How Can a Factory in Rawang, Serendah or Shah Alam Cut Carbon, Answer International Customers' ESG Requests and Harvest Rainwater?

Written by , PEA 1478 · Published · Power, height, floor and access

Short answer

A factory cuts carbon mainly through its electricity: use less (energy efficiency, which the EECA 2024 requires of sites using 21,600 GJ a year), make its own (rooftop solar under Solar ATAP) and buy green power (TNB's GET). International customers want that data in a standard form, such as Malaysia's SEDG, and detached factories in Selangor must plan rainwater harvesting.

Side of a factory with rooftop solar panels and green downpipes feeding a large rainwater tank beside a landscaped strip.
Illustrative image

Key Takeaways

  • Start with what you can measure: twelve months of TNB bills and fuel invoices. Purchased electricity and fuel are the emissions a factory controls directly, and every customer questionnaire asks for them.
  • The Energy Efficiency and Conservation Act 2024, in force since 1 January 2025, applies to energy consumers using 21,600 GJ or more in twelve consecutive months (about 6 million kWh of electricity): they must appoint a registered energy manager within three months of the Energy Commission's notice.
  • Three levers cut the electricity footprint: use less, generate on the roof under Solar ATAP, and buy certified green electricity through TNB's Green Electricity Tariff, which tenants can now reach through GET Greenpath.
  • International customers want consistent data, not slogans. Capital Markets Malaysia's Simplified ESG Disclosure Guide (SEDG) gives SMEs in supply chains a standard set of disclosures at Basic, Intermediate and Advanced levels.
  • In Selangor, building plans for every detached building with a roof of 100 m² or more must show a rainwater harvesting system (SPAH), and the by-laws set how it is built.

How can a factory reduce its carbon emissions?

Work through the electricity bill in this order.

1. Measure. Collect twelve months of TNB bills, generator and boiler fuel invoices and, if you can, sub-meter the big loads: compressors, chillers, furnaces, lighting. That baseline is also the first thing an energy auditor or a customer asks for.

2. Use less. Energy efficiency usually saves money as well as carbon, and for large users it is now law. Under the Energy Efficiency and Conservation Regulations 2024, an energy consumer is one whose consumption reaches 21,600 GJ in any twelve consecutive months; it must appoint a registered energy manager within three months of the Commission's written notice, and a site above 50,000 GJ needs a more qualified one. The Act also brings an energy management system, yearly reports and energy audits. My arithmetic: 21,600 GJ equals 6 million kWh, so an electricity-only factory paying for more than about 500,000 kWh a month is close to the line. My guide on the TNB tariff for a factory explains how the bill is built, which shows where savings land.

3. Generate on the roof. Under the Energy Commission's Solar ATAP guidelines, in force since 1 January 2026, a non-domestic consumer may install up to 100% of its maximum demand, capped at 1,000 kW, for a ten-year programme period, with surplus exports credited at the average system marginal price. Whether a particular roof suits panels, and what a tenant needs from the landlord, are covered in my guides on solar on a factory roof and on generators, solar and other installations at a factory.

4. Buy green electricity for the rest. TNB's Green Electricity Tariff lets a customer pay a premium, from as low as 3 sen/kWh on a three-year subscription, for electricity backed by Malaysia Renewable Energy Certificates (mRECs). Since 1 August 2025 the GET Greenpath programme has opened the same route to non-domestic users who are not registered directly with TNB, such as tenants on a landlord's bulk account. Subscription depends on the quota available.

How can a factory meet the ESG requirements of international customers?

When a multinational customer sends a supplier questionnaire, it is usually asking for the same few things: energy use and emissions, water and waste, workers' conditions, and basic governance. The fastest way to answer consistently is to use a recognised local template. Capital Markets Malaysia's Simplified ESG Disclosure Guide (SEDG) was released in October 2023 for SMEs in supply chains; Version 2 supersedes Version 1 with three additional disclosures, groups them into Basic, Intermediate and Advanced levels, and is aligned with the ASEAN guide launched in April 2025. A Simplified Chinese version and a disclosure template are available.

The data behind the answers comes from the factory itself, so I tell clients to keep these files in one place:

ESG area What the customer asks Where the evidence comes from
Energy and emissions kWh, fuel, emissions, renewable share TNB bills, fuel invoices, Solar ATAP contract, GET or mREC records
Water and effluent Water use, discharge compliance Air Selangor bills, effluent records; my factory wastewater guide
Waste Scheduled waste handling DOE scheduled waste records and consignment notes
Workers Housing, hours, safety Worker accommodation certificates; my guide on hiring workers and worker hostels
Building Fire safety, approvals CCC, fire certificate, council licence

The building you choose decides some of these numbers for years: a roof that can carry solar, a supply that fits your load, and a landlord willing to sign off on improvements. My guide on China Plus One and green factories covers why multinational buyers now look at these points.

How can a factory carry out rainwater harvesting?

In Selangor it is partly a legal requirement for new buildings. The Selangor Uniform Building By-Laws, as amended by Sel.P.U. 40/2012, require building plans to show the rainwater harvesting and utilisation system (SPAH), including piping, tank and pumps, for all detached buildings with a roof area of 100 m² or more, so a new detached factory must include one. By-law 115 sets the construction rules:

  • rainwater must not flow into the public water tank; mains water may top up the rainwater tank only through a one-way non-return valve, or with the rainwater tank's overflow at least 225 mm below the inlet;
  • the SPAH outlet and rainwater tank must be marked "Not For Drinking or Bathing";
  • gutters need enough slope to avoid stagnant water; and
  • rainwater pipes must be green.

For an existing factory, a retrofit follows the same logic: gutters and downpipes into a tank on the ground or a raised stand, a first-flush diverter and filter, and a separate pump and pipe network for non-drinking uses such as toilet flushing, landscape watering and yard washing. Check that the roof sheets are not asbestos cement before collecting from them, and that the tank's weight sits on ground or a slab that can take it. If the factory's mains pressure is the real problem, my guide on low water pressure in a factory covers storage and pumps.

What do I check on a factory for a client with ESG targets?

  • Twelve months of TNB bills: maximum demand, tariff and supply voltage, which also set the Solar ATAP limit.
  • The roof: structure, remaining life, material and shading.
  • Whether the unit has its own TNB account or sits on a landlord's bulk account, which decides whether Solar ATAP or GET Greenpath applies.
  • Water meter size, drainage and space for a rainwater tank.
  • The landlord's written consent for solar, meters and tanks before the tenancy is signed.

If you need a factory in Rawang, Serendah, Kundang or Shah Alam that fits your customers' ESG requirements, WhatsApp Jason Low, Probationary Estate Agent PEA 1478 with CID Realtors Sdn Bhd E(1) 1855, on +60 12-288 1834.

Questions people ask

01How can a factory reduce carbon emissions?+

Measure twelve months of electricity and fuel, then use less energy, generate on the roof under Solar ATAP and buy certified green electricity through TNB's Green Electricity Tariff for the rest. Sites using 21,600 GJ or more a year must also appoint a registered energy manager under the EECA 2024.

02Does the Energy Efficiency and Conservation Act 2024 apply to my factory?+

It applies to energy consumers using 21,600 GJ or more in twelve consecutive months, which is about 6 million kWh of electricity. Such a consumer must appoint a registered energy manager within three months of the Energy Commission's written notice and keep an energy management system, reports and audits.

03How can a factory meet the ESG requirements of international customers?+

Answer questionnaires from your own records using a recognised template such as Capital Markets Malaysia's SEDG, which sets Basic, Intermediate and Advanced disclosures for SMEs in supply chains. Keep TNB bills, fuel invoices, water and effluent records, scheduled waste records, worker housing certificates and building approvals in one place.

04Can a tenant buy green electricity for a rented factory?+

Yes. TNB's GET Greenpath, open since 1 August 2025, lets non-domestic users who are not registered directly with TNB, such as tenants on a landlord's bulk account, obtain green electricity backed by mRECs. Subscription depends on the quota available.

05Is rainwater harvesting compulsory for a factory in Selangor?+

For new detached buildings with a roof area of 100 m² or more, yes: the Selangor building by-laws require the SPAH to be shown on the building plans. Terrace and semi-detached factories are not named in that category.

06How do you build a rainwater harvesting system for a factory?+

Collect from the roof through gutters with enough slope into a tank, add a first-flush diverter and filter, and pump to non-drinking uses. Keep rainwater out of the public water tank, mark outlets Not For Drinking or Bathing and use green rainwater pipes, as by-law 115 requires.

Sources

  1. Energy Commission: Energy Efficiency and Conservation Act 2024 (Act 861)
  2. Energy Efficiency and Conservation Regulations 2024 (P.U.(A) 466/2024): 21,600 GJ threshold, registered energy manager
  3. Energy Commission: EECA 2024 page (in force 1 January 2025)
  4. Energy Commission: Guidelines for Solar ATAP (GP/ST/No. 60/2025)
  5. TNB: Green Electricity Tariff (GET) and GET Greenpath
  6. Capital Markets Malaysia: Simplified ESG Disclosure Guide (SEDG) for SMEs in Supply Chains
  7. Selangor Uniform Building By-Laws 1986, updated text including Sel.P.U. 40/2012 (SPAH, by-law 115)

Units on the market nearby

More on power, height, floor and access

All guides: Power, height, floor and access →

Probationary Estate Agent · PEA 1478 · CID Realtors Sdn Bhd E(1) 1855About Jason → · Contact →
Ask Jason about this