside a factory pays RM300. These are the council's processing fees only; the consultant's fees are separate. Where a change in the local plan has raised the land's value through a change of use, density or floor area, section 32 adds a development charge. Under section 33 the council fixes that charge before it grants KM, and the amount cannot be appealed or reviewed in court.

How long does it take, and is there a faster lane for factories?

Each council publishes its own clock:

  • MBSA (Shah Alam): its flow chart for KM to erect a building has a site visit after day 4, the recommendation papers collected on day 24 and the application tabled at the One Stop Centre committee on day 30. The decision is notified within 3 days, the consultant then has 28 days to correct the plans, and the KM letter follows within 7 days of complete plans.
  • MPS (Rawang, Kundang): the OSC committee meets twice a month.
  • MPHS (Serendah, Bukit Beruntung, Batang Kali): its customer charter report for May 2026 sets 99 days for a KM decision.

Where an area has no local plan in force, section 21(6) adds a step: the council must notify the neighbouring owners, who have 21 days to object, and hear the objections within 30 days after that. The OSC 3.0 Plus manual shows that route taking 106 to 158 days.

For new industrial buildings there is a faster lane. The SPEED Selangor guideline, in force since 1 October 2025, covers industrial buildings in planned industrial areas or in zones that match the local plan, including factories, warehouses and logistics facilities, and caps the whole process at 30 days from a complete application. If the 30 days run out, the applicant can appeal to the council, which must decide within 14 days. Its entry conditions matter to anyone buying land:

  • the park must already have an approved KM layout (master plan);
  • the land premium under Notice 5A must be paid;
  • external power, water and sewerage connections must be available, and any EIA or traffic study approved;
  • the building must not be meant for letting to parties other than the owner.

That last condition means a factory built to lease out generally goes through the normal OSC route. MPS publishes SPEED Selangor forms for its area.

How long is kebenaran merancang valid, and what if the council says no?

Section 24 says a KM lapses 12 months after the date it is granted if the development has not started in the manner the permission specifies. The council may extend it on an application made before it lapses, for the prescribed fee (RM500 in Selangor), and each extension again runs 12 months. MBSA's flow chart asks for the extension application within the 3 months before the KM expires. The 12-month rule does not apply where the permission expressly states that the development involves no building operation.

If the council refuses, or grants KM with conditions you cannot live with, section 23 lets you appeal to the state's Appeal Board within one month of the date the decision is communicated to you. A neighbour who objected under section 21(6) has the same right. The Board can confirm the decision, direct the council to grant permission, set aside a permission or change its conditions. Section 22(5)(a) also allows a change of use to be approved for a limited period only, after which the original use must resume, so read the conditions in the letter and not just the word "lulus".

What happens if you build or change the use without it?

Section 26 makes it an offence to carry out development without KM, or to permit it, with a fine of up to RM500,000, jail of up to 2 years or both, and up to RM5,000 for each day the offence continues after conviction. Section 26(2) presumes that the landowner permitted the act unless the owner proves otherwise, which is why I tell landlords to write the approved use into the tenancy and to ask what a tenant plans before handing over the keys.

Under section 27 the council can order the land restored to its earlier condition if it would have refused permission, or call on the owner or occupier to apply if it might approve. Carrying on after a stop notice is a further offence: up to RM100,000, up to 6 months' jail or both, plus up to RM5,000 a day. For factories already running without approval, MPS publishes a limited-period KM form under Selangor's compliance and enforcement programme for factories without permission (Kilang Tanpa Kebenaran). The building plan side of unapproved add-ons is in my guide to illegal factory extensions.

What I check before a client signs for a factory or a lot

  • The approved use against the use the client plans, from the CCC or CF, the approved plans and, where the seller or landlord has it, the KM letter.
  • Whether any part of the building has changed use since the CCC: a hostel floor, a showroom, an extra block at the back.
  • Whether the landlord or seller will sign the consent and supply the title, receipts and CCC that an application needs.
  • Council arrears on the lot, because the MPS checklist asks for a no-arrears certificate.
  • For land: the title category and express condition (see industrial land title conversion in Serendah and Batang Kali), whether the park has an approved layout, and whether the Notice 5A premium has been paid.
  • A written answer from the council's planning department on any use I am unsure about.

For a map of the other approvals a new plant needs, from DOE to the manufacturing licence, FactoryHub has a guide to factory approvals in Malaysia.

This is general information from my practice as an agent, not legal or planning advice: a registered town planner or architect prepares and submits the application.

If you are buying, renting or building a factory in Rawang, Serendah, Sungai Choh, Kundang, Bukit Beruntung, Batang Kali or Shah Alam and need to know whether your plan needs kebenaran merancang, WhatsApp Jason Low, Probationary Estate Agent PEA 1478 with CID Realtors Sdn Bhd, on +60 12-288 1834.

Questions people ask

01What is kebenaran merancang?+

Kebenaran merancang is planning permission granted by the local council under the Town and Country Planning Act 1976 (Act 172). It is needed before any development, which includes building works, a material change in the use of land or a building, and subdividing or merging lots. For factories in Rawang it comes from MPS, in Serendah from MPHS and in Shah Alam from MBSA.

02Do I need kebenaran merancang to renovate the inside of my factory?+

Usually not. Section 19(2)(a) of Act 172 exempts interior works that do not change the use, the outside appearance, the height or floor area, the drainage, sanitation or structure, and do not conflict with the local plan. Partitions, mezzanines and similar works still need the council's building permit.

03How long is kebenaran merancang valid?+

It lapses 12 months after it is granted if the development has not started, unless the council extends it. The extension must be applied for before the KM lapses, costs RM500 per application in Selangor, and runs another 12 months. MBSA asks for the application within the 3 months before expiry.

04How much is the kebenaran merancang fee for a factory in Selangor?+

RM100 per 100 square metres of gross floor area for a factory, workshop, store or warehouse, under the Kaedah-Kaedah Pengawalan Perancangan (Am) (Selangor) (Pindaan) 2025. A material change of use of an industrial building is also RM100 per 100 square metres, and an extension or an amendment without extra floor area is RM500. Consultant's fees and any development charge are extra.

05Can a tenant apply for kebenaran merancang for a change of use?+

Yes. A tenant or prospective buyer can apply, but section 21(2) of Act 172 requires the landowner's written consent endorsed on the application. MPS's checklist also asks a non-owner for a registered power of attorney, a sale and purchase agreement, a joint venture agreement or a tenancy agreement.

06Can I appeal if the council refuses kebenaran merancang?+

Yes. Section 23 of Act 172 allows an appeal to the state Appeal Board within one month from the date the decision is communicated, against a refusal or against the conditions imposed. The Board can confirm the decision, direct the council to grant permission or change the conditions. The amount of any development charge cannot be appealed.

07What is SPEED Selangor?+

SPEED Selangor is a state fast lane, in force since 1 October 2025, that caps approvals for qualifying industrial and commercial buildings at 30 days from a complete application. For factories and warehouses it needs a planned industrial area with an approved layout, a paid Notice 5A premium, available utilities and approved technical studies. The building must not be meant for letting to parties other than the owner.

Sources

  1. Town and Country Planning Act 1976 (Act 172), reprint as at 1 June 2021: sections 2, 18 to 27, 32 and 33 (PLANMalaysia@Pulau Pinang copy)
  2. Majlis Perbandaran Selayang: Borang A and planning permission fee form under the Kaedah-Kaedah Pengawalan Perancangan (Am) (Selangor) (Pindaan) 2025 (1 April 2026)
  3. Majlis Perbandaran Selayang: checklist for planning permission for a material change of use of a building, form KM/PMB (1 April 2026)
  4. Majlis Perbandaran Selayang: Soalan Lazim (OSC committee meetings, submitting persons)
  5. Majlis Perbandaran Selayang: Kawasan Pentadbiran
  6. Majlis Perbandaran Selayang: OSC forms, including limited-period planning permission for factories without permission (KTK)
  7. Majlis Perbandaran Selayang: SPEED Selangor@Selayang forms
  8. Majlis Bandaraya Shah Alam: flow chart and process for planning permission to erect a building
  9. Majlis Perbandaran Hulu Selangor: customer charter achievement report, May 2026
  10. Majlis Perbandaran Hulu Selangor: short-term foreign worker housing policy (adopted 17 August 2021)
  11. Garis Panduan SPEED Selangor (in force 1 October 2025), Majlis Perbandaran Kajang copy
  12. Manual OSC 3.0 Plus, second printing June 2020 (Majlis Daerah Tanah Merah copy)

Units on the market nearby

More on buying a factory or industrial land