Can You Sublet or Split a Factory in Rawang, Serendah or Shah Alam? Landlord Consent, Council and Bomba Rules, Insurance and Meters

Written by , PEA 1478 · Published · Renting a factory or warehouse

Short answer

Yes, with permission at each level. Tenants may sublet only if the tenancy allows; owners letting part of a factory may need bank and sometimes State consent. A partition wall needs written council permission (section 79, Act 133), Bomba must be told, the fire insurer must endorse the change of occupation, and TNB contracts one registered user per premises.

A single-storey factory with two open roller shutters side by side, a white partition wall inside dividing the floor into two units, and a separate meter cabinet beside each door.
Illustrative image

Key Takeaways

  • The tenancy decides whether a tenant may sublet. The National Land Code lets a tenant grant a subtenancy of the whole or part of what they hold, but only within the terms of their own tenancy (National Land Code, sections 223 and 225). A registered lease carries an implied promise not to sublet without the lessor's written consent unless it says otherwise.
  • An owner letting part of a factory may need two more consents. Charged land cannot be let without the bank's consent (section 226), and a title whose restriction in interest bars leasing without State Authority consent goes to PTG Selangor first.
  • A partition is building work. Section 79 of the Street, Drainage and Building Act 1974 requires the council's prior written permission for any partition or compartment, and the owner is presumed to have put it up.
  • Every occupier needs its own premises licence. MPS in Rawang, MPHS in Serendah, Batang Kali and Bukit Beruntung, and MBSA in Shah Alam each license the business at the address, so a sub-tenant applies in its own name.
  • Bomba, insurance and meters change too. The occupier must tell Bomba before a material change, a standard fire policy stops covering property when the occupation changes in a riskier way without the insurer's endorsement, and TNB contracts one registered user per premises.

Can a tenant sublet a factory in Malaysia?

The question comes to me in two forms: a tenant who has more space than they need and wants to let part of it, or a business that wants to move into part of someone else's factory. The law starts in the same place for both.

Under the National Land Code, a tenancy of three years or less is a "tenancy exempt from registration". Section 223(1)(c) allows a person holding land under such a tenancy to grant a subtenancy of the whole or any part of it, and section 228A says a part of the land includes a part of a building, so half of a factory floor counts (National Land Code, Act 828). Section 225(1)(c) then makes that power subject to "the provisions, express or implied" of the tenancy itself. If the tenancy agreement says the tenant may not sublet, share or part with possession without the landlord's written consent, that clause governs.

For a registered lease of more than three years, section 231(1)(d) implies a promise by the lessee not to sublet or otherwise part with possession without the lessor's prior written consent, "which consent shall not be unreasonably withheld", unless the lease expressly says otherwise. Where the letting is a tenancy of three years or less, the written clause is what we read, because section 231 is written for registered leases.

When a tenant asks me whether they can let part of their unit, I read four things in their own tenancy first:

  1. The subletting clause. I read it for words such as "share" or "allow any other person to occupy", which reach informal arrangements as well as a written sub-tenancy.
  2. The permitted use clause. The sub-tenant's business has to fit it, and it has to fit the zoning of the lot. Ms Teh's note on light, medium and heavy industry explains how that classification works.
  3. The expiry and break dates. The sub-tenant needs to know the date on which the head tenancy itself can end.
  4. Reinstatement. Someone has to remove the partition and the extra wiring at the end, so I check whether the head tenancy says who.

The sub-tenancy agreement is stamped like any tenancy; FactoryHub's tenancy stamp duty calculator works out the duty. If you are the owner taking in a new company, my note on screening a factory tenant covers the company checks.

What does the owner need before letting part of a factory?

When the owner, not a tenant, wants to let half of a building, two consents sit outside the tenancy.

The bank. Section 226(1) of the National Land Code says that where land is subject to a charge, the proprietor cannot grant any lease, sublease or tenancy without the chargee's consent. For a tenancy, section 226(2) requires that consent in writing, signed by the chargee or its authorised agent.

The State. PTG Selangor describes a restriction in interest with the example that the land "tidak boleh dipindahmilik, digadai atau dipajak melainkan dengan kebenaran Pihak Berkuasa Negeri" (may not be transferred, charged or leased without State Authority consent). The application goes through the district land office on the consent form for transfer, lease or sublease, with the latest official search, the current quit rent and assessment receipts, and the chargee's consent letter if the land is charged. The fee is RM50 (PTG Selangor). I read the restriction on the title search before the owner signs anything, and where it mentions leasing I ask the owner's lawyer whether the planned letting needs consent.

A long lease of part. A lease of part of a lot can run for at most thirty years under section 221(3)(b), and the Form 15A instrument must carry a plan that identifies the part.

Selling part. A partition does not create a separate title. To sell one half as its own property, the land has to be subdivided under section 135 with the approval of the State Director or the Land Administrator, which is a separate process.

Does a partition wall need council approval in Rawang, Serendah or Shah Alam?

Yes. Section 79(1) of the Street, Drainage and Building Act 1974 says no one may erect any partition, compartment, gallery, loft, roof, ceiling or other structure in a building without the local authority's prior written permission. Section 79(2) presumes the owner carried out the work until proved otherwise, and section 79(3) lets the council enter, remove the structure and recover the cost from the owner. That is why I ask owners to apply themselves, even when the tenant is paying for the wall.

Area Council What its own pages say
Rawang Majlis Perbandaran Selayang (MPS), covering Mukim Rawang A licensed building may not be altered without permission; the premises need building plan approval and a CF or TCF (MPS licence conditions)
Serendah, Batang Kali, Bukit Beruntung Majlis Perbandaran Hulu Selangor (MPHS) The licence form asks for the renovation approval receipt or a temporary building permit where there are partitions, and works involving partition walls need council approval (MPHS form)
Shah Alam Majlis Bandaraya Shah Alam (MBSA) A partition wall in a commercial or industrial building needs a temporary building permit under section 79 (MBSA FAQ)

The split also reaches the assessment bill. MBSA lists alterations to an existing building among the reasons it amends the valuation list under section 144 of the Local Government Act 1976, and it issues amendment notices on 1 March, 1 June, 1 September and 1 December (MBSA). I tell owners to expect that notice and to ask the valuation department how the divided building will be assessed. A mezzanine or an office loft added for the sub-tenant falls under the same section 79; my note on factory floor loading covers that.

Does each company in a shared factory need its own licence?

Yes. Each council licenses the business carried on at the premises, not the building. MPHS asks a business in a rented building for either a stamped tenancy agreement or the building owner's consent certified by a Commissioner for Oaths, and the address registered with SSM must match the premises (MPHS form). MBSA's composite licence asks for the CCC or CF, any building permit, a location sketch and a floor plan, with a processing fee of RM100 for an industrial licence (MBSA). A floor plan that shows half a building without an approved partition is where the two questions meet.

What does Bomba look at when one factory becomes two?

Under the Fire Services Act 1988, where part of a premises is designated, the other parts are treated as part of the designated premises (section 27(2)). A designated premises needs a fire certificate renewed every year (section 28), the applicant can be the owner, the occupier or the person managing the premises (section 29(6)), and an occupier who plans a material change must notify Bomba before the work begins (section 32(2)). If no fire certificate is in force, the owner commits the offence (section 33).

The dividing wall can matter too. By-law 138(c) of the Selangor Uniform Building By-Laws 1986 says a wall separating a part used for a different purpose group must be a compartment wall, and the Fifth Schedule puts factories in Purpose Group VI and storage in Purpose Group VIII. A building where one side manufactures and the other only stores goods is that case.

On a site visit I check that both halves keep a route to an exit, who owns the fire alarm panel, that hose reels and extinguishers reach both sides, and who will renew the fire certificate. My notes on the Bomba fire certificate and fire protection systems go further.

Who insures what when a factory is shared?

Read your own policy, because wordings differ. QBE Malaysia's non-consumer fire policy is a useful example. Its condition 9 says the insurance ceases to attach to the property affected, unless the insurer endorses the policy before any loss, if the trade or manufacture is altered or the nature of the occupation changes in a way that increases the fire risk, or if the building stays unoccupied for more than thirty days. Its Tenants Clause, where it is added, keeps the owner covered after a change the owner did not know about, provided the owner tells the insurer as soon as they learn of it (QBE fire policy).

In practice the owner tells their insurer before the sub-tenant moves in, the head tenant tells theirs, and the sub-tenant insures its own stock and liability. The sub-tenancy should say who insures the partition itself.

How are electricity and water split between two occupiers?

TNB contracts only one registered user for a premises at any one time, and that registered user, owner or tenant, answers for claims on the account, including use that breaks the Electricity Supply Act (TNB landlord and tenant booklet). Section 9(1)(b) of the Electricity Supply Act 1990 says no one other than a supply authority may supply electricity from an installation to another person without a licence, subject to prescribed exemptions.

TNB's Electricity Supply Application Handbook meters a single-tenant premises at the incoming switchboard. For multi-tenanted premises it describes two routes: a bulk supply, for which the owner needs a public distribution licence from the Energy Commission, or individual supplies to the landlord and each tenant following TNB's connection schemes. When a split is meant to last, I suggest the owner asks TNB about separate supplies. When it is short, the parties agree in writing how the bill is shared, and ask the Energy Commission before charging a sub-tenant through a private sub-meter. Check that the incoming supply covers both operations; FactoryHub's factory power calculator gives a first estimate and my note on TNB tariffs explains the rates. For water, I ask whose name the account is in and how each side's use will be measured.

What I check before a client sublets, shares or splits a factory

Check Who holds it Why
Subletting and use clauses in the head tenancy Tenant Section 225(1)(c) makes the power to sublet subject to them
Title search: restriction in interest and any charge Owner State and bank consent come before the letting
Bank's written consent Owner's bank Section 226(2)
Council permission for the partition Owner Section 79 of Act 133
Fire certificate and notice of the change Occupier and owner Sections 32(2) and 33 of Act 341
Insurer endorsements Each insured party A change of occupation can end the cover
TNB account and supply route Registered user One registered user per premises
Sub-tenant's own licence with a stamped sub-tenancy Sub-tenant Each council licenses the business

Registered rents for the area are on FactoryHub's Rawang transactions page, and units on my side are on the Rawang, Serendah and Shah Alam pages.

To have the tenancy, title and permits checked before you sublet, share or split a factory in Rawang, Serendah or Shah Alam, WhatsApp Jason Low (Probationary Estate Agent PEA 1478, CID Realtors Sdn Bhd E(1) 1855) on +60 12-288 1834.

Questions people ask

01Is subletting a factory legal in Malaysia?+

Yes, when the tenancy and the title allow it. Section 223(1)(c) of the National Land Code lets a tenant grant a subtenancy of the whole or part of the land they hold, and section 228A says part of the land includes part of a building. Section 225(1)(c) makes that power subject to the tenancy's own terms, so a no-subletting clause wins.

02Does the landlord have to agree before I sublet part of my factory?+

Under a tenancy of three years or less, the written clause in the tenancy decides, so read it before anything else. Under a registered lease of more than three years, section 231(1)(d) of the National Land Code implies a promise not to sublet without the lessor's prior written consent, which may not be unreasonably withheld, unless the lease says otherwise.

03Do I need council approval to put up a partition wall in a factory?+

Yes. Section 79(1) of the Street, Drainage and Building Act 1974 requires the local authority's prior written permission for any partition or compartment, and section 79(2) presumes the owner built it. MBSA asks for a temporary building permit for a partition in an industrial building, and MPHS asks for the approval receipt or temporary permit with a licence application.

04Does each company sharing a factory need its own business licence?+

Yes. The council licenses each business at the address. MPHS asks a business in a rented building for a stamped tenancy agreement or the owner's consent certified by a Commissioner for Oaths, and the SSM address must match the premises. MBSA's composite licence asks for the CCC or CF, any building permit and a floor plan.

05Can a landlord charge a sub-tenant for electricity through a sub-meter?+

Check first. TNB contracts one registered user per premises, and section 9(1)(b) of the Electricity Supply Act 1990 bars anyone other than a supply authority from supplying electricity to another person without a licence, subject to prescribed exemptions. Ask the Energy Commission before re-billing, or ask TNB about separate supplies when the split is permanent.

06Will my fire insurance still cover the factory after I sublet part of it?+

Only if the insurer knows. A standard Malaysian fire policy, such as QBE's non-consumer wording, says cover ceases for the property affected if the trade or the nature of the occupation changes in a way that increases the fire risk, unless the insurer endorses the policy before any loss. Tell your insurer before the sub-tenant moves in.

Sources

  1. National Land Code (Act 828, revised 2020), sections 135, 213, 221 to 228A, 231 (FAOLEX copy)
  2. PTG Selangor: consent to transfer, lease or sublease where the title carries a restriction in interest (documents, RM50 fee)
  3. Street, Drainage and Building Act 1974 (Act 133), section 79, reprint as at 1 June 2014 (Perbadanan Putrajaya copy)
  4. Majlis Bandaraya Shah Alam: development FAQ, partition walls in commercial and industrial buildings need a temporary building permit
  5. Majlis Bandaraya Shah Alam: Lesen Komposit (Perniagaan / Perindustrian), documents and processing fees
  6. Majlis Bandaraya Shah Alam: Pindaan Nilaian (section 144 Act 171, amendment notice dates)
  7. Majlis Perbandaran Hulu Selangor: composite premises licence form MPHS/JP/001 (documents and general conditions)
  8. Majlis Perbandaran Hulu Selangor: background, mukim and towns
  9. Majlis Perbandaran Selayang: licence application and approval conditions
  10. Majlis Perbandaran Selayang: administrative area (Mukim Rawang, Batu, Setapak)
  11. Laws of Malaysia: Fire Services Act 1988 (Act 341), sections 27 to 33 (AGC reprint)
  12. Selangor Uniform Building By-Laws 1986, updated to Sel.P.U. 142/2012: by-law 138 and Fifth Schedule (KPKT JKT copy)
  13. QBE Insurance (Malaysia): Fire Insurance Policy wording, non-consumer, condition 9 and Tenants Clause
  14. TNB: Clarification on tenant and landlord matters regarding electricity supply (booklet)
  15. Electricity Supply Act 1990 (Act 447), section 9, reprint as at 1 March 2013 (ADB copy)
  16. TNB: Electricity Supply Application Handbook 3.1 (2022), single and multi-tenanted premises
  17. FactoryHub: tenancy stamp duty calculator
  18. FactoryHub: factory power calculator
  19. FactoryHub: Rawang and Kundang JPPH-registered industrial transactions

Units on the market nearby

More on renting a factory or warehouse

All guides: Renting a factory or warehouse →

Probationary Estate Agent · PEA 1478 · CID Realtors Sdn Bhd E(1) 1855About Jason → · Contact →
Ask Jason about this