Warehouse vs Factory in Rawang, Serendah and Shah Alam: Fire Rules, Floor, Power, Licences and Switching One to the Other
Factories and warehouses differ mainly in use class, which drives the fire rules: a single-storey warehouse of combustible goods needs automatic sprinklers from 1,001 m², a factory only above 2,000 m². Since July 2025 both pay the same TNB tariff. Switching storage to production is a material change of use needing planning permission and a different council licence.
Key Takeaways
- The law sorts a building by its use, not by how it looks. The Uniform Building By-Laws put a factory in Purpose Group VI and a place for storing goods in Purpose Group VIII, and a building with mixed uses is classed by its main purpose (UBBL, by-law 134 and Fifth Schedule).
- A warehouse of combustible goods reaches the sprinkler line sooner. In a single-storey building the Tenth Schedule asks for automatic sprinklers above 2,000 m² for a factory, but from 1,001 m² (or 7,001 m³) for a warehouse of combustible goods. Bomba's fire certificate follows the same split (Palcon's copy of the designated premises schedule).
- The TNB tariff no longer depends on which one you are. Since 1 July 2025 the old commercial Tariff B and industrial Tariff D both became the Non-Domestic Low Voltage tariff (myTNB). What differs is how much supply the unit has.
- Switching use is a planning matter first. A material change in the use of a building counts as development and needs planning permission (Town and Country Planning Act 1976, sections 2 and 19). Land in the "industry" category covers factories and warehouses alike, but an express condition on the title can be narrower.
- Licences follow the activity. In Hulu Selangor, the council allows making and processing only in premises with industrial or factory status, and an industrial licence can need DOE, Bomba and DOSH papers that a plain store does not (MPHS licence form).
What makes a building a factory or a warehouse in Malaysia?
The same steel shed in Rawang can be called a factory by one caller and a warehouse by the next. On paper the line is sharper. The Uniform Building By-Laws 1984 (UBBL), which the councils apply to building plans, define a factory as a building designed, adapted or used for making an article or part of one; for altering, repairing, finishing, cleaning or breaking up articles; or for adapting articles for sale or assembly (UBBL, by-law 2). For the fire rules, the Fifth Schedule puts factories in Purpose Group VI and "storage and general", a place for storage, deposit or parking of goods and materials, in Purpose Group VIII.
Two sentences in by-law 134 decide most borderline cases:
- a building or compartment is classed by its use or intended use, and where it serves more than one purpose, only the main purpose counts;
- where a building is divided into compartments used for different purposes, each compartment is classed separately.
So a factory with a big finished-goods store can remain a factory, while a warehouse where goods are repacked or kitted may come close to the factory definition, because "adapting for sale" is part of it. When a client's work sits between the two, I ask their architect how the approved plans describe the use before we talk about rent.
The land title is a separate layer. Land in the "industry" category under the National Land Code carries an implied condition that it is used for factories, workshops, foundries, warehouses and similar buildings for manufacture, or for the assembling, processing, storage, transport or distribution of goods (National Land Code, section 117). At title level, factory and warehouse usually sit in the same category. I still read the express condition endorsed on the title, because it can be narrower, and section 117 also bars demolishing, altering or extending a building without the prior written consent of the appropriate authority.
For the nationwide comparison of specs, power and approvals, see FactoryHub's warehouse vs factory comparison.
How do the fire rules differ between a factory and a warehouse?
This is where the two part ways most, and where a cheap unit can turn expensive. The Tenth Schedule of the UBBL lists the fire extinguishing and alarm systems each building needs (Tenth Schedule). For single-storey buildings:
| Total floor area | Factory (detached, semi-D or terrace) | Warehouse of combustible goods |
|---|---|---|
| Under 250 m² | none listed | none listed |
| 250 to 500 m² | none listed | manual fire alarm |
| 501 to 749 m² | none listed | hose reels, automatic detection and manual alarm (below 7,000 m³) |
| 750 to 1,000 m² | hose reels and manual alarm | hose reels, automatic detection and manual alarm (below 7,000 m³) |
| 1,001 to 2,000 m² | hose reels, automatic detection and manual alarm | automatic sprinklers, hose reels, manual alarm and automatic fire monitoring |
| 2,001 to 10,000 m² | automatic sprinklers, hose reels, manual alarm, public address and automatic fire monitoring | automatic sprinklers, hose reels, manual alarm and automatic fire monitoring |
| Over 10,000 m² or 70,000 m³ | as the row above | adds a pressurised hydrant system |
For scale, 1,000 m² is about 10,764 sq ft and 2,000 m² about 21,528 sq ft. A warehouse of non-combustible products, such as clay, is treated more lightly: a single-storey one needs nothing listed below 2,000 m², and hose reels with a manual alarm above that.
Bomba's fire certificate uses the same split. A factory becomes a designated premises at 2,000 m² or more of floor area fitted with automatic sprinklers, or at any size with a hazardous process; storage becomes designated at 1,000 m² or more, or 7,000 m³ or more, fitted with sprinklers (Palcon). The fees differ too: RM1,000 for a new factory certificate and RM500 to renew it, against RM500 and RM250 for storage (Fire Services (Fire Certificate) Regulations 2001, Sixth Schedule). My Bomba fire certificate guide covers renewal and who holds it.
The schedules also size the escape routes by use. The Seventh Schedule assumes one person per 10 m² gross in a factory and one per 30 m² gross in a warehouse. On 2,000 m², that is 200 people against about 67, and exits are sized from that number.
Do floor loading, height and layout differ?
The UBBL no longer prints its own table of floor loads. By-law 59 says all imposed floor loads are calculated in accordance with MS EN 1991-1-1, and by-law 60 says that where forklift trucks or other mechanical stacking machines may be used, the floor design must make special provision for them (UBBL, by-laws 59 and 60). So there is no single "warehouse figure" or "factory figure" to quote: the slab carries what its engineer designed it for, and that design sits in the structural calculations and plans.
Height works differently for each. By-law 44 requires at least 3 metres of headroom in any room of a factory where a person works. A warehouse is built tall for racking, and height counts against it, because the storage thresholds above use cubic metres as well as floor area: a 1,000 m² store with an average internal height of 7 metres already holds 7,000 m³. In buildings of more than one storey, the Fifth Schedule caps a storage compartment at 21,000 m³, against 28,000 m³ for a factory, in buildings up to 28 metres high.
On a viewing I ask for:
- the structural drawings or the engineer's note showing the slab's design load, and whether forklifts were allowed for;
- where the client's heaviest machines or racking will stand, and whether they need their own plinths;
- the clear height under the roof beams, the sprinkler heads and the lights, measured, not taken from a brochure;
- visible cracks, sunken joints or patched areas near the loading bay, which tell me how the floor has been used.
Does a warehouse need a different TNB supply or tariff?
Not a different tariff. TNB's table maps the old Tariff B (low voltage commercial) and Tariff D (low voltage industrial) into one Non-Domestic Low Voltage tariff, and the old C1 and E1 into one Non-Domestic Medium Voltage General tariff (myTNB). A store and a workshop on the same supply now pay the same rates; my TNB tariff guide shows how to estimate the bill.
What differs is the supply itself. A warehouse mostly runs lights, doors, dock levellers and forklift chargers, unless it is a cold store; a production floor runs machines, compressors and ovens. When a client plans to turn a warehouse into a factory, power is the first specification I compare: the machine list against the supply shown on the bill and the switchboard. Loads above 1,000 kVA (850 kW) must take supply at medium voltage (TNB Connection Charges Book 2025), and an upgrade can bring a substation onto the lot, which my compact substation guide explains.
Which licences change between storage and production in Rawang, Serendah and Shah Alam?
Each council licenses the activity at the premises, so the paperwork follows what you do inside:
- Rawang (Majlis Perbandaran Selayang). MPS licenses premises that have planning approval or a development order, an approved building plan and a CF or TCF, and that meet Bomba's requirements (MPS licence conditions). The licence therefore leans on the use the plans approved.
- Serendah, Bukit Beruntung and Batang Kali (Majlis Perbandaran Hulu Selangor). The MPHS form says making and processing may be carried out only in premises with industrial or factory status, that a licence holder may not change or add an activity without applying to the council, and that renovated premises need the council's Building Department approval. For an industrial or manufacturing licence it lists DOE approval for activities that produce waste, recycle, handle plastics or could harm the environment, Bomba approval and a DOSH machinery certificate. Food and drink warehouses carry their own conditions, including a current pest control certificate (MPHS form).
- Shah Alam (Majlis Bandaraya Shah Alam). MBSA issues one composite licence for business and industrial premises, asks for a copy of the CCC or CF, and charges a RM50 processing fee for a business application and RM100 for an industrial one (MBSA).
Above the council sits the manufacturing licence. The Industrial Co-ordination Act 1975 requires manufacturing companies with shareholders' funds of RM2.5 million and above, or 75 or more full-time paid employees, to hold one, and it defines manufacturing activity as making, altering, blending, finishing or otherwise treating or adapting an article, including assembly, but not activity normally associated with retail or wholesale trade (MIDA). A pure storage operation falls outside that; whether repacking or labelling counts is a question for MIDA, not for me. Where the process sits on Ms Teh's light, medium and heavy industry guide also shapes what the planners will accept.
Can a warehouse be used as a factory, or a factory as a warehouse?
Often yes, but neither is automatic.
Factory to warehouse. This looks like the easy direction, yet the fire table runs the other way. A single-storey factory of 1,500 m² with an average internal height of 6 metres (9,000 m³) needs hose reels, detection and a manual alarm; fill it with cartons, plastics or other combustible stock and the warehouse row asks for automatic sprinklers. Once sprinklers are in and the floor area is 1,000 m² or more, the building is also a designated premises that needs a yearly fire certificate. I raise this before a logistics client falls for a well-priced older factory.
Warehouse to factory. Production is a different use, and the Town and Country Planning Act treats a material change in the use of a building, or a use contrary to the development plan, as development that needs planning permission (Act 172, sections 2 and 19). MPS forms already ask for a planning permission for material change (KMPM) or a change-of-use approval letter (tukar guna bangunan) from its Town Planning Department, for example before workers are housed on an existing industrial premises (MPS form JB-B04(A)), so that department is where I start. If the title's express condition names a narrower use, the owner applies to the State Authority to amend it under section 124 of the National Land Code. Then come the practical changes: three times the occupant load for exits and toilets, a supply sized for machines, a floor checked for machine loads, and the DOE and DOSH papers listed above.
Both under one roof. A store inside a factory is normal. If the two are split into compartments, each is classed on its own use; if not, the main purpose decides.
What I check before a client signs
- The use written on the approved plans and the CCC or CF, against what the client will actually do.
- The title's category and express condition.
- The floor area and internal height, worked into m² and m³ against the fire tables above.
- The sprinklers, hose reels and alarm panel actually installed, and any fire certificate on the wall.
- The TNB supply on the latest bill and the switchboard, against the client's load.
- The structural design load, if the client brings forklifts, racking or heavy machines.
- Which council licence the activity needs, and the documents that council asks for.
For more on each place, see the Rawang, Serendah and Shah Alam pages, current units on the warehouse and factory pages, and my wider list of what to check before renting a factory in Rawang. For price context, the JPPH-registered transactions for Rawang and Kundang record warehouses as their own type: 6 deals in 24 months, median price RM5.61 million, RM147 psf of land, median land 49,175 sq ft, while the median detached factory there sat on 26,215 sq ft of land (Rawang and Kundang transaction prices and rents). These are the registered records available so far, not every deal in the area.
To check whether a factory or warehouse in Rawang, Serendah or Shah Alam fits the way you will use it, WhatsApp Jason Low (Probationary Estate Agent PEA 1478, CID Realtors Sdn Bhd E(1) 1855) on +60 12-288 1834.
Also answered on this site: Does a warehouse need a Bomba fire certificate?
Questions people ask
01Can I run a factory in a warehouse in Rawang or Serendah?+
Only with the right approvals. Production is a different use from storage, and a material change in the use of a building needs planning permission under the Town and Country Planning Act 1976. In Hulu Selangor, the MPHS licence form also says making and processing may be carried out only in premises with industrial or factory status, so check the approved use before you sign.
02Can a factory be used as a warehouse?+
Often yes, but check the fire rules first. In a single-storey building, a warehouse of combustible goods needs automatic sprinklers from 1,001 m² (or 7,001 m³), while a factory needs them only above 2,000 m². A 1,500 m² factory without sprinklers may therefore need them before it can store cartons or plastics.
03Is the TNB tariff different for a warehouse and a factory?+
No. Since 1 July 2025, TNB has mapped the old commercial Tariff B and industrial Tariff D into one Non-Domestic Low Voltage tariff, and the old C1 and E1 into one Medium Voltage General tariff. What differs is the supply: loads above 1,000 kVA (850 kW) must take medium voltage supply.
04Does a warehouse need a manufacturing licence?+
A warehouse that only stores goods does not carry out manufacturing activity as the Industrial Co-ordination Act 1975 defines it, so the MIDA manufacturing licence does not arise. The licence applies to manufacturing companies with shareholders' funds of RM2.5 million and above or 75 or more full-time paid employees. Whether repacking or labelling counts as manufacturing is a question to put to MIDA.
05Is a warehouse floor stronger than a factory floor?+
Not by definition. The Uniform Building By-Laws require imposed floor loads to be calculated to MS EN 1991-1-1 and special provision where forklifts may be used, so each slab carries what its engineer designed it for. Ask for the structural drawings or the engineer's note before you bring in racking, forklifts or heavy machines.
06Is it better to invest in a logistics warehouse or a manufacturing factory in Rawang or Shah Alam?+
Neither is better by default: it depends on the tenant you can attract and the fire rules that come with that use. In a single-storey building, a warehouse of combustible goods needs automatic sprinklers from 1,001 m², while a factory needs them only above 2,000 m², so a smaller factory may cost less to fit out. Before you compare, check the approved use, the express condition on the title, the TNB supply, and which licence the council (MPS or MBSA) asks for that activity.
07Which gives a better return on investment in northern Selangor, a warehouse or a factory?+
There is no fixed answer: return comes from the rent, the fit-out cost and the tenant, not from whether the building is called a warehouse or a factory. JPPH-registered transactions in Rawang and Kundang list warehouses as a separate type, with 6 deals in 24 months, a median price of RM5.61 million, RM147 psf of land and a median land size of 49,175 sq ft; the median detached factory there sat on 26,215 sq ft of land. Weigh the fire fit-out and licence needs of each, and confirm the use with MPS or MPHS.
Sources
- Uniform Building By-Laws 1984 as amended (OSHWARE text): by-laws 2, 44, 59, 60 and 134; Fifth, Seventh and Tenth Schedules
- PAM: Uniform Building By-Laws 1984 (amendment 2021), revisions to the fire safety provisions and Fifth Schedule
- Palcon: Perakuan Bomba, schedule of designated premises for factories and storage
- Laws of Malaysia: Fire Services (Fire Certificate) Regulations 2001, reprint as at 1 April 2023, Sixth Schedule fees
- Town and Country Planning Act 1976 (Act 172): sections 2 and 19
- National Land Code (Act 828), PKNS copy: sections 117 and 124
- Majlis Perbandaran Selayang: form JB-B04(A), KMPM and change of building use approval letters (updated 5 March 2026)
- Majlis Perbandaran Selayang: licence application and approval conditions
- Majlis Perbandaran Hulu Selangor: composite premises licence form, documents and general conditions
- Majlis Bandaraya Shah Alam: Lesen Komposit (Perniagaan / Perindustrian), documents and processing fees
- MIDA: Approval and Licensing, Industrial Co-ordination Act 1975 manufacturing licence
- myTNB: tariff page, tariff category mapping from 1 July 2025
- TNB Connection Charges Book 2025: supply above 1,000 kVA (850 kW) at medium voltage
- FactoryHub: Rawang and Kundang JPPH-registered transaction prices and rents
Units on the market nearby
Semi-D Factory for Rent in Saujana Teknologi Rawang, Rawang, 6,525 sq ft
RM 10,500/month
Semi-Detached Factory for Sale or Rent in Saujana Rawang, Rawang, 8,000 sq ft
RM 4,000,000 · RM 15,000/month
Detached Factory for Rent in Batu 17 Rawang, 9,000 sq ft
RM 21,000/month
More on licences, bomba and approvals
- Business Premise Licence for a Factory or Warehouse in Rawang, Serendah and Shah Alam: What MPS, MPHS and MBSA Ask For, Signboard Rules, Timelines and Refusals
- Light Industrial Factory, or Medium or Heavy? How Zoning Classes and Buffer Zones Work in Rawang, Serendah and Shah Alam, and How I Check a Unit
- Illegal Factory Extension in Rawang, Serendah or Shah Alam: What MPS, MPHS and MBSA Can Do and How to Make It Legal
- Factory Wastewater in Rawang, Serendah and Shah Alam: Industrial Effluent Regulations 2009, LUAS Licences and What I Check in the Building