Yes, inspect before signing. Malaysian law requires periodic engineer inspections only above five storeys, so a single-storey factory is checked only if you arrange it. Check the roof after heavy rain, rust at column bases, cement sheets (treat as asbestos until tested), termites, and fire and wiring records; bring in a surveyor or engineer when defects show.
Key Takeaways
- No law requires a condition survey of a single-storey factory before a sale or tenancy. The periodic engineer inspection in section 85A of the Street, Drainage and Building Act 1974 applies only to buildings of more than five storeys, so checking a used factory is the buyer's or tenant's job.
- Look at the roof when it rains. MetMalaysia puts the main rainfall peak for most of the Peninsula in October and November (MetMalaysia), the months when leaks, blocked gutters and wet insulation show.
- Cement roof sheets on an older factory may contain asbestos. DOSH says intact sheets generally do not release fibres, but a removal contractor must send its documents to DOSH at least two weeks before preparing the site (DOSH Guidelines for Asbestos Removal 2017).
- After a fire, the steel needs an engineer, not a coat of paint. Steel starts losing strength at about 300ºC and may not fully recover after heating above about 600ºC (Australian Steel Institute).
- Ask for the electrical records. A non-domestic installation must be checked and tested by a competent person at least once every five years (Electricity Regulations 1994, regulation 110).
Is a building inspection needed before buying or renting a used factory?
Not by law, which is exactly why I recommend one. Section 85A of the Street, Drainage and Building Act 1974 lets a council require an inspection by a registered Professional Engineer after the tenth year from the CCC and at intervals of no more than ten years after that, but only for a building of more than five storeys. The factories I show in Rawang, Serendah, Bukit Beruntung and Shah Alam are mostly single-storey production halls with a low office block, well under that line, so nobody is obliged to inspect the roof or the steel for you before you sign. If the council later finds a building in a ruinous or dangerous state, section 83 of the same Act lets it order the owner to repair or demolish, and the repair itself needs planning approval and approved plans. A buyer inherits that problem; a tenant may be told to move out while it is fixed.
The method I follow comes from JKR's guideline on inspecting and rating existing buildings: a visual inspection first, then a detailed investigation by an engineer only where the visual inspection finds defects that call for one. JKR rates a building from A (very good, scheduled maintenance) to E (very critical, replacement). I do the first walk-through with my client during the viewing. A paid survey comes in when that walk-through turns up something we cannot judge by eye.
The questions differ for buyers and tenants:
- Buying: every defect is yours after completion, so price it before the SPA, not after. My guide on whether a factory asking price is fair shows how I compare a price with registered deals once the repair list is known.
- Renting: the tenancy agreement decides who fixes what. I set out the usual split in who pays for repairs in a rented factory. Record the condition with dated photos signed by both sides before you move in, so the deposit is not argued over later.
How do I check a factory roof for leaks?
I try to book the second viewing on a wet afternoon. MetMalaysia's description of the Malaysian climate puts the main rainfall peak in October and November and a second one in April and May for most of the Peninsula, so those are the months when a roof tells the truth. Inside the factory I look for:
- water stains, rust tracks or dried puddle marks on the floor, especially under skylights, ridges and the line of the gutter;
- daylight around screw fixings when the lights are off;
- insulation under the roof sheets that sags, has turned dark or is torn;
- rust on purlins and on the underside of the sheets;
- box gutters full of leaves and silt, and downpipes that are cracked, disconnected or end on the floor;
- fresh patches of sealant or bitumen, a sign that someone has been chasing a leak.
JKR's guideline lists the usual causes: old or damaged sheets, fixing holes that have loosened, poor installation, sealants that no longer work, and a roof that has sagged because the structure under it is damaged. Gutters leak when they are blocked by dirt and leaves, when joints or brackets come loose, or when they are too small. I also ask the owner three questions: when was the roof last re-sheeted, which leaks have been repaired and where, and was a council permit taken for the work. Rawang and Kundang fall under Majlis Perbandaran Selayang, whose minor works permit form covers roof repairs that do not change the original structure; Serendah, Batang Kali and Bukit Beruntung fall under MPHS.
How long does a factory roof last, and what does a new roof cost?
There is no single lifespan. It depends on the sheet and its coating, the fixings, the slope, the air around the factory and how often the gutters are cleared. A manufacturer's warranty is the nearest written reference: NS BlueScope Malaysia, for example, states a 36-year warranty against perforation by corrosion for its COLORBOND steel, subject to its terms. A warranty only helps if you can see it, so ask the owner for the certificate, the installation year and the installer. If nobody can produce them, I treat the roof's age as unknown and let the survey decide.
For the cost of a new roof I have no current published rate I can quote with confidence, and asking-price talk is not evidence. What I can do is list what belongs in a quote, so you can compare two of them line by line:
| Item in the quote | What to ask |
|---|---|
| Removal and disposal of old sheets | Are they asbestos cement? If so, are DOSH notification and scheduled waste disposal included? |
| New sheets and ridges | Sheet type, thickness, coating and the warranty that comes with it |
| Insulation and skylights | Area of each, and whether old skylights are replaced |
| Gutters and downpipes | Size, material and number of outlets |
| Scaffolding, lifting and safety | Edge protection, and how the work runs while the factory operates |
| Permits | A council minor works permit, or full plans if the job is large |
| Price validity | How long the quote holds |
Two things move the number. The first is permits. MPHS lists changing a roof finish, for example asbestos to metal deck, as minor works when the original structure is not changed, with a RM100 processing fee per item, a RM100 building material permit fee, a RM20 sticker, a RM500 deposit and a RM500 RORO compliance charge (MPHS checklist). A larger job can cross a legal line: under section 70(16) of the Act, demolishing and rebuilding more than half the roof area counts as erecting a building, which needs the council's prior written permission under section 70(1). The second is material. From 7 November 2026, MITI imposed provisional anti-dumping duties of 4.41% to 35.06% on aluminium-zinc coated flat steel from China, Taiwan and Vietnam, for up to 120 days, with a final decision due by 6 March 2027 (The Edge). Ask your roofer whether that touches the sheets in the quote.
Is the steel structure of the factory safe?
Most of the factories I handle are steel portal frames, and steel fails either slowly, through rust, or quickly, through overloading, impact or fire. JKR's guideline lists why metal frames rust: no coating or paint, contact with acid or salt, paint that has peeled off, and constant humidity or water. In a used factory I look at:
- column bases where they meet the floor, especially near wash-down areas, drains and the loading bay, for flaking rust and thinning steel;
- base plates and holding-down bolts, for cracks and missing nuts;
- rafters, purlins and bracing, for bends, dents from forklift or crane strikes, and missing bolts;
- crane beams and brackets if the factory has a crane, which I cover in the overhead crane guide;
- any mezzanine, canopy or extension that is not on the approved plans, because nobody has checked what it adds to the frame. My guide on illegal factory extensions explains how to spot one.
Surface rust that comes off with a wire brush is maintenance. Flaking layers, holes, bent members or cracked welds are a reason to pay a Professional Engineer before you sign, because only a structural check tells you whether a member still carries its load.
What should I do if the factory has an asbestos roof?
Treat any grey corrugated cement roof or ceiling sheet on an older factory as asbestos until a test says otherwise. DOSH's Guidelines for Asbestos Removal 2017 say asbestos cement was widely used for roofs and ceilings in Malaysia, that corrugated roofing sheets are non-friable and generally do not release fibres while intact, and that asbestos cement sheets can release fibres when cut, sawn or broken. Chrysotile is still in use here: in February 2025 the minister told Parliament that five types of asbestos are banned and chrysotile is restricted, with a phase-down under study (The Star), and in January 2026 the environment minister said the use of asbestos-based materials was under review (FMT).
In practice:
- Tenants: do not drill, cut or fix anything through the sheets, and do not let anyone pressure-wash them. Put that in the tenancy agreement, together with who removes a sheet that breaks.
- Buyers: price the removal. DOSH expects the contractor to carry out a workplace assessment (HIRARC and a chemical health risk assessment), submit its documents for DOSH's acknowledgement at least two weeks before preparing the site, and dispose of the waste as scheduled waste SW 201 under the Environmental Quality (Scheduled Wastes) Regulations 2005.
- Insulation under the roof: sprayed fibrous insulation is a different case, because DOSH treats it as friable. If you see it, have it tested before anyone works on the roof.
Do steel-framed factories get termites?
The steel does not get eaten, but the timber inside does. JKR's guideline names termites, beetles and rats as the cause of attack on timber stairs, roof frames, doors, windows, wall boards, timber panels and ceilings. In a factory that means the office block, door frames, partitions, cabinets and stored pallets. On a viewing I look for:
- earth tunnels on walls, columns, floor slab edges and inside cable trunking;
- door frames and skirting that sound hollow or crumble when pressed;
- damaged pallets, cartons or paper left in corners by the last occupant;
- small heaps of shed wings near lights or windows.
If I see signs, the next call is a licensed pest control operator. Under the Pesticides (Pest Control Operator) Rules 2004, anyone who carries out termite and other wood-destroying organism control on another person's property for hire must hold a licence issued by the Pesticides Board, and may use only pesticides registered by the Board. Ask the owner for past treatment records and any warranty that came with them.
What should I check in a factory that had a fire?
Factory fires are not rare. Bomba's director-general said 2,001 factory fires with losses of RM4.21 billion were recorded over six years, with 222 cases up to June 2026, and that 1,191 premises received fire hazard abatement notices in 2025 (Bernama). A burnt factory can be repaired properly, but you need paper for every step.
Steel is the main question. The Australian Steel Institute explains that steel begins to lose strength at about 300ºC and loses it quickly above 400ºC. Steel heated to below about 600ºC returns to its original strength, stiffness and ductility when it cools, while above about 600ºC it may lose some of its properties for good. Members distorted beyond tolerance must be replaced, repaired or analysed in detail, and bolts should be replaced where significant heating is indicated. A visual inspection and hardness tests by an engineer tell you which case you are in.
I ask the owner for:
- the Bomba report on the fire and the insurer's loss adjuster report, to see where it started and how far it spread;
- the engineer's post-fire report on the frame, and the scope of the repairs actually carried out;
- the council's approval for the rebuild if more than half the roof or walls were replaced, because section 70(16) treats that as erecting a building;
- new electrical certificates for any rewiring (see the next section) and the current position on the fire certificate. My guide on the Bomba fire certificate covers which factories need one.
How do I check the wiring and the switchboard?
The Electricity Regulations 1994 give a buyer or tenant a paper trail to ask for:
- The five-yearly test. Regulation 110 says a non-domestic installation must be checked and tested by a competent person at least once in every five years, and its protective relays checked, tested and calibrated at least once every two years. Ask for the latest reports.
- Monthly visits. Under regulation 67, an installation of up to 600 volts that takes its supply through switchgear rated at 100 amperes or more needs at least one inspection visit a month by a competent person. Ask for the visit records and the competent person's name.
- Certificates for changes. Regulations 12 to 14 require a supervision and completion certificate (Form G) and a test certificate (Form H) for wiring, rewiring and extensions. If the last occupant added machines or a new panel, ask to see both.
- Repairs by competent persons only. Regulation 111 bars anyone else from repairing or servicing the installation.
On the walk-through I look for burn marks or heat discolouration on the switchboard, cables run loose through the roof space, missing covers, and unlabelled panels that were added later. JKR lists a thermal imager among the tools for finding heat in electrical fittings and moisture in building elements, and a competent person with one can scan the main panel under load. Whether the supply is big enough for your machines is a separate question, answered in my guide on kVA, amps and a TNB upgrade.
When should I pay for a building survey, and who should do it?
I advise paying for one when any of these is true: the roof's age or repair history is unknown; there is cement sheeting you plan to disturb; the steel shows flaking rust or damage; the factory has had a fire; there are extensions that are not on the approved plans; or you are buying, or signing a long lease that puts repairs on you. Older estates such as Seksyen 15 Shah Alam are where I suggest it most often; FactoryHub's Seksyen 15 page covers the estate's history and MBSA's plan to redevelop Sections 15 and 16.
| Check | Who does it | What you get |
|---|---|---|
| Roof, walls, floor and drains | Building surveyor (JKR's guideline refers to surveyors registered with the Royal Institution of Surveyors Malaysia) | Defect list with photos and a condition rating |
| Structure, fire damage, corrosion | Professional Engineer registered under the Registration of Engineers Act 1967 | Whether members still carry their load, and the repair scope |
| Wiring and switchboard | Competent person under the Electricity Regulations 1994 | Test results, thermal scan and a list of faults |
| Termites | Licensed pest control operator | Findings and a treatment proposal |
| Asbestos | Sampling and laboratory analysis | Whether the sheets contain asbestos |
Fees depend on the floor area, the tests and whether anyone goes up on the roof, and I have no published scale to quote. Ask each firm for a written scope that lists the parts covered, the tests, roof access, the report date and the fee. Book the survey before you pay the deposit or sign the SPA, or make the purchase subject to a satisfactory survey, so a bad result still leaves you room to renegotiate or walk away. For the price itself, compare with registered deals on FactoryHub's industrial transactions page rather than with asking prices, and see my Rawang area page for the estates I cover in the north.
Legal checks and full due diligence
How can I avoid buying a factory with legal problems in Rawang, Serendah or Shah Alam?
Check the title, the approved plans and the CCC before you pay any deposit. A single-storey factory has no statutory inspection that would flag problems for you, so compare what stands on site with the approved plans and ask whether every extension, mezzanine and canopy was approved. Confirm with MPS for Rawang, MPHS for Serendah and Batang Kali, or MBSA for Shah Alam.
How do I do complete due diligence before buying a factory in Rawang, Serendah or Shah Alam?
Do it in order: title and approvals first, then the physical condition, then the price. Check the approved plans and any extensions with MPS for Rawang and Kundang, MPHS for Serendah, Batang Kali and Bukit Beruntung, or MBSA for Shah Alam, and ask for the CCC and the fire and electrical records. No law requires a condition survey of a single-storey factory, so check the roof, steel, asbestos, termites and wiring yourself, and pay a surveyor or engineer only for what you cannot judge by eye.
Related questions, answered in detail on FactoryHub
- Can I still buy a factory that has had environmental pollution incidents? Yes, it can still be bought, but have a Phase 1 and Phase 2 environmental site assessment done under DOE guidelines first. More on FactoryHub
- Do I need an Environmental Site Assessment before buying a factory? Yes, it is advisable before buying, especially for a factory with a pollution history, and it should cover the DOE Phase 1 and Phase 2 assessments. More on FactoryHub
To arrange a viewing with a roof, steel and wiring walk-through in Rawang, Serendah, Bukit Beruntung or Shah Alam, WhatsApp Jason Low, Probationary Estate Agent PEA 1478 with CID Realtors Sdn Bhd, on +60 12-288 1834.
Questions people ask
01How can I tell if a factory roof leaks when it is not raining?+
Look for water stains, rust tracks and dried puddle marks on the floor, rust on the purlins, dark or sagging insulation and fresh sealant patches, and switch off the lights to see daylight around fixings. Ask the owner which leaks were repaired and when. If you are still unsure, book a second visit after heavy rain; MetMalaysia puts the main rainfall peak in October and November.
02How much does a factory building inspection cost in Malaysia?+
I have no published fee scale to quote, and fees depend on the floor area, the tests (thermal scans, hardness tests, asbestos samples) and whether the inspector goes up on the roof. Ask each firm for a written scope listing the parts covered, the tests, the report date and the fee, and compare the scopes, not only the prices.
03Is it safe to rent a factory with an asbestos roof?+
DOSH says intact corrugated asbestos cement sheets generally do not release fibres; the risk comes when they are cut, sawn, broken or cleaned aggressively. Write a no-drilling and no-pressure-washing rule into the tenancy and agree who removes a broken sheet. Removal must go through a contractor who sends its documents to DOSH at least two weeks before preparing the site.
04Should I avoid buying a factory that had a fire?+
Not necessarily, but ask for the Bomba fire report, the loss adjuster report and an engineer's post-fire report on the steel frame. Steel heated above about 600ºC may lose some of its properties for good, and distorted members must be replaced, repaired or analysed. If more than half the roof or walls were rebuilt, check that the council approved it.
05Does the bank valuer's inspection count as a building survey?+
No. A bank valuation is prepared for the bank to decide how much to lend, not to list defects for you as the buyer. Commission your own condition survey, and a structural or electrical check where the walk-through shows a reason for one.
06Who pays for the defects the inspection finds?+
When buying, raise them before the SPA: negotiate the price down, ask the seller to repair before completion, or make the sale subject to the repairs. When renting, the tenancy agreement decides, so list the defects the landlord must fix before handover and attach a dated photo record of the condition.
07Is it worth buying a second-hand factory in Rawang or Shah Alam, renovating it and renting it out?+
It can, as long as you price the repairs and permits before you buy. No law requires an inspection of a single-storey factory, and every defect is yours after completion. Commission a condition survey of the roof, steel, wiring and asbestos, then check with MPS, MPHS or MBSA, depending on where the factory is, which permits the renovation needs before you commit.
Sources
- Laws of Malaysia: Street, Drainage and Building Act 1974 (Act 133), sections 70(1), 70(16), 83 and 85A (AGC reprint)
- JKR: Garis Panduan Pemeriksaan dan Penilaian Keadaan Bangunan Sedia Ada (JKR 21602-0004-13), inspection method, A to E rating, defect causes, inspector definitions
- DOSH: Guidelines for Asbestos Removal 2017, friability, uses in Malaysia, DOSH acknowledgement and SW 201 waste
- The Star, 27 February 2025: Asbestos ban to be carried out in stages, Dewan Rakyat told
- Free Malaysia Today, 15 January 2026: Asbestos ban under review, says minister
- Pesticides (Pest Control Operator) Rules 2004, P.U.(A) 70/2004, rule 3 (FAOLEX copy)
- Suruhanjaya Tenaga: Electricity Regulations 1994, regulations 12 to 14, 66, 67, 110 and 111
- Australian Steel Institute: Fire damage assessment and reinstatement of steel structures
- Bernama, 31 July 2026: 2,001 kes kebakaran kilang dengan kerugian RM4.21 bilion direkodkan sejak enam tahun lepas
- MetMalaysia: Iklim Malaysia, monthly rainfall pattern in Peninsular Malaysia
- Majlis Perbandaran Selayang: Borang JB-B08, permit kerja-kerja kecil (bukan strata), roof repairs
- Majlis Perbandaran Hulu Selangor: senarai semak permit kerja kecil bangunan selain kediaman, roof finish change and fees
- Majlis Perbandaran Hulu Selangor: latar belakang, towns in the council area
- Majlis Perbandaran Selayang: latar belakang, Mukim Rawang and Bandar Baru Kundang in the council area
- NS BlueScope Malaysia: COLORBOND steel, warranty against perforation by corrosion
- The Edge Malaysia, 7 November 2026: MITI imposes provisional anti-dumping duties on aluminium-zinc coated flat-rolled imports
- FactoryHub: Shah Alam Section 15 industrial area
- FactoryHub: industrial transactions (JPPH-registered sales and tenancies)
Units on the market nearby
Semi-D Factory for Rent in Saujana Teknologi Rawang, Rawang, 6,525 sq ft
RM 10,500/month
Semi-Detached Factory for Sale or Rent in Saujana Rawang, Rawang, 8,000 sq ft
RM 4,000,000 · RM 15,000/month
Detached Factory for Rent in Batu 17 Rawang, 9,000 sq ft
RM 21,000/month
More on buying a factory or industrial land
- Buying Industrial Land in Serendah or Batang Kali: Title Category, Land Conversion and Approvals to Check
- Before You Buy Industrial Land to Build a Factory in Rawang, Serendah or Shah Alam: Conversion, Access, Utilities, Soil, Filling, Slopes, Rivers and Flood Level
- Is the Factory Asking Price Fair? Price per Square Foot, JPPH Deals and How Much to Negotiate in Rawang, Serendah and Shah Alam
- Bank Valuation Lower Than the Purchase Price, or Factory Loan Rejected? What to Do in Rawang, Serendah and Shah Alam