Can a Factory Install a Backup Generator, Solar, EV Chargers, a Large Water Tank or Business Fibre? Rules and Consents in Rawang, Serendah and Shah Alam

Written by , PEA 1478 · Published · Licences, Bomba and approvals

Short answer

Yes, a factory can install a backup generator, a large water tank, business fibre, EV chargers and rooftop solar. Each needs its own approval: the Energy Commission for generators, chargers and Solar ATAP, the DOE for larger generators, the water rules for tanks, and the landlord's written consent in a rented unit.

A single-storey factory with solar panels on its roof, a generator enclosure, a steel water tank on a plinth and two EV chargers at parking bays.
Illustrative image

Key Takeaways

  • Yes, a factory can have a backup generator, a large water tank, business fibre, EV chargers and rooftop solar, but each one brings its own regulator and, in a rented unit, needs the landlord's written consent first.
  • A generator above 5 kW falls outside the Energy Commission's 1994 licence exemption, and a standby set burning more than 15 kg of liquid fuel an hour needs a written notification to the Department of Environment (DOE) before installation work starts.
  • A large storage tank follows the Water Services Industry (Water Reticulation and Plumbing) Rules 2014: a certified foundation, compartments above 10 cubic metres, and plumbing plans lodged by a competent person.
  • EV chargers must be wired by an Energy Commission competent person on a dedicated circuit, using Mode 2, 3 or 4 equipment with an Energy Commission certificate of approval or release letter.
  • A tenant who holds the factory's own TNB account can apply for Solar ATAP; a multi-tenant premises cannot. The ATAP period of operation is at most 10 years, so match it to the tenancy.

Can a factory install a backup generator?

Yes, and many do, but a generator is a licensed and notified installation, not just a piece of equipment. Three sets of rules apply.

The Energy Commission (Suruhanjaya Tenaga). Under the Electricity Supply (Exemption) Notification 1994, P.U.(B) 156/1994, only an installation whose own generator is 5 kW or less is exempt from the licence requirement. The same notification does not exempt an installation that has a generator connected to provide standby supply from registration, and anyone who works or operates an installation generating more than 5 kW needs a competency certificate. The Energy Commission's guidelines on licence applications (GP/ST/No. 52/2024) list a diesel generator for own consumption as a private installation activity and recommend applying about three months before the installation starts operating.

The Department of Environment. The Environmental Quality (Clean Air) Regulations 2014 bar any work that may create a new source of emission without prior written notification to the Director General (regulation 5). DOE's guidance document for fuel burning equipment says that all generators, including standby generators, consuming more than 15 kg per hour of liquid fuel need written notification before installation work starts, and that DOE reviews both the exhaust emission and the noise level.

Noise and neighbours. A generator test run at night is the complaint I hear most about from factory neighbours. My guide to 24-hour factory noise limits explains the DOE limits a set has to meet at the boundary.

What I check on a viewing: whether the unit already has a generator, its kVA rating, whether it has an automatic changeover switch, where the exhaust points, and whether there is space on the lot for an enclosure without blocking the fire engine access or the loading bay.

Can a factory install a large water storage system?

Yes. A bigger tank is usually the lawful fix when the public supply cannot keep up with production, but the tank itself has to follow the Water Services Industry (Water Reticulation and Plumbing) Rules 2014:

  • Plans first. The owner appoints a competent person to prepare the internal plumbing plans and lodge them with the water commission before the fittings go in (rule 31), and new or altered fittings are disinfected before use (rule 32).
  • A certified foundation. The foundation of a storage cistern must be certified by a competent person as safe for its operating load (rule 47). Water weighs about one tonne per cubic metre, so a large tank on an old slab or on the roof needs an engineer's check; see my guide on factory floor loading.
  • Compartments and access. A cistern larger than 10 cubic metres must be compartmentalised, placed in a secured area and lined if built from concrete or steel panels (rule 49). A tank buried in the ground must be a reinforced concrete water retaining structure, above flood and groundwater level, and pass a water tightness test (rule 47).
  • Fire water is separate. Supply to private fire hydrants and other fire fighting devices must be separately metered (rule 81), and the sprinkler or hydrant tank is designed with your Bomba requirements in mind.

How big the tank should be, the one or two days of storage the Rules set, and why a pump must draw from a tank and never straight off the main are covered in my guide on low water pressure in a factory.

Can a factory get high-speed enterprise internet?

Usually yes, and a tenant can contract the line in its own company name. The question is what the provider can actually deliver to that lot. MCMC's JENDELA map lets you check fixed and wireless broadband coverage for an area and send feedback to MCMC; the JENDELA Phase 1 report records 7.74 million premises with access to fibre by 31 December 2022, so fibre is common but not universal, and newer or more remote industrial lots in the north can still be waiting for it.

How I handle it for a client: before signing, the tenant asks two or three providers for a business fibre quotation for the exact lot, not the street. If the fibre has to be pulled from the road, the agreement should say who allows the trenching or overhead cabling across the landlord's land, who pays, and whether the cabling may stay at the end of the tenancy. Inside the building, drilling walls and running trunking for a server room is an alteration like any other.

Can a factory install an EV charging station?

Yes, within the Energy Commission's Guidelines on Electric Vehicle Charging System (GP/ST/No. 54/2025), dated 24 February 2025:

  • Wiring by a competent person. All electrical wiring for the charger is carried out by the relevant competent person, and each charger or EV socket outlet runs on its own dedicated final circuit.
  • Approved equipment only. Mode 1 charging is not allowed. Mode 2 and Mode 3 equipment needs an Energy Commission certificate of approval, and Mode 4 (DC) a release letter. Enclosures need at least IP41 indoors and IP44 outdoors.
  • A licence when it is a charging business. Anyone carrying out an activity under section 9(1) of the Electricity Supply Act in relation to EV charging needs a licence. The Energy Commission's licence criteria for EV charging require the application to come from a charge point operator, supported by local authority approval or a consent letter from the owner or management of the building, with a dedicated supply from the distribution licensee.

TNB's customer guide on EV chargers adds that the installer must be an Energy Commission registered competent person or contractor and the wall box approved and labelled under ST-SIRIM. For a factory, the real limit is often the electricity supply: several fast chargers add to the maximum demand, which may push the unit into a supply upgrade, as explained in kVA, amps and TNB upgrades.

Can I install solar on a rented factory?

Yes, if you hold the factory's TNB account and the landlord agrees in writing. The Energy Commission's Guidelines for Solar ATAP (GP/ST/No. 60/2025), in operation from 1 January 2026, define a consumer as "an owner or occupier of a premise" supplied by the utility, so a tenant with its own TNB account can apply. What rules a unit out:

  • Multi-tenant premises. A building where the landlord and several tenants each have their own supply is excluded, and so is a consumer who is also a generator, such as a co-generator.
  • Panels must stay on the premise. Panels go on the rooftop of buildings within the same premise, or on a solar car park or covered walkway in the same compound.
  • Capacity follows your maximum demand. For non-domestic consumers the inverter output may not exceed 100% of maximum demand (the 12-month average, or the declared figure for a new account), capped at 1,000 kW, and SEDA's Solar ATAP page shows that systems above 72 kW need a connection assessment study. Exported surplus earns bill credits at the average system marginal price, not the full tariff.
  • The period is at most 10 years. If the consumer moves, it may apply to continue at the new premise for the remaining period under a new contract; if the factory is sold, the new owner may apply to continue.

The roof still belongs to the landlord, so I ask for written consent covering the roof's condition and remaining life, who repairs leaks around the mountings, insurance, and whether the panels are removed or left at the end. A tenancy shorter than the payback period is the usual reason a tenant's solar plan does not work. For owners, how solar affects the sale is in selling a factory with a tenant or vacant, and the tariff side in my TNB tariff guide for factories.

Is it worth installing solar on a factory?

It pays where the factory uses most of the power itself during daylight, because under Solar ATAP every unit used on site replaces power bought at your tariff, while surplus sent to the grid only earns bill credits at the average system marginal price. A plant running machines or cold rooms through the day fits that pattern; a warehouse that draws little power by day does not. When a client asks me, I set four things side by side before any installer's payback figure:

  1. Daytime load. Twelve months of TNB bills and the daily load pattern show how much solar output would be used on site.
  2. The size cap. For non-domestic consumers the inverter may not exceed 100% of maximum demand, capped at 1,000 kW, so a small maximum demand limits the system.
  3. Time left on site. Solar ATAP runs for at most 10 years; a tenancy, or a plan to sell, that ends well before the installer's payback period is the usual reason it does not pay for a tenant.
  4. The roof. A roof near the end of its life should be replaced before panels go on, or the panels have to come off again for the repair; my used factory inspection guide covers roof life.

Ask each installer to base its payback on your own bills and the Solar ATAP export rate, not on the full tariff for every unit generated.

What should the tenancy agreement say before any of these goes in?

Every one of these five is an alteration or an addition to the landlord's building. When a tenant plans one, I ask both sides to put five points in writing before work starts:

  1. Consent and drawings. What exactly is installed, where, and that the landlord has seen the drawings or the contractor's proposal.
  2. Approvals. The tenant obtains and pays for the Energy Commission, DOE, water and council approvals it needs, and gives the landlord copies.
  3. Who owns it at the end. Whether the generator, tank, chargers or panels are removed, left without payment, or bought by the landlord at an agreed value.
  4. Reinstatement. What condition the roof, walls and slab must be returned in; my renovation and reinstatement guide shows how to word it.
  5. Maintenance, insurance and records. Who services the equipment, who insures it, and who keeps the test reports. Repair duties in general are in who pays for repairs in a rented factory.

Agreed early, these points often help the rent talks, because the tenant is improving the building at its own cost.

If you are looking at a factory in Rawang, Serendah or Shah Alam and need a generator, solar, EV chargers, more water storage or business fibre, WhatsApp Jason Low, Probationary Estate Agent PEA 1478 with CID Realtors Sdn Bhd E(1) 1855, on +60 12-288 1834.

Questions people ask

01Does a factory backup generator need an Energy Commission licence?+

A generator above 5 kW is outside the 1994 exemption from licensing, so it needs a private installation licence from the Energy Commission, which recommends applying about three months before the set starts operating. An installation with a standby generator connected is also not exempt from registration, and whoever operates it needs a competency certificate.

02Do I need to notify the DOE before installing a generator?+

Yes, if it burns more than 15 kg of liquid fuel an hour. DOE's guidance says every such generator, standby sets included, needs a written notification under the Clean Air Regulations 2014 before installation work starts, and DOE looks at both the exhaust and the noise.

03Can a tenant install solar panels on a rented factory?+

Yes, if the tenant holds the factory's own TNB account and the landlord consents in writing. Solar ATAP defines a consumer as an owner or occupier, but it excludes multi-tenant premises, and the period of operation is at most 10 years, so the tenancy should run long enough to recover the cost.

04Who can install an EV charger at a factory?+

Only an Energy Commission competent person or registered contractor, on a dedicated final circuit, using Mode 2, 3 or 4 equipment with an Energy Commission certificate of approval or release letter. Selling charging to others is a licensed activity applied for by a charge point operator with the building owner's consent.

05What approvals does a large water tank at a factory need?+

A competent person lodges the internal plumbing plans with the water commission before installation, and the tank foundation must be certified by a competent person. Tanks above 10 cubic metres must be compartmentalised, and buried tanks must be reinforced concrete and pass a water tightness test.

06How do I check if a factory lot has fibre internet?+

Check the area on MCMC's JENDELA map, then ask two or three providers to quote a business fibre line for the exact lot. If cabling has to cross the landlord's land, agree in the tenancy who allows it, who pays and whether it stays at the end.

Sources

  1. Suruhanjaya Tenaga: exemptions under the Electricity Supply (Exemption) Notification 1994, P.U.(B) 156/1994
  2. Suruhanjaya Tenaga: Guidelines on Licence Application under section 9 of the Electricity Supply Act 1990 (GP/ST/No. 52/2024)
  3. Department of Environment: Environmental Quality (Clean Air) Regulations 2014, P.U. (A) 151
  4. Department of Environment: Guidance Document for Fuel Burning Equipment and Air Pollution Control Systems (2015), generator section
  5. Water Services Industry (Water Reticulation and Plumbing) Rules 2014, P.U. (A) 36
  6. MCMC: JENDELA map, fixed and wireless broadband coverage
  7. MCMC: JENDELA Phase 1 (2020 to 2022) Concluding Report
  8. Suruhanjaya Tenaga: Guidelines on Electric Vehicle Charging System (GP/ST/No. 54/2025)
  9. Suruhanjaya Tenaga: Criteria and Documents Required for Licence Application, EVCS (December 2023)
  10. TNB: Customer Guide, Before You Install an EV Home Charger
  11. Suruhanjaya Tenaga: Guidelines for Solar Accelerated Transition Action Programme (Solar ATAP), GP/ST/No. 60/2025
  12. SEDA Malaysia: Solar ATAP eligibility, capacity limits and technical studies

Units on the market nearby