Factory With Overhead Crane for Rent or Sale in Rawang, Serendah and Shah Alam: Crane Beams, 5 to 20 Ton Cranes, DOSH Approval and What to Check
Yes, a factory in Rawang, Serendah or Shah Alam can run an overhead crane or goods lift, but two approvals apply. Columns, crane beams and footings must be designed for the crane, and new structures need the council's written permission. The crane needs DOSH design verification, installation approval and a certificate of fitness, valid 15 months, before use.
Key Takeaways
- The law changed on 1 June 2024. Cranes, hoists, lifts, boilers and pressure vessels now fall under Part VIA of the Occupational Safety and Health Act 1994 and the Plant Requiring Certificate of Fitness Regulations 2024, which replaced the Factories and Machinery Act regime.
- Two approvals from two authorities. DOSH approves the crane. The council approves new columns, brackets, runway beams or a lift shaft: MPS for Rawang and Kundang, MPHS for Serendah, Sungai Choh, Bukit Beruntung and Batang Kali, MBSA for Shah Alam.
- 5, 10 and 20 ton cranes go through the same DOSH steps. What changes is the inspection fee (RM750, RM950 and RM1,200 for each inspection) and the load the building has to carry.
- A certificate of fitness lasts 15 months and ends if the crane is dismantled, repaired or damaged. Operating a crane without one can mean a fine of up to RM100,000, a year in jail, or both.
- Before you rent or buy, I ask for the crane's certificate of fitness, its design verification, the approved structural plans showing the crane beams, and a written answer on who owns the crane and who pays its inspections.
Is DOSH approval still needed for an overhead crane now that the Factories and Machinery Act is gone?
Yes, and the rules are now in a different law. The Plant Requiring Certificate of Fitness Regulations 2024 came into operation on 1 June 2024 and name three kinds of plant that need a certificate of fitness: steam boilers, pressure vessels and lifting machinery. Lifting machinery is defined widely, as "any equipment for lifting, raising, transporting or lowering loads", and an overhead travelling crane is a crane with a girder that raises and lowers loads and moves on a fixed runway.
The Occupational Safety and Health Act 1994 carries the two prohibitions that matter. Section 27C bars anyone from installing prescribed plant without the Director General's written approval. Section 27D bars anyone from operating it without a certificate of fitness issued by a DOSH officer or a licensed person. Each offence carries a fine of up to RM100,000, up to one year in jail, or both, and ignoring a DOSH notice to stop using the crane raises that to RM500,000 or two years.
Two things from the old system help buyers and tenants. DOSH's FAQ on the Factories and Machinery (Repeal) Act 2022 says owners no longer apply for a first factory inspection after 31 May 2024, so you do not register the building itself with DOSH when you move into a factory in Rawang or Shah Alam. The same FAQ says certificates of fitness issued on or before 31 May 2024 stay valid until they expire. An older crane may therefore still carry a certificate from the old regime; at its next inspection it moves into the new 15-month cycle.
Which equipment in a factory must have a DOSH certificate of fitness?
DOSH's 2025 application guide for lifting machinery says equipment is classified by what it does, not by what the supplier calls it. This is how the regulations sort what I usually see in a factory:
| Equipment | Certificate of fitness? | Where the rule sits |
|---|---|---|
| Overhead travelling crane: single girder, double girder, underhung, monorail (DOSH lists monorails "including SWL < 4T") | Yes | Regulation 3, guide Appendix 1A |
| Gantry crane or jib crane | Yes, as "other crane" | Guide Appendix 1A |
| Goods lift for goods only, goods hoist, material hoist, dumbwaiter | Yes, in the hoist category | Guide Appendix 1A |
| Lift that carries people, or people and goods | Yes, as a lift | Regulation 2 |
| Steam boiler | Yes | Regulation 3 |
| Air receiver and other pressure vessels | Yes, unless listed in the Second Schedule (for example, design pressure not over 15 psig) | Regulation 3, Second Schedule |
| Forklift, dock leveller, tail lift, vertical conveyor, automated storage and retrieval system, manipulator | No | Third Schedule |
| Crane lifting no higher than 9 m and no more than 80 kg; air or pneumatic lifting up to 500 kg | No | Third Schedule |
| Chain block, chain sling, shackle and other lifting tackle | Not a certificate item, but must meet a recognised standard and be in good condition | Regulations 2 and 16 |
What does the building need before an overhead crane goes in?
A crane hangs its whole working load on the building. The load runs from the hook to the crane girder, then to the runway beams (the crane beams), the brackets on the columns, the columns and finally the footings. Each link has to be designed for it. The building's usable height needs checking too; I explain clear height versus ceiling height in a separate guide.
Selangor's building by-laws say so directly. By-law 69 requires crane gantry girders to be designed for vibration, shock from slipping slings, acceleration and braking, and the impact of wheel loads, to MS EN 1991-1-1. By-law 68 requires the framework to allow for dynamic effects from machinery, runways and cranes. On the DOSH side, regulation 4(1)(h) makes the person installing the crane ensure its foundation is designed and built to carry the load, and DOSH's guide asks for the design calculation of the crane's support system by a certified professional engineer where required.
Height is the other limit. What matters is not the eave height in a brochure but the clear height to the lowest thing under the roof: the truss or haunch, lights, sprinkler pipes. Take away the crane's own depth and its clearance and you have the hook height. I ask the crane supplier for a clearance drawing laid over the building section before a client signs, and I compare the hook height with the tallest load the client lifts. The floor matters too, for the loads set down under the crane; my floor loading guide covers that.
New structural work needs the council. Section 79(1) of the Street, Drainage and Building Act 1974 says no one may erect any partition, compartment, gallery, loft, roof, ceiling or other structure in a building without the local authority's prior written permission, and section 70(11) sets a fine of up to RM25,000 for altering a building without permission, with a court able to order it altered or demolished. Each council handles it through its own forms:
- MPS (Rawang, Kundang): its checklist for additions and alterations through OSC 3.0 asks, where relevant, for structural plans and calculations with a covering letter from the structural engineer and Form A, signed by the submitting person.
- MPHS (Serendah, Sungai Choh, Bukit Beruntung, Batang Kali): it publishes checklists for additions and alterations, and for minor works on non-residential buildings.
- MBSA (Shah Alam): its development FAQ applies section 79 even to a partition wall in an industrial building.
So I treat new crane columns, brackets, runway beams or a lift shaft as structural work that goes to the council with an engineer's plans. A crane structure added without permission is the same problem as any unapproved factory extension.
5 ton, 10 ton or 20 ton: what changes?
The DOSH steps are the same for all three. The design verification fee for a crane other than a mobile, tower or quay crane is RM300 for each design unit. The inspection fees in the Sixth Schedule rise with the safe working load (SWL):
| Safe working load | First certificate of fitness inspection | Each periodic inspection |
|---|---|---|
| Under 3,000 kg | RM350 | RM350 |
| 3,000 kg to under 5,000 kg | RM600 | RM600 |
| 5,000 kg to under 10,000 kg (a 5 ton crane) | RM750 | RM750 |
| 10,000 kg to under 20,000 kg (a 10 ton crane) | RM950 | RM950 |
| 20,000 kg and above (a 20 ton crane) | RM1,200 | RM1,200 |
These are the government fees only. The crane company's price for supply, installation and the test weights varies, so get it itemised in the quotation. All three sizes are above 4,000 kg, and the Seventh Schedule lists overhead travelling cranes on standard I or H beam girders above that load among the plant that only a DOSH-registered competent person or the origin manufacturer may install or dismantle. You can check a company's registration and scope on DOSH's MyKKP search.
The building is where 5 and 20 tons differ. A heavier crane puts larger wheel loads on the runway beams, brackets, columns and footings, so the question "can this factory take a 20 ton crane?" has three possible answers:
- The frame was designed for a crane of that capacity. The approved structural plans will show crane beams and their design load. This is the easy case.
- The columns can be strengthened and brackets added. An engineer has to prove it, and the work goes to the council.
- A separate runway on its own columns and footings is built inside the building, so the crane load does not touch the existing frame. Again, engineer and council.
When none of these works, the answer is a building designed around the crane, and I look with the client at land in places like UMW HVM Park in Serendah or at detached units in heavy engineering estates such as HICOM Seksyen 26. Crane motors also add to the electrical load; my kVA to amps guide shows how to check the supply.
How does DOSH approve a new crane, step by step?
- Design verification. Applied for online through MySKUD, which you reach through MyKKP. For a crane made in Malaysia only a DOSH-registered competent person company may apply; for an imported crane, the origin manufacturer or its appointed installer or distributor. The file includes design drawings, calculations to a recognised standard, the safety features and the wire rope or chain certificate. DOSH's client charter is 15 working days for a complete application.
- Written approval to install. Only the owner, the occupier or the holder of the design verification may apply.
- Installation by the competent person or origin manufacturer.
- Inspection and certificate of fitness. The officer or licensed person carries out a load test at the load set in the design verification and a functional test of every safety device. The certificate runs 15 months from the inspection date.
- Periodic inspections. Each one falls no earlier than the first day of the twelfth month after the month of the last inspection. DOSH may give 14 days' written notice, and the owner or occupier must make the crane available to be tested under its safe working load.
Two limits catch people out. DOSH's guide does not allow design verification for used imported overhead travelling cranes, goods hoists or passenger hoists, so a second-hand crane shipped in from abroad is not a route. And moving your own crane from an old factory needs fresh written approval to install at the new site under regulation 4(3), plus alteration approval, which DOSH requires for a relocated overhead travelling crane even when the SWL does not change. My factory relocation guide puts that into the moving timetable.
Can I install a goods lift in my factory?
Yes, on the same two tracks. On DOSH's side the difference between a goods lift and a lift is who rides it. DOSH's guide lists the "Lif Barang (Goods Lift)" for transporting goods only, to EN 81-31, in its goods hoist category, with a design verification fee of RM300. The material hoist inspection fees run from RM350 below 500 kg to RM1,000 at 1,500 kg and above; ask the installer which category the design is verified under.
If staff will ride with the goods, it is a lift under the regulations. The design verification fee is RM5,000, the inspection fee starts at RM650 for a travel distance under 12 m, and regulation 14 requires a comprehensive examination by a competent person at least every three months.
On the building side, a lift shaft or hoist frame is a new structure, so it goes to MPS, MPHS or MBSA like a crane runway. Check the upper floor's loading where the goods will land.
What do I check when renting or buying a factory with an overhead crane?
On a site visit in Rawang, Serendah or Shah Alam, this is my list:
- The certificate of fitness. The number (DOSH's guide calls it the PMA number), the last inspection date, and an SWL that matches the plate on the crane. A certificate past its 15 months, or one from a crane that has since been repaired, damaged or taken down, is no longer good.
- The crane file. Regulation 20 requires the employer to keep the design verification, installation, testing, inspection, repair, alteration and maintenance records at the workplace. I ask the owner or outgoing tenant to hand the file over.
- Who owns the crane. A landlord's crane and an outgoing tenant's crane are different deals. When a crane is sold or leased, the owner must notify DOSH or the licensed person within 30 days, and must do the same within 30 days of finding it has fallen into disuse.
- The approved structural plans. I want the crane beams and their design load on approved plans. At MPS, copies of approved development plans can only be requested by the developer or the submitting person it appointed, so the owner has to produce them.
- Height and span. Hook height against your tallest load, and the span against the bay you will work in.
- The tenancy terms. Who books and pays each periodic inspection, who pays if the crane fails it, who repairs it, and whether a crane you install must be removed when you leave.
FactoryHub keeps a page of factories with cranes for rent in Selangor and a floor loading calculator for the slab side. Current units near me are on the Rawang detached factory and Shah Alam detached factory pages.
To have a factory with a crane in Rawang, Serendah or Shah Alam checked before you sign, WhatsApp Jason Low (Probationary Estate Agent PEA 1478, CID Realtors Sdn Bhd E(1) 1855) on +60 12-288 1834.
OSHA checks for a factory
How do I check whether a factory in Rawang or Shah Alam complies with OSHA requirements?
Check the factory's plant records against the Occupational Safety and Health Act 1994 and the 2024 regulations. For every crane, hoist, boiler or pressure vessel, ask for the certificate of fitness, the design verification and the maintenance file that regulation 20 requires at the workplace, and confirm that any new structure has MPS, MPHS or MBSA approval. A certificate past its 15 months, or one for a crane that has since been dismantled, is no longer valid, and that crane is not compliant. For fabrication shops, I cover zoning, power, crane and DOE checks in my guide to factories for metal fabrication and CNC.
Need around 30,000 sq ft with 1,000 A and a crane in Klang? The crane checks above are the same in Klang. Ms Teh Seok Hoon (PEA 4006), the CID Realtors colleague who handles Klang, lists Klang units with 1,000 A or more and high eaves by area in where to find 1,000 A and high-ceiling factories in Klang.
Questions people ask
01How do I find out the capacity of the crane beams in an existing factory?+
The capacity sits in the structural design, not on the beam itself. Ask the owner for the approved structural plans and calculations; at MPS only the developer or the submitting person it appointed can request copies of approved plans, so the owner has to obtain them. The crane's own safe working load is on its certificate of fitness and design verification. If neither exists, have a professional engineer assess the beams before you rely on them.
02Do large machines that do not lift anything need DOSH approval?+
Only plant named in the 2024 regulations needs a certificate of fitness: steam boilers, pressure vessels and lifting machinery. A press, CNC machine or extruder does not, but Selangor by-law 68 still requires the structure to allow at least 20% extra for impact and vibration from installed machinery. New machine foundations or structures inside the building need the council's permission under section 79 of Act 133, and the power supply has to be checked with TNB.
03Does a forklift or a chain block need a DOSH certificate of fitness?+
No. Forklifts are material handling equipment, which the Third Schedule of the 2024 regulations excludes. A chain block is lifting tackle: it needs no certificate, but it must meet a recognised standard and be in good condition. A powered hoist running on a beam is different, because that is a monorail or overhead crane and needs a certificate.
04Is a crane certificate issued under the old Factories and Machinery Act still valid?+
Yes, until it expires. DOSH's FAQ on the repeal says certificates of fitness issued on or before 31 May 2024 remain valid until the end of their term. After that, the crane is inspected under the 2024 regulations and receives a certificate valid for 15 months.
05Who pays for the crane inspection in a rented factory?+
The law puts the duties on the owner or occupier: preparing for the inspection and making the crane available to be tested at its safe working load. Who pays is a matter for the tenancy agreement, so write down who books each inspection, who pays the fee and who pays for repairs if the crane fails. For a 5 ton crane the government fee is RM750 for each inspection.
06Can I move my crane from my old factory to the new one?+
Yes, but it is treated almost like a new installation. You need fresh written approval to install it at the new site, DOSH requires alteration approval for a relocated overhead travelling crane even when its safe working load does not change, and the certificate of fitness ends when the crane is dismantled. The new building's crane beams must also be checked for it.
07What approvals are needed to install large machinery in a factory in Rawang or Shah Alam?+
Up to two: the council's permission for any new structure, and DOSH only if the machine is plant named in the 2024 regulations. Under section 79 of Act 133, new foundations or structures need the council's prior written permission: MPS for Rawang and Kundang, MPHS for Serendah, Sungai Choh, Bukit Beruntung and Batang Kali, MBSA for Shah Alam. DOSH covers only boilers, pressure vessels and lifting machinery, so a press, CNC machine or extruder needs no certificate of fitness, though Selangor by-law 68 still requires the structure to allow for machine impact and vibration.
08Where can I find factories for rent with goods lifts in Rawang, Serendah or Shah Alam?+
They are found in industrial areas across Rawang, Serendah and Shah Alam, but before you rent one, check two things: the lift's DOSH certificate of fitness and the council approval for its shaft. A lift that carries goods only sits in DOSH's hoist category, with a design verification fee of RM300, and the shaft is a structure that needs MPS, MPHS or MBSA approval. Ask the owner for both documents and check the loading of the upper floor where the goods land.
Sources
- DOSH: Occupational Safety and Health (Plant Requiring Certificate of Fitness) Regulations 2024, P.U. (A) 99 (Malay and English text, with the Second, Third, Sixth and Seventh Schedules)
- DOSH Industrial Safety Division: Application Guide for Design Verification and Alteration Approval of Lifting Machinery Other Than Lift, Escalator and Walkalator (2025)
- DOSH: Occupational Safety and Health Act 1994 (Act 514), reprint as at 1 June 2024, sections 27C and 27D
- DOSH: FAQ on the change management for the Factories and Machinery (Repeal) Act 2022 (updated 18 May 2024)
- Selangor Uniform Building By-Laws 1986, updated text including Sel.P.U. 142/2012: by-laws 68 and 69 (KPKT JKT copy)
- Street, Drainage and Building Act 1974 (Act 133), sections 70 and 79 (Perbadanan Putrajaya copy)
- Majlis Perbandaran Selayang: checklist JB-B01(B) for additions and alterations through OSC 3.0
- Majlis Perbandaran Selayang: form JB-D06, application for copies of documents and approved plans
- Majlis Perbandaran Hulu Selangor: downloadable forms (Building Department checklists)
- Majlis Bandaraya Shah Alam: development FAQ (partition walls in commercial and industrial buildings, section 79)
- DOSH MyKKP: competent person and company registration search
Units on the market nearby
Semi-D Factory for Rent in Saujana Teknologi Rawang, Rawang, 6,525 sq ft
RM 10,500/month
Semi-Detached Factory for Sale or Rent in Saujana Rawang, Rawang, 8,000 sq ft
RM 4,000,000 · RM 15,000/month
Detached Factory for Rent in Batu 17 Rawang, 9,000 sq ft
RM 21,000/month
More on power, height, floor and access
- TNB Compact Substation for a Factory in Rawang or Serendah: When You Need One and What to Check
- Pulau Indah Industrial Park (PIIP) Factories on Soft Ground: Piling, Settlement and King Tide Checks
- Factory Handover Checklist and Dilapidation Report: What to Record When You Take Over a Rented Factory in Rawang, Serendah or Shah Alam
- Factory Ceiling Height vs Clear Height in Rawang, Serendah and Shah Alam: What 30 ft, 40 ft, 12 m and 15 m Suit, Racking Levels and Column Spacing